ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / THE SPECTRUM

Registered No litigation declared Others project

THE SPECTRUM

By SHRIRAM PROPERTIES LIMITED

RG-MH-31731 · RERA P52100080066 · Last updated on MahaRERA portal: 21 Apr 2026

Source: official MahaRERA filing

Red flags

  • Rs 95.00 crore secured on the land, in favour of IndusInd Bank Limited

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 4 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2035Possession promisedno revision filed
0 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 94%
426 of 657Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 219 documents Report an error

THE SPECTRUM is a Others project by SHRIRAM PROPERTIES LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100080066 on 22 Apr 2025. Possession is promised by 14 Apr 2035. 231 of the 657 units on this registration are recorded sold or booked, and 0 of 44 construction stages are filed complete.

At a glance

Project

  • NameTHE SPECTRUM
  • TypeOthers
  • Location
    • Sy No 27/1
    • 27/2
    • 27/10 & S No 33(p)
    • Undri
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100080066
  • ReraGenie IDRG-MH-31731

Builder

  • NameSHRIRAM PROPERTIES LIMITED
  • Entity typeCompany
  • Chairman & Managing DirectorsAnita Kapoor, Ashish Pradeep Deora, Malayappan Murali, Kulumani Gopalrathnam Krishnamurthy, Thai Salas Vijayan, Vaidyanathan Ramamurthy
  • Declared earlier projects4 →

Key dates

this monthRegisteredApr 2025PromisedApr 2035

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Apr 2025
  • Promised completion14 Apr 2035
  • Revised completionNone
  • Buildings4 building records
  • Documents filed219 files

Current status

35%231 of 657 units booked
7.5%Work done, per cost certificate

Figures as on 21 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING - ANA191712118139
BUILDING - BNA242216821189
BUILDING - CNA242216819187
BUILDING - DNA191712814142

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 94%.

BUILDING - A9%
ActivityProgress
Excavation94%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING - B8%
ActivityProgress
Excavation84%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING - C3%
ActivityProgress
Excavation37%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING - D1%
ActivityProgress
Excavation12%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes5%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed637

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots637
Closed/Covered600
Open Space37
BuildingClosed/CoveredOpen SpaceTotal
BUILDING - A1258133
BUILDING - B17510185
BUILDING - C1709179
BUILDING - D13010140

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area64,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofIndusInd Bank Limited
Secured amountRs 95.00 crore
CERSAI search filedYes
Declared on22 May 2026
LandownerVillageDistrict
ETHIX REALTORS PRIVATE LIMITEDPune (M Corp.)Pune
Dharmesh Kishor GathaniPune (M Corp.)Pune
Srichand Goumal GalaniPune (CB)Pune

Approvals and building plan

Sanctioning authorityPoona municipal corporation
Permissible FSI202759.84
Proposed, not sanctioned83,458 sq m
Buildings approved10
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2401,GEN.THIMMAYYA RD. (CANTONMENT), PUNE - 411 001.
Estimated costRs 288.36 cr
Cost incurredRs 21.67 cr
Work done7.51%
BuildingWingEstimatedIncurred
BUILDING - CNARs 76.71 crRs 1.71 cr
BUILDING - BNARs 71.20 crRs 2.25 cr
BUILDING - DNARs 58.19 crRs 21.67 lakh
BUILDING - ANARs 51.93 crRs 1.95 cr
-NARs 30.33 crRs 15.54 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectS R DOSHI
EngineerVishalkumar
Chartered AccountantVivek Gupta
PartnerRole in project
SHRIRAM PROPERTIES LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 14 Apr 2035

Documents filed219

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 219 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 undri-27 Architectural certificate.pdf21 Apr 2026
Withdrawal Update Form 2File: Form-2 Engineering certificate..pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3 CA certificate Mar 26.pdf21 Apr 2026
Withdrawal Update Form 1File: Form-1 Architect certificate.pdf16 Feb 2026
Withdrawal Update Form 1File: Form-1 Architect certificate.pdf16 Feb 2026
Withdrawal Update Form 2File: Form-2 Engineering certificate Dec-2025.pdf16 Feb 2026
Withdrawal Update Form 2File: Form-2 Engineering certificate Dec-2025.pdf16 Feb 2026
Withdrawal Update Form 3File: Form3- CA Certificate_Final Dec 25.pdf16 Feb 2026
Withdrawal Update Form 3File: Form3- CA Certificate_Final Dec 25.pdf16 Feb 2026
Withdrawal Update Form 1File: Architect Certificate.pdf27 Nov 2025
Withdrawal Update Form 1File: Architect Certificate.pdf27 Nov 2025
Withdrawal Update Form 2File: Form-2 Engineering certificate.pdf27 Nov 2025
Withdrawal Update Form 2File: Form-2 Engineering certificate.pdf27 Nov 2025
Withdrawal Update Form 3File: Form 3- CA certificate_Final Sepu002725.pdf27 Nov 2025
Withdrawal Update Form 3File: Form 3- CA certificate_Final Sepu002725.pdf27 Nov 2025
Withdrawal Update Form 1File: FORM 1 RERA ARCHITECT CERTIFICATE UNDRI-27 (1).pdf3 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf3 Oct 2025
Withdrawal Update Form 3File: Form 3- CA certificate_FInal.pdf3 Oct 2025
Building plan approvalFile: Request Letter.pdf19 Apr 2025
Building plan approvalFile: 39 Building Plan Approval _ NA Order for plotted development_Compressed.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Request Letter.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 39 Building Plan Approval _ NA Order for plotted development_Compressed.pdf19 Apr 2025
Building plan approvalFile: Gmail - Commencement Certificate - PMC.pdf17 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Gmail - Commencement Certificate - PMC.pdf17 Apr 2025
Building plan approvalFile: Site Plan -01.pdf16 Apr 2025
Building plan approvalFile: D TY REFUGE 35.pdf16 Apr 2025
Building plan approvalFile: D TY ODD 34.pdf16 Apr 2025
Building plan approvalFile: D TY EVEN 33.pdf16 Apr 2025
Building plan approvalFile: D TERRACE 36.pdf16 Apr 2025
Building plan approvalFile: D MEZZ 31_11zon.pdf16 Apr 2025
Building plan approvalFile: D GF 30.pdf16 Apr 2025
Building plan approvalFile: D FF 32.pdf16 Apr 2025
Building plan approvalFile: C TY ODD REFUGE 26.pdf16 Apr 2025
Building plan approvalFile: C TY ODD 25_11zon.pdf16 Apr 2025
Building plan approvalFile: C TY EVEN 24_11zon.pdf16 Apr 2025
Building plan approvalFile: C TERRACE.pdf16 Apr 2025
Building plan approvalFile: C MEZZ 22_compressed.pdf16 Apr 2025
Building plan approvalFile: C GF 21_compressed.pdf16 Apr 2025
Building plan approvalFile: C FF 23.pdf16 Apr 2025
Building plan approvalFile: C 22 FLOOR 28_11zon (1).pdf16 Apr 2025
Building plan approvalFile: C 21 FLOOR REFUGE 27 (1).pdf16 Apr 2025
Building plan approvalFile: Basement 2 -03_compressed.pdf16 Apr 2025
Building plan approvalFile: Basement 1 -02.pdf16 Apr 2025
Building plan approvalFile: A EVEN FLOOR -07.pdf16 Apr 2025
Building plan approvalFile: A FF -06.pdf16 Apr 2025
Building plan approvalFile: A Ground Floor - 04.pdf16 Apr 2025
Building plan approvalFile: A Mezz -05_compressed.pdf16 Apr 2025
Building plan approvalFile: A ODD -08.pdf16 Apr 2025
Building plan approvalFile: A REFUGE -09.pdf16 Apr 2025
Building plan approvalFile: A REFUGE ODD -10.pdf16 Apr 2025
Building plan approvalFile: A TERRACE -11.pdf16 Apr 2025
Building plan approvalFile: B 22 FLOOR 19.pdf16 Apr 2025
Building plan approvalFile: B FF 14_compressed.pdf16 Apr 2025
Building plan approvalFile: B GF -12 (1).pdf16 Apr 2025
Building plan approvalFile: B MEZZ -13_compressed.pdf16 Apr 2025
Building plan approvalFile: B REFUGE ODD 18 (1).pdf16 Apr 2025
Building plan approvalFile: B REFUGE TYOICAL 17_11zon.pdf16 Apr 2025
Building plan approvalFile: B TERRACE 20.pdf16 Apr 2025
Building plan approvalFile: B TYPICAL EVEN 15.pdf16 Apr 2025
Building plan approvalFile: B TYPICAL ODD 16_11zon.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Site Plan -01.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D TY REFUGE 35.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D TY ODD 34.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D TY EVEN 33.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D TERRACE 36.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D MEZZ 31_11zon.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D GF 30.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: D FF 32.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C TY ODD REFUGE 26.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C TY ODD 25_11zon.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C TY EVEN 24_11zon.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C TERRACE.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C MEZZ 22_compressed.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C GF 21_compressed.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C FF 23.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C 22 FLOOR 28_11zon (1).pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: C 21 FLOOR REFUGE 27 (1).pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Basement 2 -03_compressed.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Basement 1 -02.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: A EVEN FLOOR -07.pdf16 Apr 2025

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHRIRAM SERENITYADDEVISWANATHAPURA VILLAGE HESARAGHATTA HOBLI YELAHANKA TALUK BANGALORE URBAN Bengaluru North Bengaluru Urban Karnataka 560064270OngoingJul 2029Jul 2029
Shriram SapphireBommasandra village Attibele hobli Bengaluru414OngoingNov 2028Nov 2028
SHRIRAM ESQUIREHBCS LTD Nirguna Mandir Layout Bengaluru South Bengaluru Urban Karnataka64OngoingJan 2027Jan 2027
SHRIRAM MYSTIQUEROYAL STREET MYDRAHALLI YESHWANTHAPURA HOBLI BBMP WARD NO 12 BANGALORE 560090148OngoingApr 2025Apr 2025

How this compares with Pune

35%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE SPECTRUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Undri13,700+ in Pune

2 kmTHE SPECTRUMCompleted 70Lapsed / revoked 29Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 157 registered projects within 2 km.

Builder: SHRIRAM PROPERTIES LIMITED

SHRIRAM PROPERTIES LIMITED has 1 registration on MahaRERA, including THE SPECTRUM. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if THE SPECTRUM is delayed beyond 14 Apr 2035?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE SPECTRUM?

The registered promoter entity is SHRIRAM PROPERTIES LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE SPECTRUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE SPECTRUM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE SPECTRUM?

The professionals named in the filing: Architect: S R DOSHI; Engineer: Vishalkumar; Chartered Accountant: Vivek Gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE SPECTRUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE SPECTRUM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE SPECTRUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.