Red flags

  • Litigation declared, 2 cases
  • Rs 200.00 crore secured on the land, in favour of RBL BANK LIMITED

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 completed earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 47%
33 of 33Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

High-Street of Raheja Galaxy in RVP is a Commercial project by CAVALCADE PROPERTIES PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100080368 on 27 May 2025. Possession is promised by 31 Mar 2029. 0 of the 33 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameHigh-Street of Raheja Galaxy in RVP
  • TypeCommercial
  • Location
    • Cloud 9
    • NIBM
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • RERA no.P52100080368
  • ReraGenie IDRG-MH-32634

Builder

  • NameCAVALCADE PROPERTIES PVT LTD
  • Entity typeCompany
  • CINU70100MH2005PTC154307
  • DirectorsARVIND DIGAMBAR PRABHU, ANAND PRABHU CHANDAN
  • Other registrations11 more →
  • Completed3 of 12
  • Declared earlier projects9 →

Key dates

this monthRegisteredMay 2025PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 May 2025
  • Promised completion31 Mar 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed89 files

Current status

0%0 of 33 units booked
7.3%Work done, per cost certificate

Figures as on 7 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
High-Street of Raheja Galaxy in RVP - Commercial DevelopmentNA5503333

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 47%.

High-Street of Raheja Galaxy in RVP - Commercial Development: 6% average across the applicable activities

ActivityProgress
Excavation47%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure23%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered118

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,100 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofRBL BANK LIMITED
Secured amountRs 200.00 crore
CERSAI search filedYes
Declared on26 Jun 2025

Approvals and building plan

Permissible FSI7500.0
Proposed, not sanctioned5,663 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRBL BANK LTD,DHANNUR HOUSE,15,SIR P M ROAD, FORT,MUMBAI-400001
Estimated costRs 34.33 cr
Cost incurredRs 2.51 cr
Work done7.32%
BuildingWingEstimatedIncurred
High-Street of Raheja Galaxy in RVP - Commercial DevelopmentNARs 26.21 crRs 1.92 cr
-NARs 8.11 crRs 59.40 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKapadia Associates
ArchitectSharad Kumbhar
EngineerCBM Engineers
EngineerNilesh Soni
Chartered AccountantS N Doshi and Associates
Chartered AccountantSolase and Associates
PartnerRole in project
CAVALCADE PROPERTIES PVT LTD-

Litigation declared2

CaseCourtStatus
1774/2023Civil Judge Senior Division PuneOngoing
40/2021Additional Commissioner PuneClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2029

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf7 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf7 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf7 Jul 2026
Form 2A (FY 2026-2027)File: Form 2A High-Street.pdf30 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf13 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf13 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf13 Apr 2026
Layout approvalFile: Layout.pdf19 Jan 2026
Commencement certificateFile: Commencement Certificate.pdf19 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf7 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf7 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf7 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf8 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf8 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf8 Oct 2025
Form 2A (FY 2025-2026)File: Form 2A High Street.pdf27 Jun 2025
Layout approvalFile: Declaration with Layout.pdf21 May 2025
Layout approvalFile: Layout highlighted.pdf21 May 2025
Copy of Layout Approval (in case of layout)File: Declaration with Layout.pdf21 May 2025
Copy of Layout Approval (in case of layout)File: Layout highlighted.pdf21 May 2025
Details of encumbrances concerned to FinanceFile: Encumbrance concerned to Finance 14042025.pdf14 Apr 2025
CERSAI detailsFile: CERSAI Report 14042025.pdf14 Apr 2025
Details of encumbrances concerned to LegalFile: Encumbrance concerned to Finance 14042025.pdf14 Apr 2025
Building plan approvalFile: 2 Podium 1 LG and UG.pdf28 Mar 2025
Building plan approvalFile: 3 Podium 2 and 3.pdf28 Mar 2025
Building plan approvalFile: 5 Elevation.pdf28 Mar 2025
Building plan approvalFile: 6 Section.pdf28 Mar 2025
PAN CardFile: PAN CPPL.pdf28 Mar 2025
Copy of the legal title reportFile: TC 1.pdf28 Mar 2025
Copy of the legal title reportFile: TC 2.pdf28 Mar 2025
Copy of the legal title reportFile: RERA Certificate highlighted 10022025.pdf28 Mar 2025
Details of encumbrances concerned to FinanceFile: 2 Encumbrance concerned to Litigation.pdf28 Mar 2025
Proforma of Allotment letterFile: Allotment Letter.pdf28 Mar 2025
Declaration in FORM BFile: Form B.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 6 Section.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 5 Elevation.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2 Podium 1 LG and UG.pdf28 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 3 Podium 2 and 3.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 15704 2020 Part 1.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 7.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 14920 2020 Part 1.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 14920 2020 Part 2.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 14921 2020 Part 1.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 14921 2020 Part 2.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 17204 2020 Part 1.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 17204 2020 Part 2.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 17204 2020 Part 3.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 15704 2020 Part 2.pdf28 Mar 2025
Other - LegalFile: Deed Of Conveyance 15704 2020 Part 3.pdf28 Mar 2025
Other - LegalFile: Confirmation Deed IMIPL to CPPL Part 1.pdf28 Mar 2025
Other - LegalFile: Confirmation Deed IMIPL to CPPL Part 2.pdf28 Mar 2025
Other - LegalFile: Confirmation Deed IMIPL to CPPL Part 3.pdf28 Mar 2025
Other - LegalFile: Confirmation Deed IMIPL to CPPL Part 4.pdf28 Mar 2025
Other - LegalFile: Declaration Order 50.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 4.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 5.pdf28 Mar 2025
Other - LegalFile: BR.pdf28 Mar 2025
Other - LegalFile: Delcaration of Plot area.pdf28 Mar 2025
Other - LegalFile: 5 Declaration for Sale Deed with Index II compressedd.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 1.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 2.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 3.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 4.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 5.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 7.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 8.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 9.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 1.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 2.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 3.pdf28 Mar 2025
Other - LegalFile: Conveyance 1757 2012 Part 6.pdf28 Mar 2025
Other - LegalFile: Sale Deed 5784 2014 part 6.pdf28 Mar 2025
Declaration about Commencement CertificateFile: 4 CC Declaration.pdf28 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf28 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter.pdf28 Mar 2025
Details of encumbrances concerned to LegalFile: 2 Encumbrance concerned to Litigation.pdf28 Mar 2025

