Home / Browse projects / Pune, Maharashtra / GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N

Registered Litigation declared Residential / Group Housing project

GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N

By GOEL GANGA INDIA PVT LTD

RG-MH-16428 · RERA P52100025883 · Last updated on MahaRERA portal: 9 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 9 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 30 months
  • 1 extension taken
  • Rs 50.00 crore secured on the land, in favour of Pride Capital Pvt Ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • All 5 earlier projects delivered on promise

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 30 months from the original
23 of 66Construction stages doneacross 6 buildings; furthest along: Internal walls, 98%
7 of 543Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N is a Residential / Group Housing project by GOEL GANGA INDIA PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100025883 on 24 Jul 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 30 months from the original filing. 536 of the 543 units on this registration are recorded sold or booked, and 23 of 66 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N
  • TypeResidential / Group Housing
  • Location
    • KADNAGAR
    • UNDRI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100025883
  • ReraGenie IDRG-MH-16428

Builder

  • NameGOEL GANGA INDIA PVT LTD
  • Entity typeCompany
  • GSTIN27AAGCG6139B6ZN
  • DirectorsAMIT JAIPRAKASH GOEL, ATUL JAIPRAKASH GOEL
  • Other registrations23 more →
  • Completed6 of 24
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

this monthRegisteredJul 2020First promiseJun 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jul 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2025)
  • Buildings6 building records
  • Documents filed134 files

Current status

99%536 of 543 units booked

Figures as on 9 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING J 1 -10 FLOORSNA11101100110
BUILDING J 11-15 FLOORS and STILTNA6663063
BUILDING K 1-14 FLOORS and stilt , 15 th floorNA17171300130
BUILDING L 1-14 FLOORS, STILT AND 15 TH FLOORNA161664064
BUILDING M 1-14 FLOORS , STILT AND 15 TH FLOORNA161696096
BUILDING N 1-14 FLOORS, STILT AND 15 TH FLOORNA171780080

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

23 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Internal walls, at 98%.

BUILDING J 1 -10 FLOORS88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.88%
BUILDING J 11-15 FLOORS and STILT97%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.88%
BUILDING K 1-14 FLOORS and stilt , 15 th floor47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure97%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises11%
Sanitary Fittings within the flats / premises14%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING L 1-14 FLOORS, STILT AND 15 TH FLOOR9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING M 1-14 FLOORS , STILT AND 15 TH FLOOR22%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING N 1-14 FLOORS, STILT AND 15 TH FLOOR40%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)6%
Plinth100%
Stilt Floor100%
Slabs of Super Structure34%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed140

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots140
Closed/Covered140
BuildingClosed/CoveredTotal
BUILDING J 1 -10 FLOORS2020
BUILDING J 11-15 FLOORS and STILT88
BUILDING K 1-14 FLOORS and stilt , 15 th floor2828
BUILDING L 1-14 FLOORS, STILT AND 15 TH FLOOR2828
BUILDING M 1-14 FLOORS , STILT AND 15 TH FLOOR2828
BUILDING N 1-14 FLOORS, STILT AND 15 TH FLOOR2828

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area9,850 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofPride Capital Pvt Ltd
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on4 Jun 2026

Approvals and building plan

Sanctioning authorityPune Municipal Corporation (PMC)
Permissible FSI37161.3
Proposed, not sanctioned7,161 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCHAKAN BRANCH

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSpace Designers Syndicate
EngineerPradhuman Sacchindanand Doiphode
EngineerShivaji Patil
Chartered AccountantSachin Chordiya & Co
PartnerRole in project
MILLENNIA SCHEMES PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024340Jun 2025 → Dec 2027

Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52100025883. As per HEARING DATED 10th December 2024, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31.12.2027. The order is Annexed in Sr No 2 for your reference.

Litigation declared9

CaseCourtStatus
666/2013CIVIL COURT PUNEPENDING
361/2015CIVIL COURT PUNEPENDING
64/2013CIVIL COURT PUNEPENDING
699/2014CIVIL COURT PUNEPENDING
357/2015CIVIL COURT PUNEPENDING
1901/2015CIVIL COURT PUNEPENDING
1157/2019CIVIL COURT PUNEPENDING
32/2016CIVIL COURT PUNEPENDING
64/2013Civil Judge Senior Division, PuneOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12502710Salman Rahuf AttarGOEL GANGA INDIA PVT LTD02/08/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Apr 2025

