Home / Browse projects / Palghar, Maharashtra / Sunteck ONEWorld 3, Tivri, Naigaon East
Sunteck ONEWorld 3, Tivri, Naigaon East
RG-MH-89476 · RERA P99000033099 · Last updated on MahaRERA portal: 24 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- 1 complaint at MahaRERA
- Completion date moved by 36 months
- 1 extension taken
- Rs 300.00 crore secured on the land, in favour of Axis Bank
Clear
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sunteck ONEWorld 3, Tivri, Naigaon East is a Others project by Sunteck Realty Limited in Palghar, Maharashtra, registered with MahaRERA as P99000033099 on 9 Feb 2022. Possession is promised by 31 Dec 2029. The completion date has moved by 36 months from the original filing. 184 of the 350 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSunteck ONEWorld 3, Tivri, Naigaon East
- TypeOthers
- Location
- Tivari
- Vasai
- Palghar
- 401208
- Pincode401208
- RERA no.P99000033099
- ReraGenie IDRG-MH-89476
Builder
- NameSunteck Realty Limited
- Entity typeCompany
- CINL32100MH1981PLC025346
- GSTIN27AAACI0336E1Z3
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Company SecretaryRachana Vipul Hingarajia
- Other registrations24 more →
- Completed10 of 25
- No longer live3 lapsed, de-registered or revoked
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Feb 2022
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2026)
- Buildings2 building records
- Documents filed93 files
Current status
Figures as on 24 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 5 | NA | 24 | 23 | 171 | 0 | 171 |
| Tower 6 | NA | 24 | 23 | 179 | 0 | 179 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 79%.
Tower 528%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 4% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Tower 635%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 79% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 3% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 85% |
| Solid Waste Management And Disposal | Yes | 85% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed6
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Tower 5 | 3 | 3 |
| Tower 6 | 3 | 3 |
Land and ownership2
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| DDPL GLOBAL INFRASTRUCTURE PRIVATE LIMITED | Borivali | Mumbai Suburban |
| UNICORN INFRAPROJECTS AND ESTATES PRIVATE LIMITED | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower 5 | NA | Rs 30.64 cr | Rs 14.50 cr |
| Tower 6 | NA | Rs 30.64 cr | Rs 14.50 cr |
| - | NA | Rs 16.76 cr | Rs 14.09 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Practice Design Pvt. Ltd |
| Engineer | Raju HJ |
| Engineer | Gul Ghanshyam Mirani |
| Chartered Accountant | Jhanwar & Maheshwari |
| Chartered Accountant | Walker Chandiok & Co LLP |
| Partner | Role in project |
|---|---|
| Sunteck Realty Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per order of the Hon'ble Chairman (MahaRERA) Dated 27/07/2026, we request you kindly to grant us extension till 31/12/2029.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 127 of 2019/2019 | NCLT | Pending |
| 127 of 2019/2019 | National Company Law Tribunal | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12604359 | Sachin Nagji Shah | Sunteck Realty Limited | 13/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jan 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed93
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 ARCHITECTS CERTIFICATE SOW 3_June-26.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE SOW 3_June-26.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA CERTIFICATE SOW 3_June-26.pdf | 24 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 ARCHITECTS CERTIFICATE SOW 3_Mar-26.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE SOW 3_Mar-26.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: Form 3 CA CERTIFICATE SOW 3_Mar-26.pdf | 8 May 2026 |
| Withdrawal Update Form 1File: Form 1 ARCHITECTS CERTIFICATE SOW 3_Dec-25.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 ENGINEERS CERTIFICATE SOW 3_Dec-25.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA CERTIFICATE SOW 3_Dec-25.pdf | 3 Feb 2026 |
| Form 2A (FY 2021-2022)File: 2022 03 Annexure C-Form 2A-QUALITY ASSURANCE ONEWorld 3.pdf | 17 Dec 2025 |
| Form 2A (FY 2025-2026)File: 2025 03 Annexure C-Form 2A-QUALITY ASSURANCE ONEWorld 3.pdf | 17 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 ARCHITECTu0027S CERTIFICATE SOW 3_Sep-25.pdf | 4 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 ENGINEERu0027S CERTIFICATE SOW 3_Sep-25.pdf | 4 Nov 2025 |
| Withdrawal Update Form 3File: Form 3-CA CERTIFICATE SOW 3_Sep-25.pdf | 4 Nov 2025 |
| Form 5 (FY 2024-2025)File: 2024-25_Form 5-CA CERTIFICATE ANNUAL REPORT SOW 3_2024-25.pdf | 24 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 ARCHITECTu0027S CERTIFICATE SOW 3_June-25.pdf | 21 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 ENGINEERu0027S CERTIFICATE SOW 3_June-25.pdf | 21 Aug 2025 |
| Withdrawal Update Form 3File: Form 3-CA CERTIFICATE SOW 3_June-25.pdf | 21 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT'S CERTIFICATE SOW 3_Mar-25.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW 3_Mar-25 Compress.pdf | 25 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGINEER'S CERTIFICATE SOW 3_Mar-25.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT'S CERTIFICATE SOW 3_Jan-25.pdf | 23 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Jan-25 Compres.pdf | 23 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGINEER'S CERTIFICATE SOW 3_Jan-25.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Oct-24.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Oct-24.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Oct-24.pdf | 28 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: One world 3.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_June-24.pdf | 29 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_June-24.pdf | 29 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_June-24.pdf | 29 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Mar-24.pdf | 29 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Mar-24.pdf | 29 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2024 03 Annexure C-Form 2A-QUALITY ASSURANCE ONEWorld 3.pdf | 29 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Mar-24.pdf | 29 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Jan-24.pdf | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Jan-24.pdf | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Jan-24 Compress.