Registered Litigation declared Others project

Sunteck OneWorld -Tower 1

By Sunteck Realty Limited

RG-MH-32524 · RERA P99000080341 · Last updated on MahaRERA portal: 4 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Apr 2031Possession promisedmoved 28 months from the original
1 of 11Construction stages donefurthest along: Plinth, 50%
183 of 183Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Sunteck OneWorld -Tower 1 is a Others project by Sunteck Realty Limited in Palghar, Maharashtra, registered with MahaRERA as P99000080341 on 26 May 2025. Possession is promised by 30 Apr 2031. The completion date has moved by 28 months from the original filing. 0 of the 183 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameSunteck OneWorld -Tower 1
  • TypeOthers
  • Location
    • Naigaon East Vasai Link road
    • Tivari
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • RERA no.P99000080341
  • ReraGenie IDRG-MH-32524

Builder

  • NameSunteck Realty Limited
  • Entity typeCompany
  • CINL32100MH1981PLC025346
  • GSTIN27AAACI0336E1Z3
  • Company SecretaryRachana Vipul Hingarajia
  • Other registrations24 more →
  • Completed10 of 25
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredMay 2025First promiseDec 2028Revised toApr 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 May 2025
  • Promised completion30 Apr 2031
  • Revised completionRevised to 30 Apr 2031 (originally 31 Dec 2028)
  • Buildings1 building record
  • Documents filed60 files

Current status

0%0 of 183 units booked
4.9%Work done, per cost certificate

Figures as on 4 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Plot No 2 Sector -I Tower 1NA252317112183

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Plinth, at 50%.

Plot No 2 Sector -I Tower 1: 14% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed81

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots81
Closed/Covered3
Open Space78

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,530 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Jul 2026
LandownerVillageDistrict
DDPL GLOBAL INFRASTRUCTURE PRIVATE LIMITEDKandivaliMumbai Suburban
UNICORN INFRAPROJECTS AND ESTATES PRIVATE LIMITEDKandivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityVasai Virar City Municipal Corporation (VVCMC)
Permissible FSI12000.0
Proposed, not sanctioned11,609 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, AXIS HOUSE,BOMBAY DYEING MILL COMPOUND,PANDURANG BUDHKAR MARG,WORLI, MUMBAI - 400 025
Estimated costRs 42.62 cr
Cost incurredRs 2.10 cr
Work done4.93%
BuildingWingEstimatedIncurred
Plot No 2 Sector -I Tower 1NARs 33.00 crRs 2.10 cr
-NARs 9.62 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPractice Design Pvt. Ltd
EngineerSameer Kotkar
EngineerRaju HJ
EngineerGul Ghanshyam Mirani
Chartered AccountantWalker Chandiok & Co LLP
Chartered AccountantJhanwar & Maheshwari Chartered Accountants
Chartered AccountantJhanwar & Maheshwari
PartnerRole in project
Sunteck Realty Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA28012619602Dec 2028 → Dec 2030

Reason as filed by the promoter1. The consent of 51% of allottees could not be obtained as there are no sold units as on date. 2. Form B uploaded 3. PERT Chart for the remaining completion work is uploaded in the Application. 4. The Project got delayed due to following reasons: a) Commencement certificate was issued on 16 February 2024 b) Promoter decided to modify the sanctioned plans c) Obtaining approval of revised plans delayed completion further. d) Therefore for completion of project in realistic timeline the promoter seeks advanced Extension of the project 5. We hereby assure the Hon’ble Authority that the project sh

P99000080341/WarDec 2028 → Apr 2031

Reason as filed by the promoterNA

Litigation declared1

CaseCourtStatus
127 of 2019/2019NCLTOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2031

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: 2026 03 Annexure A-Form 2A-QUALITY ASSURANCE ONEWorld Tower 1.pdf4 Sep 2026
Withdrawal Update Form 1File: Form 1 ARCHITECTS CERTIFICATE SOW-Tower 1_June-26.pdf23 Jul 2026
Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE SOW-Tower 1_June-26.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 CA CERTIFICATE SOW-Tower 1_June-26.pdf23 Jul 2026
Withdrawal Update Form 1File: Form 1 ARCHITECTS CERTIFICATE SOW-Tower 1_Mar-26.pdf25 Apr 2026
Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE SOW-Tower 1_Mar-26.pdf25 Apr 2026
Withdrawal Update Form 3File: Form 3 CA CERTIFICATE SOW-Tower 1_Mar-26.pdf25 Apr 2026
Withdrawal Update Form 1File: Form 1 ARCHITECTS CERTIFICATE SOW-Tower 1_Dec-25.pdf23 Jan 2026
Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE SOW-Tower 1_Dec-25.pdf23 Jan 2026
Withdrawal Update Form 3File: Form 3 CA CERTIFICATE SOW-Tower 1_Dec-25.pdf23 Jan 2026
Withdrawal Update Form 1File: Form 1 ARCHITECTu0027S CERTIFICATE SOW-Tower 1_Sep-25.pdf31 Oct 2025
Withdrawal Update Form 1File: Form 1 ARCHITECTu0027S CERTIFICATE SOW-Tower 1_Sep-25.pdf31 Oct 2025
Withdrawal Update Form 1File: Form 1 ARCHITECTu0027S CERTIFICATE SOW-Tower 1_June-25.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2 ENGINEERu0027S CERTIFICATE SOW-Tower 1_Sep-25.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2 ENGINEERu0027S CERTIFICATE SOW-Tower 1_Sep-25.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2 ENGINEERu0027S CERTIFICATE SOW-Tower 1_June-25.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3-CA CERTIFICATE SOW-Tower 1_Sep-25.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3-CA CERTIFICATE SOW-Tower 1_Sep-25.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3-CA CERTIFICATE SOW-Tower 1_June-25.pdf31 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-Tower 1 Revised.pdf23 May 2025
Other - TechnicalFile: Additional Plot Area Payment.pdf13 May 2025
Declaration in FORM BFile: Form B Sunteck ONEWorld Tower 1.pdf5 May 2025
Commencement Certificates / NA Order for plotted developmentFile: Revised CC Letter.pdf5 May 2025
Declaration about Commencement CertificateFile: Format D- SOW T-1.pdf5 May 2025
Layout approvalFile: Sunteck One World P1 Layout.pdf7 Apr 2025
Copy of Layout Approval (in case of layout)File: Sunteck One World P1 Layout.pdf7 Apr 2025
Building plan approvalFile: Sunteck One World T1 Page 1.pdf31 Mar 2025
Building plan approvalFile: Sunteck One World T1 Page 2.pdf31 Mar 2025
Building plan approvalFile: Sunteck One World T1 Page 3.pdf31 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Sunteck One World T1 Page 1.pdf31 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Sunteck One World T1 Page 2.pdf31 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Sunteck One World T1 Page 3.pdf31 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Veification Mail.pdf31 Dec 2024
Proforma of Agreement for saleFile: 21 12 2024 OneWorld AFS Sunteck - final upload (1).pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 2024 08 28_SRL RERA BR.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Vaddarse Shetty 00021773.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Sandhya Malhotra 06450511.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Mukesh Jain 01316027.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: KK 00017527.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Chaitanya Dalal 00185847.pdf31 Dec 2024
Other - TechnicalFile: ANNEXURE 'A' Declaration cum Undertaking One plot one registration SOW T-1 RERA Vision.pdf20 Dec 2024
Deviation Report with respect to model copy of AgreementFile: 2024 12 20 SOW AFS- DEVIATION REPORT_compressed.pdf20 Dec 2024
Copy of the legal title reportFile: Title ReportRevise.pdf19 Dec 2024
Other - TechnicalFile: Declaration of plot area SOW Tower 1.pdf19 Dec 2024
Details of encumbrances concerned to FinanceFile: DECLARATION REGARDING Financial ENCUMBRANCES SOW T-1.pdf18 Dec 2024
CERSAI detailsFile: DECLARATION REGARDING CERSAI REPORT SOW T-1.pdf18 Dec 2024
Details of encumbrances concerned to LegalFile: DECLARATION REGARDING Financial ENCUMBRANCES SOW T-1.pdf18 Dec 2024
Other - TechnicalFile: Declaration regarding clarification on the Plot Area .pdf18 Dec 2024
Proforma of Allotment letterFile: 12- 12 2024 Proforma allotment letter.pdf17 Dec 2024
Deviation Report with respect to Allotment letterFile: 12 12 2024 Allotment letter - deviation.pdf17 Dec 2024
PAN CardFile: Pancard.pdf16 Dec 2024
Details of encumbrances concerned to FinanceFile: Encumbrance concerned to Legal SOW T-1.pdf16 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf16 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf16 Dec 2024
Details of encumbrances concerned to LegalFile: Encumbrance concerned to Legal SOW T-1.pdf16 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations RH.pdf16 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format-B.pdf16 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured -unsecured finance available for project SOW T-1.pdf16 Dec 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Sunteck GrandeurSunteck Grandeur 42 S. V. Road near Andheri Subway Andheri West Mumbai 400 05720CompletedMar 2013Late, Jul 2014
Sunteck CentreSunteck Centre 37-40 Subhash Road Vile Parle East Mumbai 40005715CompletedSep 2009Late, Dec 2009

How this compares with Palghar

0%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 28 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sunteck OneWorld -Tower 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tivari3,200+ in Palghar

Builder: Sunteck Realty Limited

Sunteck Realty Limited has 25 registrations on MahaRERA, including Sunteck City Avenue 1 and Sunteck City Avenue 2. Its filings disclose 6 earlier MahaRERA projects: declares 4 of 6 past projects completed on time. Litigation is declared on 12 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Sunteck OneWorld -Tower 1 is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sunteck OneWorld -Tower 1?

The registered promoter entity is Sunteck Realty Limited, a company as per the filing. Its CIN L32100MH1981PLC025346 and GSTIN 27AAACI0336E1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sunteck OneWorld -Tower 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sunteck OneWorld -Tower 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sunteck OneWorld -Tower 1?

The professionals named in the filing: Architect: Practice Design Pvt. Ltd; Engineer: Sameer Kotkar; Engineer: Raju HJ; Engineer: Gul Ghanshyam Mirani; Chartered Accountant: Walker Chandiok & Co LLP; Chartered Accountant: Jhanwar & Maheshwari Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sunteck OneWorld -Tower 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sunteck OneWorld -Tower 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sunteck OneWorld -Tower 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.