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise5 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
T4A named Celina of Raheja Galaxy in RV PremiereP52100079576NIBM, Pune66Mar 2025OngoingMar 2030Not due yet
T1 named Helios of Raheja Galaxy in RV PremiereP52100077444NIBM, Pune64Aug 2024OngoingNov 2028Not due yet
T3 named Altair of Raheja Galaxy in RV PremiereP52100054163NIBM, Pune156Dec 2023OngoingJul 2028Not due yet
T2 named Constella of Raheja Galaxy in RV PremiereP52100054218NIBM, Pune156Jan 2024OngoingJul 2028Not due yet
T11 named as Raheja Stellar in RV PremiereP52100033399Off NIBM, Pune209Feb 2022OngoingDec 2026Not due yet
T8 named LUXURIANT Phase 2 of Raheja Reserve being Buildings T7 T8 T9 T10 in RV PremiereP52100024187NIBM Road, Pune168Jan 2020CompletedMar 2026Jan 2024
T9 Chronos and T10 Supremus Phase 1 Of Raheja Reserve being Buildings T7 T8 T9 T10 in RV PremiereP52100021356NIBM, Pune-Jun 2019CompletedSep 2025Oct 2022
T7 named Belvedere phase 3 of Raheja Reserve being buildings T7 T8 T9 T10 in RV PremiereP52100030551NIBM, Pune168Aug 2021CompletedMar 2025Jan 2024

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep High-Street of Raheja Galaxy in RVP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NIBM13,700+ in Pune

Builder: CAVALCADE PROPERTIES PVT LTD

CAVALCADE PROPERTIES PVT LTD has 12 registrations on MahaRERA, including RAHEJA STERLING - TOWER 1 and RAHEJA STERLING - TOWER 2. Its filings disclose 9 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 12 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if High-Street of Raheja Galaxy in RVP is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of High-Street of Raheja Galaxy in RVP?

The registered promoter entity is CAVALCADE PROPERTIES PVT LTD, a company as per the filing. Its CIN U70100MH2005PTC154307 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in High-Street of Raheja Galaxy in RVP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for High-Street of Raheja Galaxy in RVP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at High-Street of Raheja Galaxy in RVP?

The professionals named in the filing: Architect: Kapadia Associates; Architect: Sharad Kumbhar; Engineer: CBM Engineers; Engineer: Nilesh Soni; Chartered Accountant: S N Doshi and Associates; Chartered Accountant: Solase and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in High-Street of Raheja Galaxy in RVP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About High-Street of Raheja Galaxy in RVP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save High-Street of Raheja Galaxy in RVP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.