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Sep-23.pdf | 1 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Sep-23.pdf | 1 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Sep-23.pdf | 1 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: One World 3.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_June-23.pdf | 23 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_June-23.pdf | 23 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_June-23 Compress.pdf | 23 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Annexure C-Form 2A-QUALITY ASSURANCE ONEWorld 3-02_Mar-23.pdf | 9 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Mar-23.pdf | 29 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Mar-23.pdf | 29 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Mar-23.pdf | 29 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Jan-23.pdf | 23 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Jan-23.pdf | 23 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Jan-23.pdf | 23 Jan 2023 |
| Details of encumbrancesFile: 2022 12 23 Encumbrance Certificate ONEWorld 3.pdf | 31 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ARCHITECT'S CERTIFICATE SOW-3_Oct-22.pdf | 14 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-ENGINEER'S CERTIFICATE SOW-3_Oct-22.pdf | 14 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-CA CERTIFICATE SOW-3_Oct-22.pdf | 14 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-CA CERTIFICATE ANNUAL REPORT SOW 3_2021-22.pdf | 30 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Sunteck ONEWorld 1_July-22.pdf | 9 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Sunteck ONEWorld 3_July-22.pdf | 9 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate ONEWorld 3_July-22.pdf | 9 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2022 07 Form 3-CA Certificate SOW3_July-22.pdf | 9 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Sunteck ONEWorld 3.pdf | 16 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate ONEWorld 3.pdf | 16 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: -QUALITY ASSURANCE ONEWorld 3-01_Mar-22.pdf | 16 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2022 03 Form 3-CA Certificate SOW3_Mar-22.pdf | 16 Apr 2022 |
| Details of encumbrancesFile: Encumbrance Certificate ONEWorld 3.pdf | 31 Jan 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE ONEWorld 3.pdf | 31 Jan 2022 |
| Declaration in FORM BFile: Affidavit cum-Declaration Sunteck ONEWorld 3.pdf | 31 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B-Form 2-Engineer Certificate ONEWorld 3.pdf | 31 Jan 2022 |
| Proforma of Allotment letterFile: Alloment Letter and AFS SOW - 3.pdf | 31 Jan 2022 |
| Layout approvalFile: 2021 12 31 RDP Naigaon Phase III.pdf | 29 Jan 2022 |
| Layout approvalFile: Layout plan 01 of 02.pdf | 29 Jan 2022 |
| Building plan approvalFile: 2021 12 31 RDP Naigaon Phase III.pdf | 29 Jan 2022 |
| Building plan approvalFile: Layout plan 01 of 02.pdf | 29 Jan 2022 |
| PAN CardFile: PAN Card.pdf | 29 Jan 2022 |
| Copy of the legal title reportFile: DDPL RERA TITLE - Legal Title Report-compressed.pdf | 29 Jan 2022 |
| Copy of the legal title reportFile: DDPL RERA TITLE - Flow of the Title 01.pdf | 29 Jan 2022 |
| Copy of the legal title reportFile: DDPL RERA TITLE - Search Report-compressed.pdf | 29 Jan 2022 |
| Details of encumbrancesFile: Encumbrance certificate Owner Sunteck ONEWorld.pdf | 29 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: 2021 12 31 RDP Naigaon Phase III.pdf | 29 Jan 2022 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Sunteck Grandeur | Sunteck Grandeur 42 S. V. Road near Andheri Subway Andheri West Mumbai 400 057 | 20 | Completed | Mar 2013 | Late, Jul 2014 |
| Sunteck Centre | Sunteck Centre 37-40 Subhash Road Vile Parle East Mumbai 400057 | 15 | Completed | Sep 2009 | Late, Dec 2009 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 24 other registrations, which the RERA portal never shows together
- All 93 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sunteck ONEWorld 3, Tivri, Naigaon East on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tivari3,200+ in Palghar
Suraksha Smart City - Phase I
Conceptual Advisory Services LLP
The Great Western Mumbai
HOABL Impactum Land Private Limited
Suraksha Smart City - Phase II
Conceptual Advisory Services LLP
Suraksha Smart City - Phase III
Conceptual Advisory Services LLP
Rashmi Star City Phase 2
Rashmi Realty Builders Pvt Ltd
Agarwal Sky Heights
Shreenath Realtors
See every Palghar project, with the district possession charts
Builder: Sunteck Realty Limited
Sunteck Realty Limited has 25 registrations on MahaRERA, including Sunteck City Avenue 1 and Sunteck City Avenue 2. Its filings disclose 6 earlier MahaRERA projects: declares 4 of 6 past projects completed on time. Litigation is declared on 12 of its registrations. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if Sunteck ONEWorld 3, Tivri, Naigaon East is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sunteck ONEWorld 3, Tivri, Naigaon East?
The registered promoter entity is Sunteck Realty Limited, a company as per the filing. Its CIN L32100MH1981PLC025346 and GSTIN 27AAACI0336E1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sunteck ONEWorld 3, Tivri, Naigaon East?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Sunteck ONEWorld 3, Tivri, Naigaon East?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Sunteck ONEWorld 3, Tivri, Naigaon East?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sunteck ONEWorld 3, Tivri, Naigaon East?
The professionals named in the filing: Architect: Practice Design Pvt. Ltd; Engineer: Raju HJ; Engineer: Gul Ghanshyam Mirani; Chartered Accountant: Jhanwar & Maheshwari; Chartered Accountant: Walker Chandiok & Co LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sunteck ONEWorld 3, Tivri, Naigaon East?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback