ReraGenieLog inGet a buyer report

Home / Areas / Solapur

New projects and RERA data in Solapur district, Maharashtra

551 of the projects in this build are in Solapur district: 21,393 units across them, 25 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

551Projects in this build
25Registered, last 12 months
21,393Units declared
16,796Units not yet booked
84Completion dates revised
2With declared litigation

Of the 551 covered registrations, 84 have revised their promised completion date and 2 declare litigation. The median project here is 18% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.

When Solapur projects promise possession

Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 551 projects with a promised date, 173 are recorded delivered, 154 are still on the register and 224 have a registration that has lapsed or been cancelled.

DeliveredOn the registerRegistration lapsed or cancelled

0255075100today2017: 3 projects, delivered2017: 1 projects, registration lapsed or cancelled’172018: 23 projects, delivered2018: 5 projects, registration lapsed or cancelled’182019: 25 projects, delivered2019: 9 projects, registration lapsed or cancelled’192020: 14 projects, delivered2020: 8 projects, registration lapsed or cancelled’202021: 15 projects, delivered2021: 10 projects, registration lapsed or cancelled’212022: 25 projects, delivered2022: 26 projects, registration lapsed or cancelled’222023: 21 projects, delivered2023: 26 projects, registration lapsed or cancelled’232024: 12 projects, delivered2024: 48 projects, registration lapsed or cancelled’242025: 20 projects, delivered2025: 68 projects, registration lapsed or cancelled’252026: 10 projects, delivered2026: 49 projects, on the register2026: 22 projects, registration lapsed or cancelled’262027: 3 projects, delivered2027: 46 projects, on the register2027: 1 projects, registration lapsed or cancelled’272028: 1 projects, delivered2028: 15 projects, on the register’282029: 19 projects, on the register’292030: 20 projects, on the register’302032: 4 projects, on the register’322035: 1 projects, delivered2035: 1 projects, on the register’35

192 projects promise possession in 2026 or later. Facts as per filings on RERA website.

02,5005,0007,50010ktoday2017: 45 flats, registration lapsed or cancelled (only 1 of 4 projects filed a flat count)’172018: 834 flats, delivered (only 4 of 28 projects filed a flat count)’182019: 276 flats, delivered (only 4 of 34 projects filed a flat count)2019: 325 flats, registration lapsed or cancelled (only 4 of 34 projects filed a flat count)’192020: 18 flats, delivered (only 2 of 22 projects filed a flat count)2020: 74 flats, registration lapsed or cancelled (only 2 of 22 projects filed a flat count)’202021: 695 flats, delivered (only 2 of 25 projects filed a flat count)’212022: 704 flats, delivered (only 9 of 51 projects filed a flat count)2022: 65 flats, registration lapsed or cancelled (only 9 of 51 projects filed a flat count)’222023: 142 flats, delivered (only 13 of 47 projects filed a flat count)2023: 489 flats, registration lapsed or cancelled (only 13 of 47 projects filed a flat count)’232024: 344 flats, delivered (only 6 of 60 projects filed a flat count)2024: 528 flats, registration lapsed or cancelled (only 6 of 60 projects filed a flat count)’242025: 159 flats, delivered (only 16 of 88 projects filed a flat count)2025: 416 flats, registration lapsed or cancelled (only 16 of 88 projects filed a flat count)’252026: 126 flats, delivered (only 31 of 81 projects filed a flat count)2026: 2,529 flats, on the register (only 31 of 81 projects filed a flat count)2026: 638 flats, registration lapsed or cancelled (only 31 of 81 projects filed a flat count)’262027: 8,814 flats, on the register (only 23 of 50 projects filed a flat count)’272028: 526 flats, on the register’282029: 1,800 flats, on the register’292030: 1,631 flats, on the register’302032: 83 flats, on the register’322035: 132 flats, on the register’35

16,279 flats are promised in 2026 or later, across the 51% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.

How far Solapur possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 84 of 551 projects (15%) have moved at least once; the median move is 24 months and the longest is 191 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

0255075100Originally due 2017: 4 projects kept the original date, 100% of the year’17Originally due 2018: 27 projects kept the original date, 73% of the yearOriginally due 2018: 4 projects moved by under 2 years, 11% of the yearOriginally due 2018: 6 projects moved by 2 years or more, 16% of the year’18Originally due 2019: 33 projects kept the original date, 66% of the yearOriginally due 2019: 6 projects moved by under 2 years, 12% of the yearOriginally due 2019: 11 projects moved by 2 years or more, 22% of the year’19Originally due 2020: 16 projects kept the original date, 73% of the yearOriginally due 2020: 1 projects moved by under 2 years, 5% of the yearOriginally due 2020: 5 projects moved by 2 years or more, 23% of the year’20Originally due 2021: 19 projects kept the original date, 83% of the yearOriginally due 2021: 2 projects moved by under 2 years, 9% of the yearOriginally due 2021: 2 projects moved by 2 years or more, 9% of the year’21Originally due 2022: 40 projects kept the original date, 91% of the yearOriginally due 2022: 1 projects moved by under 2 years, 2% of the yearOriginally due 2022: 3 projects moved by 2 years or more, 7% of the year’22Originally due 2023: 42 projects kept the original date, 72% of the yearOriginally due 2023: 8 projects moved by under 2 years, 14% of the yearOriginally due 2023: 8 projects moved by 2 years or more, 14% of the year’23Originally due 2024: 51 projects kept the original date, 88% of the yearOriginally due 2024: 4 projects moved by under 2 years, 7% of the yearOriginally due 2024: 3 projects moved by 2 years or more, 5% of the year’24Originally due 2025: 75 projects kept the original date, 82% of the yearOriginally due 2025: 11 projects moved by under 2 years, 12% of the yearOriginally due 2025: 5 projects moved by 2 years or more, 5% of the year’25Originally due 2026: 64 projects kept the original date, 94% of the yearOriginally due 2026: 3 projects moved by under 2 years, 4% of the yearOriginally due 2026: 1 projects moved by 2 years or more, 1% of the year’26Originally due 2027: 42 projects kept the original date, 100% of the year’27Originally due 2028: 14 projects kept the original date, 100% of the year’28Originally due 2029: 16 projects kept the original date, 100% of the year’29Originally due 2030: 19 projects kept the original date, 100% of the year’30Originally due 2032: 4 projects kept the original date, 100% of the year’32Originally due 2035: 1 projects kept the original date, 100% of the year’35

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

05,00010k15k20kOriginally due 2017: 45 flats kept the original date, 100% of the year (only 1 of 4 projects filed a flat count)’17Originally due 2018: 834 flats kept the original date, 73% of the year (only 5 of 37 projects filed a flat count)Originally due 2018: 18 flats moved by 2 years or more, 16% of the year (only 5 of 37 projects filed a flat count)’18Originally due 2019: 601 flats kept the original date, 66% of the year (only 8 of 50 projects filed a flat count)Originally due 2019: 1,136 flats moved by 2 years or more, 22% of the year (only 8 of 50 projects filed a flat count)’19Originally due 2020: 92 flats kept the original date, 73% of the year (only 3 of 22 projects filed a flat count)Originally due 2020: 68 flats moved by 2 years or more, 23% of the year (only 3 of 22 projects filed a flat count)’20’21Originally due 2022: 751 flats kept the original date, 91% of the year (only 9 of 44 projects filed a flat count)Originally due 2022: 141 flats moved by 2 years or more, 7% of the year (only 9 of 44 projects filed a flat count)’22Originally due 2023: 631 flats kept the original date, 72% of the year (only 18 of 58 projects filed a flat count)Originally due 2023: 65 flats moved by under 2 years, 14% of the year (only 18 of 58 projects filed a flat count)Originally due 2023: 111 flats moved by 2 years or more, 14% of the year (only 18 of 58 projects filed a flat count)’23Originally due 2024: 807 flats kept the original date, 88% of the year (only 7 of 58 projects filed a flat count)Originally due 2024: 34 flats moved by under 2 years, 7% of the year (only 7 of 58 projects filed a flat count)’24Originally due 2025: 433 flats kept the original date, 82% of the year (only 25 of 91 projects filed a flat count)Originally due 2025: 2,180 flats moved by under 2 years, 12% of the year (only 25 of 91 projects filed a flat count)Originally due 2025: 8,037 flats moved by 2 years or more, 5% of the year (only 25 of 91 projects filed a flat count)’25Originally due 2026: 874 flats kept the original date, 94% of the year (only 23 of 68 projects filed a flat count)Originally due 2026: 103 flats moved by under 2 years, 4% of the year (only 23 of 68 projects filed a flat count)Originally due 2026: 126 flats moved by 2 years or more, 1% of the year (only 23 of 68 projects filed a flat count)’26Originally due 2027: 777 flats kept the original date, 100% of the year (only 17 of 42 projects filed a flat count)’27Originally due 2028: 373 flats kept the original date, 100% of the year’28Originally due 2029: 1,386 flats kept the original date, 100% of the year’29Originally due 2030: 1,555 flats kept the original date, 100% of the year’30Originally due 2032: 83 flats kept the original date, 100% of the year’32Originally due 2035: 132 flats kept the original date, 100% of the year’35

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Projects in Solapur

ProjectDeveloperUnits BookedRegistered
Ray Nagar Housing Project Phase 2Vasant Vihar Realty Pvt Ltd78825%28 Sep 2018
PMAY BARSHI NAGAR PARISHAD AHPBARSHI NAGAR PARISHAD160710%31 Oct 2022
R M Dhariwal Township Velapur PlottingDhariwal And Chhoriya Buildcon Pvt Ltd51263%4 Aug 2017
Kurdu Plotting on Gat No 264Pragati Infra Services Pvt. Ltd.50885%24 Aug 2017
CHHORIYA TOWNSHIP WAKHARI PANDHARPUR PHASE 3Chhoriya Properties And Development Company4230%18 Feb 2021
Chhoriya Township - KarmalaChhoriya Properties41246%17 Aug 2017
ANANTA SOLAPURPROPWIZZ INFRA LLP38542%31 Aug 2017
VARAD NAGARIM/S SHRIRAM BUILDERS & DEVELOPERS3444%24 Jan 2023
MHDCL ANTROLIKAR NAGAR SOLAPUR PMAY PROJECTMAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED3400%28 Apr 2022
SAMRUDDHI PARKWAYNAGNATH SHIVSHANKAR AKKALKOTE33121%22 Nov 2021
Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman SansthaAnukarati Homes Private Limited28860%21 Jun 2024
The Platino Wing A, B, CPP Developers28476%8 Jun 2023
Shri Swami Samarth PuramDivyaa Ashtavinayaka Realty21926%24 Aug 2017
Paras Business ParkPriyadarshani Corporation1890%14 Nov 2024
KATHALE VIHARSATISH MALANBAI ANDHARE18715%6 Aug 2017
Chhoriya Township - Plotting Layout AkkalkotChhoriya and Chopda Properties18722%22 Aug 2017
R M Dhariwal Township Tembhurni PlottingDhariwal And Chhoriya Buildcon Pvt Ltd17734%31 Jul 2017
KIMAYA SWAPANAPURTI PHASE 2ALACRITY CONSTRUCTIONS PVT LTD1745%11 Jun 2025
Chhoriya Township Wakhari Pandharpur Phase 2Chhoriya Properties And Development Company15322%21 Oct 2020
VENKATESH LA-ARKA PHASE IIP A SATHE & ASSOCIATES1450%11 Oct 2022
Shhraddha EmraldShhraddha Buildcons14170%15 Jul 2017
NAKSHATRA HEIGHTSGAYATRI BUILDERS AND DEVELOPERS14122%23 Oct 2021
Vrundavan ParkVrundavan Properties1390%14 Sep 2022
Platinum MallM/S Ganesh Ramchandra Apte13268%10 Nov 2023
Chhoriya Residency - PandharpurDhariwal And Chhoriya Developers LLP13178%12 Oct 2019
Chhoriya Township Modnimb G No 139/Part PlottingDhariwal And Chhoriya Buildcon Pvt Ltd12994%5 Aug 2017
INDRADHANU-Phase-IVM/S Ganesh Ramchandra Apte12665%11 Jan 2018
INDRADHANU-Phase-6M/S Ganesh Ramchandra Apte12277%30 Mar 2021
MANOMAY VIHARSUKHAKARTA REALITY11726%31 Aug 2017
CENTER-PRIDEAMOL DATTATRAY NAGTILAK1170%6 Jan 2020
Jijau ResidencyRachana Developers1090%15 Sep 2025
ROYAL SYNERGYSHREE JAGDAMB DEVELOPERS10737%10 Feb 2025
Chhoriya Township - Plotting Layout VairagKhinvosara and Chhoriya Properties10676%10 Aug 2017
505 Bahava Row Houses,Open PlotsPandhe Infracons Pvt Ltd10697%31 Aug 2017
Heritage PalmsManoj Kantilal Shah9971%8 Dec 2017
Anantkoti SkyvillaANANTKOTI BUILDCON9725%23 Jul 2025
Mahanandi HeightsSneharika Vijayshree Developers940%3 Sep 2025
RAJASHREE HEIGHTSRajashree Builders8913%15 May 2023
HMEMPIRE210211HERIYTAGE MANIYDHARI EMPIRE860%25 Sep 2019
BRAMHA GALAXYBRAMHA BUILDCON8587%6 Jun 2022
Tirumala ParadiseSachin Vitthal Ghanate844%15 Jan 2024
KIMAYA SWAPANASHRUSTHIKIMAYA CONSTRUCTIONS PVT LTD8218%27 Mar 2025
Shree Vasundhara HeightsKishor Rajendra Sanjekar8140%11 Jan 2022
TIRUPATI PURAMTIRUPATI CONSTRUCTION PRAMOTERS AND DEVELOPERS7828%16 Apr 2024
DHANSHREE PARKKAZI BUILDERS780%2 Dec 2025
PANJWANI MARKETV V SOMSHETTI BUILDERS LLP7658%6 Dec 2021
SAMARTH PRASADJJRV INFRA PRIVATE LIMITED7626%11 Aug 2025
Madhuban Paradise Part-IIMadhuri Lature740%18 Jun 2019
Gokul ViharAakruti Builders7424%5 Apr 2023
FOUR SEASONST6 REALTY PVT LTD7447%6 Feb 2024
Sai Suman NagarPandhe Construction Pvt Ltd7384%19 Aug 2017
Panchganga Bramhaputra HeightsHANMANTU KOMARAYYA BURA7399%27 Jun 2023
SAI ICONBJR CONTRUCTIONS PRIVATE LIMITED7121%2 Feb 2024
F.F AMORAF F CITY TOWER DEVELOPERS68100%9 Oct 2017
Paras ParadiseAnantkoti Developers6847%2 Feb 2024
MAHESH COMPLEXSHRI CHAITANYA ADHYATMIK TRUST670%29 Jul 2025
Balaji HeightsBalaji Infra6673%1 Sep 2021
VINAYAK SQUARESHRI VINAYAK CONSSTRUCTIONS6560%23 Feb 2018
522Pandhe Infracons Pvt Ltd6466%22 Aug 2017
RSM HEIGHTS C TOWERRAJENDRA SUKHADEV MIRGANE6313%9 Aug 2017
Kaveri HeightsGayatri Developers6398%26 Jul 2021
Tirupati Puram IITIRUPATI CONSTRUCTION PRAMOTERS AND DEVELOPERS630%19 Nov 2025
H M EMPIRE 207HERITAGE MANIDHARI EMPIRE6092%23 Oct 2018
BLOSSOM PARKA J BUILDCON600%26 Feb 2026
FLORA PARKIMAGE SPACE INCORPORATED582%4 Jun 2026
SURYAMALA-B PHASE ISUVASTU PROPERTIES5630%22 Aug 2017
SUYOG SHRUSHTI PHASE 2SUYOG DEVELOPERS5636%23 Oct 2023
INDRAPRASTHA-Phase-3M/s Apte Reality550%29 Mar 2019
GANPAT MOREGANPAT PARSU MORE540%5 Apr 2020
Lokhandwala horizonSiddique Iqbal Motiwala544%26 Sep 2022
Radha GardenSudhir Patil5018%17 Aug 2017
LAYOUTPRAVIN PRADIP JADHAV500%24 Feb 2020
FURDE HEIGHTS - PHASE-I A BUILDINGSUNIL FURDE CONSTRUCTIONS PVT. LTD.4949%28 Oct 2021
Gayatri Vihar wing ARahul Rajnikant Arakal470%12 Nov 2021
Chhoriya Township Wakhari Pandharpur Phase 1Chhoriya Properties Development Co4659%7 Aug 2017
Sripad Shirvallabh Dream HomesYog Builders And Developers460%23 Apr 2018
PADMAWATI REJENCYGURAPPA MALLIKARJUN KAPSE4630%17 Oct 2023
SnehsrusthiGayatri Developers460%16 Jun 2025
Jaychandajit SuranaJAYCHAND SHANTILAL SURANA450%23 Oct 2017
Kandre ResidencyKANDRE DEVELOPER4547%28 Oct 2020
Heaven GalaxyAltaf Abdulhamid Shaikh4540%29 May 2021
Royal Imperial TowerRoyal Buildcon & Associates450%1 Jun 2026
MATOSHRI RESIDENCYBHARAT HAMBIRRAV SALUNKE4420%3 Feb 2022
G N NAGARNAZIR NADAF HAMID NADAF IBRAHIM NADAF432%31 Aug 2017
JayPrakash HeightsVijay Constructions4358%25 Aug 2021
Altamash ResidencyAbdulsattar Shaikh4221%2 Nov 2022
Rita EmpireRajesh Kashinath Prachande420%23 Feb 2026
FURDE HEIGHTS-PHASE-I,B BUILDINGSUNIL FURDE CONSTRUCTIONS PVT. LTD.425%10 Feb 2026
LAKE VIEWKachare Promoters And Developers4129%13 Jul 2023
Dream City Gowardhan ApartmentSanjay Raghunath Bagal400%4 Oct 2020
RADHA DAMODAR SANKULSHASHIKANT MARUTIRAO JIDDIMANI408%27 Dec 2024
SURYA COMPLEXSURESH AMBADAS MITTHAKOL383%27 Jun 2023
Heritage PrimeHeritage Ashcon Properties370%29 Dec 2021
Royal Residency Building No 4Shubhankar Developers370%5 May 2026
Deepgiri HeightsSachin Purushottam Kulkarni360%21 Jul 2025
Shrikhande PrideB. S. L. DEVELOPERS360%11 Aug 2025
Gayatri Vihar wing BShriniwas Ashayya Arakal350%3 Dec 2021
FLORA KALPANAIMAGE SPACE INCORPORATED350%20 Jun 2024
Yarawa ResidencyYarawa Buildcon LLP350%1 Oct 2025
PRAJAY HEIGHTSJAYKANT CONSTRUCTION3444%26 Feb 2024
SHHRADDHA ELLEGANCE BUILDING HShhraddha Properties3234%15 Dec 2022
Godavari HeightsGayatri Developers320%30 Jun 2025
Rakhi TowerSHIVA CONSTRUCTION300%16 Oct 2025
INDRADHANU-Phase-2M/S Ganesh Ramchandra Apte2910%14 Aug 2017
SHHRADDHA AVENUESHRADDHA ENTERPRISES2934%28 Apr 2023
Dnyanai ApartmentV B Lad Promoters & Builders2836%8 Jul 2021
Manidhari Empire 212Manidhari Realtors Pvt Ltd.280%24 Mar 2022
RAGHURAJ PRIDEVASTURAJ BUILDERS AND DEVELOPERS280%27 Jun 2025
Royal PragatiRoyal Buildcon & Associates280%23 Sep 2025
Gulmohar ResidencyGulmohar Residency2722%20 Mar 2025
Kalyani MajesticFarooque Ismail Kalyani2662%3 Nov 2020
VIJAYRAJ VISHVAARUNA REALTORS250%8 Dec 2025
HARISAMARTH RESIDENCYSHRI SAMARTH ASSOCIATES250%12 Jun 2026
VEER KOHINOOR TOWERVIRENDRA CONSTRUCTIONS2483%29 Jan 2019
BHOSALE PRIDEVAISHNAVI VISHAL MALAPE240%2 Aug 2023
Pushpakunj ParkManali Realty2450%18 Jun 2024
SAI SAMARTH RESIDENCYAtul Jagdish Deshpande2421%24 Oct 2025
SHINDE ARCADESHINDE AND KULKARNI ASSOCIATES240%8 Jun 2026
PARMESHWAR RESIDENCYSANJAY UTTAMPRASAD ABUTE230%31 Jul 2019
PRIME GALAXYPRIME CONSTRUCTION2370%10 Jan 2023
Samarth ResidencyAbhaykumar Malharao Edke2322%22 Mar 2024
Manmeet MandarSolapur Infracons Private Limited230%23 Jul 2025
Samruddhi HeightsPragati Associates2223%14 Mar 2024
VEDANTA ATULYAMHARESH JANI2119%7 Nov 2017
AKSHATAKISAN CONSTRUCTIONS PVT LTD215%4 Apr 2024
RN GOLI SUNDARBAN PHASE 1SHRI RAJRAJESHWARI DEVELOPERS200%14 Aug 2017
Heritage Prime Phase 2Heritage Ashcon Properties200%10 Sep 2022
Aviraj HeightsVidhyadhar Mallikarjun Akkalwadi2030%22 Sep 2023
MAHAVIR HEIGHTSARIHANT VENKATESHWARA INFRA200%11 Jun 2025
SHANTIBHUSHAN APARTMENTSShri Mauli Developers And Builders1958%22 Aug 2017
GALAXY GOLDGALAXY DEVELOPERS190%21 Jan 2021
M/S Manidhari Realtors Pvt LtdManidhari Realtors Pvt Ltd.190%30 Mar 2022
Vishwa PrideShri Samarth Associates1942%16 Oct 2023
TATHASTUTATHASTU DEVELOPERS1811%14 Aug 2017
MANJUL PLAZAASLAM BABALAL MUJAWAR1856%25 Oct 2017
Lokhandwala ParkIliyas Aziz Motiwala180%23 Mar 2020
Gajanan ComplexD S R Developers180%28 Apr 2022
KHUSHI HERITAGEKHUSHI BUILDCON1894%4 Mar 2024
VASANT VIHARV.A. DEVELOPERS180%9 Jul 2024
Pankha VihirPandhe Construction Pvt Ltd17100%19 Aug 2017
SEVEN HILLS APARTMENTSEVEN HILLS DEVELOPERS1662%5 Apr 2023
Heritage Prime phase 3Heritage Ashcon Properties140%5 Sep 2022
Manmeet AbhilashaSolapur Multicons LLP1436%29 Feb 2024
K-S BougainvilleaKaranje-Surana Constructions Pvt. Ltd.140%14 Feb 2025
R N GOLI SUNDARBAN PHASE 1 2SHUBHAM DEVELOPERS1377%9 Aug 2017
KANDRES RESIDENCY A5 BUILDINGKANDRE DEVELOPER1217%1 Oct 2025
Tirupati HarishaTIRUPATI CONSTRUCTION PRAMOTERS AND DEVELOPERS120%8 Dec 2025
GOLDEN SKYLINESAVALKAR AND SONTAKALE GROUP120%12 Jan 2026
SILVER PARKV.A. DEVELOPERS110%22 Mar 2024
Saukhya ResidencyB Square Builders And Developers100%13 Feb 2021
Kandre's Residency Building No.B2KANDRE DEVELOPER888%23 Jun 2023
RSM Heights E PhaseRAJENDRA SUKHADEV MIRGANE70%29 Aug 2018
UNIQUE PARKUNIQUEDEVELOPERS60%9 Sep 2019
Takalikars ProsperityAJIT NARSINHA TAKALIKAR520%19 Jan 2023
Ray Nagar Housing ProjectVasant Vihar Realty Pvt Ltd10%27 Sep 2018
Manmeet BlossomSolapur Infracon Pvt Ltd--4 Aug 2017
Shhraddha VishwaShhraddha Enterprises--22 Jun 2017
K-S AsterKaranje-Surana Constructions Pvt. Ltd.--31 Jul 2017
INSTYLE RESIDENCYT6 REALTY PVT LTD--29 Jul 2017
Chhoriya - RegencyPragati Infra Services Pvt. Ltd.--29 Jul 2017
AnuthamNorth West Infra--2 Aug 2017
Dream CityFuture Housing Corporation--6 Aug 2017
IMP GREENS PRAKRITI BUILDING PHASE IIIMP REALTY PRIVATE LIMITED--5 Jul 2017
Shhraddha Ellegance Building BShhraddha Properties--30 Jun 2017
SUKHADA APARTMENTSNIKHIL MANMATH RAUT--5 Jul 2017
SUNRISE HEIGHTSUNITED DEVELOPER--15 Jul 2017
KEDARNATH RESIDENCY PHASE IIPRAMOD VASANT JOSHI--15 Jul 2017
S B ICONS B MULTICONS--5 Jul 2017
BALAJI PARADISESHRINIWAS ASSOCIATES--29 Jul 2017
BLUE MOONPRECISION REALTY--18 Jul 2017
Tembhurni Prime City Mall - Wing - A - GF And FF - Phase - A1Dhariwal And Chhoriya Buildcon Pvt Ltd--14 Aug 2017
Tembhurni Prime City Mall - Wing - B - GF And FF - Phase - B1Dhariwal And Chhoriya Buildcon Pvt Ltd--22 Aug 2017
HARSHWARDHAN RESIDENCYYASHWARDHAN CONSTRUCTIONS PVT LTD--12 Jul 2017
Mayuresh Residency Bldg 2Devendra Vasudeo Sangolkar--29 Jul 2017
Shhraddha Ellegance Building CShhraddha Properties--20 Jul 2017
SAMRUDDHI GREENSNAGNATH SHIVSHANKAR AKKALKOTE--18 Jul 2017
KIMAYA MAYURSHRISAMIR AMRUT GANDHI--23 Jul 2017
SOHAM HEIGHTSMetroDevelopers--31 Jul 2017
AMBAL TOWERARCHANA DAYANAND AMBAL--6 Aug 2017
MANGAL VIHAR WING BMANGAL CONSTRUCTION--31 Jul 2017
SAIRAJ VIHARARJUN ANANT WAGHMARE--8 Aug 2017
DIVYARATNA RESIDENCYIDHANT CONSTRUCTION AND DEVELOPERS--25 Jul 2017
SHALIMAR RESIDENCYMOHAMMED HANIF ANWAR MOTIWALA--23 Jul 2017
Tembhurni Prime ParkDhariwal And Chhoriya Buildcon Pvt Ltd--14 Aug 2017
HIra HeightsMayura Promoters And Developers Pvt. Ltd.--6 Aug 2017
Athrva PrideDevendra Vasudeo Sangolkar--27 Jul 2017
Sai PalacioSATISH MALANBAI ANDHARE--6 Aug 2017
Sanvi ArcadeSantosh Dattatraya Kalkutgi--9 Aug 2017
PEACE HEIGHTSS M PROPERTIES--29 Jul 2017
NAKSHTRA PRESTIGEM/S NAKSHTRA DEVLOPERS &BUILDERS--14 Aug 2017
G N HEIGHTSG N DEVELOPERS--17 Aug 2017
Gadsing EmpirePradeep Shankar Gadsing--29 Jul 2017
SHOPPERS SQUAREYUSUF JAMAL SHAIKH--9 Aug 2017
RUSHI HEIGHTSMEGHASHAM MALLIKARJUN YEMUL--19 Aug 2017
Aradhana HomesABHINANDAN DAGADU RATHOD--7 Aug 2017
RAGHAVENGRA BHUVANAMRAGHVENDRA CONSTRUCTION--22 Aug 2017
Jijau ResidencyJay Construction--14 Aug 2017
SHRI VYANKATESH NAGAR BUILDING B PURANDAR APARTMENT AND BUILDING C PRATAPGAD APARTMENTSHRI VYANKATESH DEVELOPERS--31 Jul 2017
PANTNAGAR SARITA BUILDING CHANDRABHAGAPARICHARAK BUILDERS AND DEVELOPERS PVT LTD--22 Aug 2017
Shree Vishwa ResidencyKishor Rajendra Sanjekar--15 Sep 2017
MOTI MAHALKarishma Developers--9 Aug 2017
PRIME RESIDENCYPRIME CONSTRUCTION--11 Aug 2017
TRIANGLE TOWERSURESH SHIVRAM KASHID--14 Aug 2017
Peshwai AppartmentRajeshri Balkrishna Devadikar--31 Aug 2017
RUSHI CELEBRATIONMEGHASHAM MALLIKARJUN YEMUL--24 Aug 2017
Suryoday HeightsRahul Developers--17 Aug 2017
Mayuresh PrideSHRI MAYURESH CONSTRUCTION--4 Aug 2017
KUSHI RESIDENCYSHRI R N GOLI DEVELOPERS--17 Aug 2017
SAI SUPREMESATISH MALANBAI ANDHARE--22 Aug 2017
RUSHI PRIDEMEGHASHAM MALLIKARJUN YEMUL--14 Aug 2017
97 PALMSSUSHILA NANDKISHOR JAJU--19 Aug 2017
RAMCHANDRA EMPIRESHRI R N GOLI DEVELOPERS--11 Aug 2017
R N GOLI CELEBRATIONSHRI R N GOLI DEVELOPERS--9 Aug 2017
KALPITA HEIGHTSSHRI R N GOLI DEVELOPERS--9 Aug 2017
IMPERIAL TOWERABDUL RASHEED ABDUL GANI BADEWALE--6 Aug 2017
Sayali HeightsRahul Developers--31 Aug 2017
Greens Block AShree Siddhi Sambhav Developers--22 Aug 2017
Samartha ResidencyM/s Samruddhi Realty--11 Aug 2017
GULMOHAR PLAZASUNIL UTTAMRAO FURDE--17 Aug 2017
SUKHADEV NAGAR PHASE I PART 1RAJENDRA SUKHADEV MIRGANE--14 Aug 2017
Preshak PresidencyPreshak Infrastructure and Holding Co.--27 Aug 2017
Sun City Wing B2CHATUR PROPERTIES PVT LTD--14 Aug 2017
INDRADHANU Phase-3M/S Ganesh Ramchandra Apte--22 Aug 2017
MAHAVEER VIHARMAHAVEER DEVELOPERS AND BUILDERS--16 Aug 2017
MOTIWALA HEIGHTSAYYUB USMAN MOTIWALA--4 Aug 2017
Marvella Luxurious A Wing Phase ISURATWALA BROTHERS--17 Aug 2017
INDRAPRASTHA-Phase-2M/s Apte Reality--22 Aug 2017
NIRMITI ARMAANNIRMITI DEVELOPERS--16 Aug 2017
Bhargavi ResidencyAmol Suresh Yadav--21 May 2018
MAHALAXMI APARTMENTPRAVIN VITTHAL MORE--18 Aug 2017
SAMARTH VIHARSHIRISH DATTATRAY KULKARNI--14 Aug 2017
suvidha galaxysuvidha developers--18 Aug 2017
SHRI PAWAN APARTMENTSHRINIWAS HANMANTU YANGANTI--1 Sep 2017
Shree ResidencyHEMENT DAMU PINGALE--11 Aug 2017
Om Shhraddha Height Phase IIOm Shhraddha Realty--16 Aug 2017
MOTIWALA PRIDEAYYUB USMAN MOTIWALA--9 Aug 2017
FLORA CASASynergy Infra--17 Aug 2017
Vasant Vihar GulmoharPandhe Infracons Pvt Ltd--22 Aug 2017
Bhargavi HeightsAmol Suresh Yadav--25 Aug 2019
Vasant Vihar Phase IIIPandhe Infracons Pvt Ltd--31 Aug 2017
CRYSTAL TOWERASIF SATTAR PATHAN--23 Aug 2017
AMARS WONDERLANDM/s PRAGATI REALTY--11 Aug 2017
Shree HeritageHemant Damu Pingale--1 Sep 2017
Arihant ComplexAdya Constructions--15 Jan 2018
SATYA SHANTI VIHARANWARHUSEN MAHAMUD SHAIKH--31 Aug 2017
BHUDEVI TOWERSHRUSHTI DEVELOPERS--7 Sep 2017
GALAXY PANACHEGALORE DEVELOPERS PRIVATE LIMITED--17 Aug 2017
PAWAN RESIDENCYVYANKATESHWARA DEVELOPERS--7 Sep 2017
Shindeshahi PhaseIITIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS--30 Oct 2017
SKY-ONEYUSUF JAMAL SHAIKH--16 Aug 2017
Vrundavanam Phase IRoyal Realtors--17 Aug 2017
Swapna PushpaPushpam Infra LLP--31 Aug 2017
IRIS RESIDENCYRathi Infracon--31 Aug 2017
GOKULDHAMRUSHABH DEVLOPERS--15 Sep 2017
VIJAYRAJ MARVELARUNA AMAR BIRAJDAR--9 Oct 2017
Shree Shambhavi ResidencyRSDevelopers--14 Sep 2017
SUNSHREESANTOSH NAGESH SURWASE--4 Oct 2017
PIONEER ICON WING APIONEER PROMOTERS AND DEVELOPERS--21 Sep 2017
Anandam Vihar Phase I WING ASV SMART CITY DEVELOPERS--25 Oct 2017
Picaka GalaxySwapnil Suhas Raut--27 Oct 2017
S. S. ICON - PHASE IS S INFRASTRUCTURE--27 Oct 2017
KAMTAM ICON A WINGPRAKASH SHANKAR KAMTAM--23 Oct 2017
SAEE RESIDENCYM S CONSTRUCTIONS--7 Nov 2017
Vardhaman ResidencyAMAR KALYANI BIRAJDAR--25 Oct 2017
Shree Varad ResidencyMr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty--2 Nov 2017
Narhar ComplexYamuna Developers--2 Nov 2017
SIDDHIVINAYAK HIGHTSSAI DEVELOPERS--5 Dec 2017
RALERASKAR HEIGHTSNITIN SADANAND KULKARNI--24 Jul 2018
JV SQUAREJay Group--31 Jan 2018
Swapna Pushpa Phase IIPushpam Infra LLP--9 Nov 2017
S M RESIDENCYSHRISHAIL SIDRAMAPPA MAKANE--29 Nov 2017
DEGAONKAR APARTMENTPRASAD PRAKASH DEGAONKAR--15 Dec 2017
Lokhandwala PrestigeLokhandwala Builders--26 Dec 2017
SAHYADRI RESIDENCYSHALAN TANAJI DAMARE--26 Dec 2017
SAI PARADISESUNRISE DEVELOPERS--15 Dec 2017
GRISHMASHRI MAULI BUILDCON--20 Dec 2017
VIJAYRAJ MANORAMAR KALYANI BIRAJDAR--31 Jan 2018
Sarathi Estatevikas popatrao savant--9 Jan 2018
VANGA APARTMENTSADANAND SOMMAYYA VANGA--15 Jan 2018
ROYAL RESIDENCYSHUBHANKAR DEVELOPERS--11 Jan 2018
SHIVSMRUTI RESIDENCYBHAIRAVNATH DEVELOPERS--9 Jan 2018
Pearl HeightsFair Deal Constructions--24 Apr 2018
Hari Har ResidencySHRI SWAMI SAMARTH CONSTRUCITON--8 Feb 2018
SARYASH APARTMENTSARYASH CONSTRUCTIONS--13 Apr 2018
SMRUTIGANDHA APARTMENTSUNIL UTTAMRAO FURDE--15 Feb 2018
Shindeshahi ResidencySIDDHANATH CONSTRUCTION & DEVLOPERS--23 May 2018
City Center TowerCity Centre Developers--3 May 2018
INDRADHANU-Phase-5M/S Ganesh Ramchandra Apte--28 Mar 2018
VED RESIDENCYSANJAY VISHWANANTH HANKARE--7 Aug 2018
Ashoka TowerMaya Builders & Developers--25 May 2018
BHAVANI RESIDENCYBHAWANI DEVELOPERS--10 Apr 2019
Tembhurni Prime City Mall - Wing A - Smart Office - Phase A2Dhariwal And Chhoriya Buildcon Pvt Ltd--3 Oct 2018
Shri Audumbar PlazaTIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS--23 Mar 2020
SHIV SHRUSTIGAYATRI DEVELOPERS--28 Aug 2018
Chandak SnehShruti Kishor Chandak--11 Oct 2018
BALAJI REGENCYAAKRUTI BUILDERS AND DEVELOPERS--6 Dec 2018
SANSKRUTI TOWERRUGVED CONSTRUCTION CO--10 Dec 2018
AANANDAM VIHAR PHASE I WING B AND CSV SMART CITY DEVELOPERS--29 Jan 2019
AARYA RESIDENCYNITIN HUKUMCHAND RATHOD--19 Mar 2019
Constructing 288 t/s EWS on gat no 238/1 KarmalaPune Housing and Area Development Board Pune--14 Feb 2019
Hari Mohan ParkSHRI SWAMI SAMARTH CONSTRUCITON--5 Apr 2019
GLOBAL ICONGLOBAL CONSTRUCTIONS--26 Mar 2019
KIMAYA SWAPANAPURTI PHASE IALACRITY CONSTRUCTIONS PVT LTD--21 Feb 2019
Rastratej Atal Projectajan homes private limited--11 Mar 2019
Sukhdev Nagar Phase 2RSM NEST DEVELOPERS--5 Mar 2019
SUNRISE RESIDENCYMOHAMMED HANIF ANWAR MOTIWALA--29 Mar 2019
Sukhdev Nagar Phase 3RSM NEST DEVELOPERS--9 Apr 2019
Aryash ResidencyAbhijeet Ajit Takalikar--2 Apr 2019
Shubharambh - Wing BVeer Housing Projects LLP--5 Apr 2019
Pawan HeightsH P Developers--22 Apr 2019
MALHAR HEIGHTSSAI SAMARTH DEVELOPERS--27 May 2019
DARGOPATIL APARTMENTAJINKYA CONSTRUCTIONS--23 May 2019
SUYOG SHRUSHTISUYOG DEVELOPERS--10 Jun 2019
SHRI VITTHAL RUKMINI VYAPARY SANKULbalrkishna jagnnath lad--26 Jun 2019
SHREE KRUSHNA PANDHARI TOWERSYOGESHWAR BUILDCON--21 Jun 2019
SHAKUNTAL NAGAR -PHASE 4KAPIL PANDURANG DINGARE--28 Jun 2019
SHISHIRSHRI MAULI BUILDCON--5 Jul 2019
JABs Shaheen ArcadeIrfan Chitasaab Khairdi--19 Jul 2019
Mayuresh Residency Phase 2Devendra Vasudeo Sangolkar--19 Jul 2019
DESHBHAKTA HARINARAYAN SONI CITY D-WINGSoni Somani Infrastructure--22 Jul 2019
S B PEACE CORNERS B CONSTRUCTION--27 Aug 2019
Murudkar Manor Phase -1Murudkar Doyens--14 Jan 2020
INDRAPRASTHA RESIDENCYYASHWARDHAN CONSTRUCTIONS PVT LTD--28 Aug 2019
Lokhandwala HeritageLokhandwala Builders--9 Sep 2019
KHUSHI HEIGHTSKHUSHI BUILDERS AND DEVELOPERS--16 Sep 2019
FLORA GALAXIAIMAGE SPACE INCORPORATED--4 Sep 2019
RSM Unity DevelopersRSM Unity Developers--28 Aug 2019
OM RESIDENCY PHASE IIOMKARA HOME CONSTRUCTION PRIVATE LIMITED--9 Oct 2019
Shindeshahi ResidencyMaruti Narayan Shinde--22 Nov 2019
Moraya ResidencyGAVASANE BUILDERS--30 Oct 2019
Golden TowerSAMIR WALMIK AHIRE PROPRIETOR OF PALLAVI REALTORS--30 Oct 2019
SHREE GURURAJ PARKGAYATRI BUILDERS AND DEVELOPERS--3 Jan 2020
RAJYOG RESIDENCYNIRMITEE DEVELOPERS&BUILDERS--1 Nov 2019
Akruti HeightsAkruti Constructions--9 Dec 2019
SAI RESIDENCYSAIBUILDERS AND DEVELOPERS--28 Jun 2020
Mahalaxmi apartmentnagesh Laxman Takmoge--5 Feb 2020
AASHRAYKISAN CONSTRUCTIONS PVT LTD--21 Jan 2020
Construction of 2092 DUs for EWS under AHP vertical of PMAY Scheme - Phase IPANDHARPUR MUNICIPAL COUNCIL--9 Jan 2020
MAHAVEER TOWERMAHAVEER DEVELOPERS AND BUILDERS--16 Jan 2020
Sarthaki ResidencySeema Umesh Gatkal--30 Jan 2020
Manmeet Blossom Wing BSolapur Infracon Pvt Ltd--23 Mar 2020
MAHALAXMI RECEDENCYSATYABHAMAVITTHAL CONSTRUCTION AND LAND DEVELOPERS PRIVATE LIMITED BARSHI--2 Mar 2020
TULJAI RECEDENCYSATYABHAMAVITTHAL CONSTRUCTION AND LAND DEVELOPERS PRIVATE LIMITED BARSHI--11 Feb 2020
Prayag HeightsNingdalli Associates--18 Mar 2020
KRUSHNA TOWERSANGITA MADHUSUDN PATANGE--9 Mar 2020
AKSHAY LABHNITIN HUKUMCHAND RATHOD--24 Feb 2020
DAS SANKULCHHAYA KAMALAKAR CHAFEKAR--18 Feb 2020
Shree Renuka ApartmentTIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS--23 Mar 2020
Sai SonetRamesh Vishwanath Ajari--18 Mar 2020
Rushi AvenueMeghshyam Mallikarjun Yemul--18 Mar 2020
Pearl ResidencyFairdeal constructions--7 Nov 2020
SHRDHA DEVELOPERSSHRDHA DEVELOPERS--23 Mar 2020
KRISHNA COMPLEXSHASHIKANT MARUTIRAO JIDDIMANI--3 Jun 2020
VIDYARATNA RESIDENCYSEEMA VIDHYARATNA PHADTARE--7 Nov 2020
ShivalayaMillenium Enterprises--10 Nov 2020
Pujari C.T.TIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS--28 Oct 2020
Galaxy apartmentSP Constructions--12 Aug 2020
Motimahal residencyKarishma Developers--30 Aug 2020
Synchron Prime SquareYusuf Jamal Shaikh--2 Sep 2020
MANALI PLAZAGLOBAL INFRASTRUCTURE--20 Aug 2020
KRISHNANGANMINIYAR BUILDERS AND DEVELOPERS--21 Aug 2020
CAPITAL GANGASHREE SURYA PROMOTORS AND BUILDERS--19 Nov 2020
Ameena ApartmentIliyas Tajammul Ustad--7 Sep 2020
SAI RESIDENCY BVIJAYKUMAR PUNDLIKRAO KATHARE--11 Sep 2020
Roshan ApartmentRoshan Builders & Developers--26 Sep 2020
Bhumayya ResidencyRamkrishna Bhumayya Yemul--31 Oct 2020
KHUSHI BLOSSOMKHUSHI BUILDERS AND DEVELOPERS--10 Oct 2020
BHAGIRATHI HEIGHTSHANMANTU KOMARAYYA BURA--25 Oct 2020
Shri Samrat ResidencyShree Construction--7 Nov 2020
Lokmangal oxyparkLokmangal Properties--15 Jan 2021
JAGNNATH PURAM PHASE ISAHAYOG DEVELOPERS--18 May 2021
Nirmiti SakuraM/S Nircon Developers--14 Dec 2020
JAGNNATH PURAM PHASE IISAHAYOG DEVELOPERS--1 Dec 2020
MAGESTY BLOSSOMMAGESTY BUILDERS & DEVELOPERS--18 Feb 2021
CORAL BUSINESS CENTERKhamitkar Properties--3 Jan 2021
MAHESHWARI HEIGHTSMAHESHWARI HEIGHTS--4 Jan 2021
Karnul ApartmentRoyal Builders And Developers--8 Jan 2021
Gulmohar SquareSquare One Builders & Developers--3 Jan 2021
Aastha ResidencyNitin Hukumchand Rathod--18 Feb 2021
Crown PlazaMohammad Irfan Abdul Latif Attar--18 May 2021
Global City ViewGlobal Constructions--27 Jan 2021
Pearl ApartmentFairdeal constructions--21 Jan 2021
Chandrama ApartmentAshok Shankar Gandhi--27 Jan 2021
Sharda HeightsVijay Constructions--31 Jul 2021
Damyanti PlazaShridatta Builders And Developers--25 Jan 2021
Moreshwar And Tamboli HeightsSumit Developers--18 Feb 2021
MHDC JV MAJREWADI SOLAPUR PMAY PROJECTMAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED--18 Feb 2021
RAMSWAMI ROW HOUSERAMESH RAMSWAMI KAMUNI--22 Feb 2021
JAYENDRA ARCADEJayant Dinkarrao Holeypatil--5 Apr 2021
INDRADHANU-Phase-7M/S Ganesh Ramchandra Apte--25 Mar 2021
I SQUARESHRINIWAS NARSAYYA IPPAKAYL--5 Apr 2021
MOTIWALA GALAXYAYYUB USMAN MOTIWALA--7 Apr 2021
Rushi PearlMeghshyam Mallikarjun Yemul--15 Apr 2021
BHAGWAN RESIDENCYRUPESH VASANT BHADULE--23 Apr 2021
SHRI RADHA KRISHNA RESIDENCYSHRI SIDDHIDATA BUILDERS AND DEVELOPERS--26 Jun 2021
VARDHAMAN RESIDENCY PHASE-2AMAR KALYANI BIRAJDAR--10 May 2022
MALAPE PRIDEBAGAL NARSALE AND MALAPE DEVELOPERS--4 Jul 2021
Rushi MarvelMeghshyam Mallikarjun Yemul--3 Nov 2021
GALAXY 52Swapnil Suhas Raut--23 Oct 2021
Darul HamdS M Realty--15 Jul 2021
Mahesh ResidencyRathi Infracon--17 Aug 2021
Venkateshwara Seven HillsRAHUL DEVELOPERS--5 Aug 2021
Global HightsGlobal Constructions--25 Aug 2021
Hundekari ResidencyAmmar Construction Solution--30 Aug 2021
Krishna HeightsKrishna Heights--25 Oct 2021
Central IconUsman Hassam Mansuri--8 Sep 2021
Padmavati PlazaPopat Rajaram Patil--30 Aug 2021
Krushna BaghNagesh Laxman Takmoge--1 Sep 2021
Shivaji ApartmentRohini Dattatray Bagal--13 Sep 2021
Signature SquareMohsin Haroon Shaikh--22 Nov 2021
Al Safa ResidencyH S Motiwala Builders--23 Oct 2021
Silver Oak PrimeSkyline builders & Developers--8 Sep 2021
Kotkunde residencyMurtuz Abdul Razzaque Kotkunde--13 Sep 2021
Central ParkUsman Hassam Mansuri--15 Dec 2021
Siddha-Trimbak TowerMinakshi Jayprakash Jankar--29 Nov 2021
ARVIND VIHARLAXMIBAI ARVIND AMBAL--1 Oct 2021
Metros zaheer plazaAbdulsattar Shaikh--23 Oct 2021
VIJAYRAJ ARUNODAYRAJLAXMI AMAR BIRAJDAR--23 Oct 2021
Millennium TowerHamid Ramzansab Shaikh--31 Oct 2021
RAMALAYAMDIDDI INFRACON--3 Nov 2021
AL Awwal HeightsSarfaraz Allauddin Barchi--17 Dec 2021
ADITYA VIHAR KURUDUWADINAGNATH SHIVAJI PARKALE--22 Feb 2023
INDRADHANU-Phase-8M/S Ganesh Ramchandra Apte--24 Nov 2021
NIRMITI LANDMARKNIRMITI DEVELOPERS--29 Jan 2022
SHRI BHANDARE HEIGHTSGOKUL CHANDRAKANT BHANDARE--11 Jan 2022
JAHAGIRDAR RESIDENCYPARWEZ ISAK JAHAGIRDAR--24 Jan 2022
BAITUL FALAHVIJAYRAJ ENTERPRISES--24 Jan 2022
Barchi AvenuoSarfaraz Allauddin Barchi--22 Jun 2022
SANKALP HEIGHTSDaiwik Developers--24 Jan 2022
Yaseen SquareMohsin Haroon Shaikh--28 Apr 2022
Punjabi SquareMohsin Haroon Shaikh--20 Apr 2022
Alif SquareMohsin Haroon Shaikh--10 May 2022
Harikrupa residencyShri Samarth Construction--22 Feb 2022
Bajirao HeightsShekhar Bajirao Jadhav--14 Jan 2022
Royal TowerRoyal Infra--2 Feb 2022
RADHAKRISHNA AVENUEMAINAVI CONSTRUCTION AND DEVELOPERS--22 Feb 2022
Maheshwari HeightsMaheshwari Developers And Builders--2 Feb 2022
GURUKRUPA RESIDENCYGIRISH GURAPPA SAKHARE--16 Feb 2022
Rajdeep homesRajiv Ramchandra Dipali--20 Apr 2022
MANGAL VASUDHAMANGAL CONSTRUCTION--17 Mar 2022
Sahil CornerEtihad Builders And Developers--8 Mar 2022
Shri Soham HeightsSharanappa Urf Annarao Birajdar--4 Apr 2022
Sudarshan HeightsShri Mahalaxmi Builders And Developers--2 Mar 2022
Madur SquareShri Mahalaxmi Developers--20 Oct 2022
STAR ICON RESIDENCYNAZNEEN JAINODIN NADAF--5 Sep 2022
SARASWATHI HEIGHTSHANMANTU KOMARAYYA BURA--24 Mar 2022
MAHESHWARI CONSTRUCTIONRAMESH RAMSWAMI KAMUNI--28 Apr 2022
MHDCL KASBE SOLAPUR PMAY PROJECTMAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED--15 Jun 2022
Royal ApartmentImran Mohammed Ismail Attar--28 Apr 2022
Aryash PristineAbhijeet Ajit Takalikar--28 Apr 2022
SIDDH-KHUSHI COMPLEXKHUSHI BUILDERS--10 May 2022
Killedar HeightsMumtaj Ibrahim Killedar--18 May 2022
KIMAYA PRIMESAMIR AMRUT GANDHI--1 Dec 2022
Ambaji EmpireShaan Builders and Developers--20 Jun 2022
KAMUNI COMPLEXPHOENIX ASSOCIATES (AOP)--18 May 2022
KUBER HEIGHTSBHAGYODAY DEVELOPERS (A.O.P.)--18 May 2022
ASHAAI RESIDENCYGayatri Developers--16 Sep 2022
Shalimar HeightsShalimar Developers--20 Jun 2022
Alif ResidencyOrion Developers--20 Jun 2022
MANGALMURTI RESIDENCYGAVASANE BUILDERS--22 Jun 2022
Ascent TowerRoyal Infra--20 Jun 2022
Roseland Apartments Building C and DRoseland Residencies--20 Jun 2022
Tirupati Royal HomesTIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS--28 Nov 2022
JAY VIJAY RESIDENCYSHWETA JAYANT HOLEYPATIL--5 Apr 2023
ShivMalhar ComplexSAISAMARTH DEEP DEVELOPERS--26 Sep 2022
SUDHIR PATILS BUSINESS SQUARESUDHIR GUNDERAO PATIL--21 Nov 2022
SHRI PANDURANG REIDENCYMNK BUILDERS AND DEVELOPERS--7 Dec 2022
Nikunj ResidencySudarshan Umakant Chakre--2 Nov 2022
SNC GRAND RESIDENCEA S D C DEVELOPERS--26 Sep 2022
Majestic SquareMohsin Haroon Shaikh--19 Oct 2022
Laxminarayan HillsVijayshree Construction And Developers--1 Dec 2022
High MarkNishat Motiwala--21 Nov 2022
GODHAWARI HEIGHTSHANMANTU KOMARAYYA BURA--7 Feb 2023
Bhaiji ApartmentBHAIJI APARTMENT--28 Nov 2022
FLORA GRANDVIEWIMAGE SPACE INCORPORATED--17 Jan 2023
SHELAR COMPLEXVIJAY SHRIRANG SHELAR--3 Jan 2023
Atharv Pride Phase 3Devendra Vasudeo Sangolkar--10 Jan 2023
JAYDEV HEIGHTSAshwini Facility Creators LLP--1 Apr 2023
VIDYASHREE RESIDENCYGHADAGE PATIL DEVELOPER--13 Jan 2023
FLORA ICONIMAGE SPACE INCORPORATED--12 Jan 2023
ESTIAMaheshwari Developers--7 Feb 2023
VIJAYRAJ OM SHRUTI SOURABHVIJAYRAJ REALTORS--22 Feb 2023
Crown ResidencyBhramha Developers--7 Feb 2023
Kohinoor MajesticParvej Aslam Mujawar--30 Jan 2023
Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIGPune Housing and Area Development Board Pune--16 May 2024
Saffron SquareMohsin Haroon Shaikh--5 Apr 2023
Global AvenueGlobal Infracon--24 Jan 2023
H and H HeightsVNS Builders and Developers--22 Feb 2023
TOWER A , GROUP HOUSING AT GAT NO. 637/1/4MARVAL CONSTRUCTION AND DEVELOPERS--1 Feb 2023
MANGAL RESIDENCYPRADNYA ABHIJIT PATIL--5 Apr 2023
TULSI APARTMENTSHRISAI VISHWA BUILDERS AND DEVELOPERS--28 Apr 2023
UNIQUE PARKUNIQUE DEVLOPERS--19 Jul 2023
Harikrupa HeightsShri Samarth Construction--15 May 2023
Shivalay ResidencySakar Construction--14 Jun 2023
Motiwala SkylineAYYUB USMAN MOTIWALA--6 Mar 2023
Sonal ParadiseLadubai Naghnath Babar--6 Mar 2023
E GalaxyShaileshkumar Sharadkumar Ekbote--3 May 2023
Mayresh Residency Phase 2 Building C and DDevendra Vasudeo Sangolkar--21 Apr 2023
ALTAMOUNTMaheshwari Developers--21 Apr 2023
Royal CrownRoyal Buildcon--28 Apr 2023
Regal IconVighnesh Developers--21 Apr 2023
VIGNHARTA RESIDENCYMAHESH ANNARAO THOBADE--15 May 2023
SHAZNEEN GALAXYNAZNEEN JAINODIN NADAF--8 Jun 2023
ROYAL RESIDENCY BUILDING NO 2SHUBHANKAR DEVELOPERS--6 Nov 2023
SHRI RAM SANKUL APPARTMENTCHHAYA KAMALAKAR CHAFEKAR--13 Jul 2023
Swami Samarth RegencyShri Swami Samarth Developers--21 Nov 2023
Kotkunde CrownMurtuz Abdul Razzaque Kotkunde--27 Jun 2023
Pinnacle 33 AvenueRanjeet Kantilal Shah--8 Sep 2023
Moti Mahal ApartmentKarishma Developers--13 Jul 2023
Sun City SapphireChatur Properties Pvt Ltd--22 Sep 2023
SwapnshilpRoyal Buildcons--7 Jul 2023
Skyline ResidencyShree Constructions--27 Jun 2023
Shree Ekdant HeightsMahesh Mahantappa Hatte--17 Oct 2023
Ethos KrishnaGoodwill Developers--22 Sep 2023
Icon TowerSameer Shrikant Tadawalkar & Deepak Navnath Alkunte--8 Sep 2023
Vivek HeightsAzam Ismail Saifan--19 Dec 2023
KAMTAM ICON WING BVISHWA DEVELOPERS--11 Dec 2023
Patel PlazaEhsan Construction--2 Apr 2024
Rushi RichMeghshyam Mallikarjun Yemul--15 Jan 2024
Nilayam HeightsSachin Purushottam Kulkarni--14 Mar 2024
UNIQUE PARK PHASE 1UNIQUE DEVLOPERS--5 Jun 2024
Adinath ApartmentArchit Developers--15 Feb 2024
Necklace PrideMukhtiyar Shahadat Maindargi--2 Apr 2024
Construction of 224 LIG Residential T/S on Land Bearing Survey No 25A/1 Pandharpur Dist SolapurPune Housing and Area Development Board Pune--9 Jul 2024
SOMNATH HEIGHTSSandeep Shivrudra Mokashi--28 Jun 2024
Green OneMohammed Jaweed Nasiruddin Lunje--23 Apr 2024
CENTRE COURTMaheshwari Developers--11 May 2024
INFINITY ENCLAVEINFINITY REALITY--3 Jul 2024
B9 LifestyleDinesh Khushiram Agrawal--29 Jul 2024
Aakruti HeritageAakruti Developers--10 Jul 2024
Kaizen EmeraldSwapnil Nalin Kothadia--7 Nov 2024
Shivtej PlazaSomanath Jagnnath Nikam--12 Dec 2024
DAKSH RESIDENCYBHAGYODAY BUILDERS--12 Dec 2024
Bahava ApartmentTauseef Jaweed Shaikh & Jaweed Gulam Shaikh--17 Dec 2024
GAWADE HEIGHTSSWATI AJITKUMAR GAWADE--29 Oct 2024
Laxmi ResidencyLaxmikant Infra--13 Jan 2025
Lotus ApartmentLotus Apartment--20 Jan 2025
Royal HeritageMahadev Iranna Akalwadi--3 Feb 2025
KrishnalayamDiddi Infracons--10 Feb 2025
Shri Pralhad Smurti ResidencyVijayratna Developers--18 Feb 2025
Dwarkadhish EnclaveVaishnavi Construction--3 Mar 2025
Maner ComplexJahir Jamal Maner--6 Mar 2025
Madhusudan HeightsSuyash Developers--17 Mar 2025
Unique ResidencyUnique Developers--24 Mar 2025
Shivyogi ResidencyMohan Hiromal Sachdev--18 Apr 2025
Skyline SpringsSkyline builders & Developers--6 May 2025
Samruddhi ApartmentAshwa Vishwa Builders Private Limited--13 May 2025
Shantais ParadiseShri Samarth Construction--16 Jun 2025
Mithila Golden HeightsAim Properties--3 Jul 2025
VIJAYRAJ SAMRUDDHIOm Realtors--1 Aug 2025
VIJAYS THE PRESTIGEGAVASANE AND KHED BUILDERS--5 Feb 2026
Planning a launch in Solapur? The area consolidated report packs launches, inventory movement, unit sizes and absorption across the projects you pick into one document. Rs 2,999 for the first project and Rs 1,999 for each additional one. Area report · Rs 2,999 · coming soon  See what is coming

Developers active in Solapur

M/S Ganesh Ramchandra Apte (8), Dhariwal And Chhoriya Buildcon Pvt Ltd (7), Mohsin Haroon Shaikh (6), Gayatri Developers (5), IMAGE SPACE INCORPORATED (5), Devendra Vasudeo Sangolkar (5). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Solapur projects listed above?

Compare each project against its neighbours, not against the brochure. The median project on this page is 18% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Solapur project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What stamp duty will I pay on a flat in Solapur district?

The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.

What does it mean that some Solapur registrations have lapsed?

A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.

What if a Solapur project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Data from official MahaRERA filings.