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 JKLMN.pdf9 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate Bldg JKLMN.pdf9 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf9 Jul 2026
Withdrawal Update Form 2File: FORM 2 JKLMN.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Bldg JKLMN.pdf9 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf9 Jul 2026
Withdrawal Update Form 3File: FORM 3 JKLMN.pdf9 Jul 2026
Withdrawal Update Form 3File: Form 3 JKLMN Q2 signed.pdf9 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf9 Jul 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JKLMN.pdf28 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JKLMN.pdf28 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JKLMN.pdf28 Jul 2025
Layout approvalFile: SHEET NO 1 LAYOUT PLAN_compressed (1).pdf18 Jul 2025
Building plan approvalFile: SHEET NO 1 LAYOUT PLAN_compressed (1).pdf18 Jul 2025
Copy of Layout Approval (in case of layout)File: SHEET NO 1 LAYOUT PLAN_compressed (1).pdf18 Jul 2025
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE NO 0730 DATED 30 05 2025.pdf18 Jul 2025
Building Plan Approval / NA Order for plotted developmentFile: SHEET NO 1 LAYOUT PLAN_compressed (1).pdf18 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Millenia March 25.pdf25 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: J building complition certficate.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JKLMN.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JKLMN.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE JKLMN_compressed (1).pdf24 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A JKLMN.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JKLMN FORM 1.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JKLMN FORM 2.pdf19 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: JKLMN FORM 2A.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Millennia December 2024_compressed.pdf6 Feb 2025
Layout approvalFile: SHEET NO 1 LAYOUT BUILDING PERMISSION_compressed.pdf1 Feb 2025
Building plan approvalFile: SHEET NO 1 LAYOUT BUILDING PERMISSION_compressed.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: SHEET NO 1 LAYOUT BUILDING PERMISSION_compressed.pdf1 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERMISSION COMMENCEMENT CERTIFICATE CC NO 2857 DATED 26 12 2024.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: SHEET NO 1 LAYOUT BUILDING PERMISSION_compressed.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate Bldg JKLMN- Dec 2024.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate Bldg JKLMN - Dec 2024.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate Bldg JKLMN- Sept 2024.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JKLMN sept 2024_compressed.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate Bldg JKLMN - Sept 2024.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: Discloser of sold inventory JKLMN_compressed.pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JKLMN_compressed.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate Bldg JKLMN- June 2024.pdf8 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate Bldg JKLMN - June 2024.pdf8 Aug 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29_11zon.pdf6 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Millennia JKLMN 2022-23.pdf31 Jul 2024
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf15 Jul 2024
Declaration in FORM BFile: FORM B.pdf15 Jul 2024
Declaration in FORM BFile: FORM B_rotated (2).pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEPTEMBER 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 2 DECEMBER 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEPTEMBER 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DECEMBER 2023.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH 2024.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE 2023.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SEPTEMBER 2023.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DECEMBER 2023.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH 2024.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A 2020-21.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2021-22.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2023-24.pdf15 Jul 2024
CERSAI detailsFile: CERSAI DECLARATION.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MARCH 2023_11zon.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 JUNE 2023.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SEPTEMBER 2023.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DECEMBER 2023.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MARCH 2024.pdf15 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf15 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Atul Sir-1-0.pdf15 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.pdf15 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 MARCH 2022.pdf15 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Seperate Bank Account Details.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 JKLMN March 2024.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - Architect's Certificate Bldg JKLMN- March 2024.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - Engineer's Certificate Bldg JKLMN - March 2024.pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 3 Form - 2A - Engineer's Certificate (Quality Assurance) Bldg JKLMN - March 2024.pdf7 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - GANGA MILLENIA_compressed_compressed.pdf24 Jan 2024

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GANGA GLITZSR NO 16P AND 17 P UNDRI PUNE192CompletedApr 2018Apr 2017
GANGA ARCADIASR NO 22 HISSA NO 2 PLOT A KHARADI PUNE 41101428CompletedJun 2017Jun 2017
GANGA ARCADIASR NO 22 HISSA NO 2 PLOT A KHARADI PUNE 411014120CompletedDec 2015Oct 2015
GANGA SPARSHSR NO 16 P AND 17 P UNDRI PUNE154CompletedApr 2014Nov 2013
AMRUTGANGAVADGAON BK PUNE611CompletedDec 2013Oct 2013

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near UNDRI13,700+ in Pune

2 kmGANGA MILLENNIA UNDRI BUCompleted 89Lapsed / revoked 28Other 90Dot size: filed unitsN

Filed coordinates, straight-line distance. 207 registered projects within 2 km.

Builder: GOEL GANGA INDIA PVT LTD

GOEL GANGA INDIA PVT LTD has 24 registrations on MahaRERA, including GANGA GLITZ F. BLDG and GANGA LEGEND A4 AND B1... Its filings disclose 8 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Litigation is declared on 11 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N?

The registered promoter entity is GOEL GANGA INDIA PVT LTD, a company as per the filing. Its GSTIN 27AAGCG6139B6ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N?

The professionals named in the filing: Architect: Space Designers Syndicate; Engineer: Pradhuman Sacchindanand Doiphode; Engineer: Shivaji Patil; Chartered Accountant: Sachin Chordiya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.