New projects and RERA data in Solapur district, Maharashtra
554 projects are registered in Solapur district: 21,638 units across them, 19 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 554 covered registrations, 87 have revised their promised completion date and 3 declare litigation. The median project here is 15% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.
Also free on ReraGenie: a monthly RERA report for the seven biggest markets in Maharashtra (Pune, Mumbai, Thane, Navi Mumbai, Nagpur, Nashik and Vasai-Virar): what registered that month, the possession pipeline and the busiest pincodes, from the filings. See the latest editions.
When Solapur projects promise possession
Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 554 projects with a promised date, 173 are recorded delivered, 161 are still on the register and 220 have a registration that has lapsed or been cancelled.
DeliveredOn the registerRegistration lapsed or cancelled
196 projects promise possession in 2026 or later. Facts as per filings on RERA website.
16,592 flats are promised in 2026 or later, across the 54% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.
How far Solapur possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 87 of 554 projects (16%) have moved at least once; the median move is 24 months and the longest is 191 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Permissions and land in Solapur
Who sanctions building in Solapur
127 of the 554 registrations on this page name the body that sanctioned their building plan. The rest leave that box empty, which is a gap in the filing and not a project without permission: the commencement certificate is filed as a separate document and is on the file for most projects. The body named here is where a commencement or occupancy certificate is verified.
| Sanctioning authority | Projects |
|---|---|
| Solapur Municipal Corporation | 74 |
| Pandharpur Municipal Council | 12 |
| Pandharpur Municipal Corporation | 7 |
| 29 other bodies | 34 |
One body is often filed under several spellings, and those are counted together. Acronyms that could mean two different bodies are not: PMC is Pune or Pimpri Chinchwad depending who typed it, so it is counted as filed.
Whose name the land is in
Every one of the 554 registrations on this page answers this: on 339 the promoter is the only owner named; on 204 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 11 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.
Where in Solapur: projects by taluka
554 of the 554 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Solapur North | 396 | 71% |
| Pandharpur | 72 | 13% |
| Barshi | 38 | 7% |
| 9 other talukas | 48 | 9% |
Projects in Solapur
Showing 1 to 60 of 554 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Ray Nagar Housing Project Phase 2KUMBHARI TO DARGANHALLI ROAD, 413007 | Vasant Vihar Realty Pvt Ltd | 7882 | 5% | 28 Sep 2018 | Registered |
| PMAY BARSHI NAGAR PARISHAD AHPBARSHI NAGAR PARISHAD, 413401 | BARSHI NAGAR PARISHAD | 1607 | 12% | 31 Oct 2022 | Registered |
| R M Dhariwal Township Velapur PlottingVelapur, 413113 | Dhariwal And Chhoriya Buildcon Pvt Ltd | 512 | 63% | 4 Aug 2017 | Completed |
| Kurdu Plotting on Gat No 264Kurudwadi, 413208 | Pragati Infra Services Pvt. Ltd. | 508 | 85% | 24 Aug 2017 | Completed |
| CHHORIYA TOWNSHIP WAKHARI PANDHARPUR PHASE 3A/P - Wakhari , Pandharpur, 413304 | Chhoriya Properties And Development Company | 423 | 0% | 18 Feb 2021 | Registered |
| Chhoriya Township - Karmalakarmala, 413203 | Chhoriya Properties | 412 | 46% | 17 Aug 2017 | Completed |
| ANANTA SOLAPURSolapur (M Corp.), 413008 | PROPWIZZ INFRA LLP | 385 | 42% | 31 Aug 2017 | Registered |
| VARAD NAGARIMOUJE NAGOBACHIWADI, 413401 | M/S SHRIRAM BUILDERS & DEVELOPERS | 344 | 4% | 24 Jan 2023 | Completed |
| MHDCL ANTROLIKAR NAGAR SOLAPUR PMAY PROJECTANTROLIKAR NAGAR, 413003 | MAHARASHTRA HOUSING DEVELOPMENT CORPORATION LIMITED | 340 | 0% | 28 Apr 2022 | Registration lapsed |
| SAMRUDDHI PARKWAYNEAR RUPA BHAVANI TEMPLE, 413002 | NAGNATH SHIVSHANKAR AKKALKOTE | 331 | 21% | 22 Nov 2021 | Registered |
| Niyojit Shri Somvanshiya Sahastrarjun Kshatriya Samaj Mahalaxmi Grih Nirman SansthaSolapur North, 413005 | Anukarati Homes Private Limited | 288 | 76% | 21 Jun 2024 | Registered |
| The Platino Wing A, B, CJule Solapur, 413004 | PP Developers | 284 | 76% | 8 Jun 2023 | Registered |
| Shri Swami Samarth PuramSolapur (M Corp.), 413228 | Divyaa Ashtavinayaka Realty | 219 | 26% | 24 Aug 2017 | Registration lapsed |
| Paras Business ParkSouth kasba, 413007 | Priyadarshani Corporation | 189 | 0% | 14 Nov 2024 | Registered |
| Chhoriya Township - Plotting Layout AkkalkotAkkalkot, 431216 | Chhoriya and Chopda Properties | 187 | 22% | 22 Aug 2017 | Completed |
| KATHALE VIHARBarshi, 413411 | SATISH MALANBAI ANDHARE | 187 | 15% | 6 Aug 2017 | Completed |
| R M Dhariwal Township Tembhurni PlottingTembhurni, 413211 | Dhariwal And Chhoriya Buildcon Pvt Ltd | 177 | 34% | 31 Jul 2017 | Completed |
| KIMAYA SWAPANAPURTI PHASE 2SAAT RASTA, 413004 | ALACRITY CONSTRUCTIONS PVT LTD | 174 | 5% | 11 Jun 2025 | Registered |
| Chhoriya Township Wakhari Pandharpur Phase 2Wakhari, Pandharpur, 413304 | Chhoriya Properties And Development Company | 153 | 22% | 21 Oct 2020 | Registered |
| VENKATESH LA-ARKA PHASE IINEHARU NAGAR, 413004 | P A SATHE & ASSOCIATES | 145 | 0% | 11 Oct 2022 | Registration lapsed |
| NAKSHATRA HEIGHTSKASABE SOLAPUR, 413005 | GAYATRI BUILDERS AND DEVELOPERS | 141 | 22% | 23 Oct 2021 | Registered |
| Shhraddha EmraldGandhi Nagar, 413006 | Shhraddha Buildcons | 141 | 70% | 15 Jul 2017 | Registration lapsed |
| Vrundavan ParkVasant Vihar, 413001 | Vrundavan Properties | 139 | 0% | 14 Sep 2022 | Registered |
| Platinum MallLaxmi Peth, 413001 | M/S Ganesh Ramchandra Apte | 132 | 68% | 10 Nov 2023 | Registered |
| Chhoriya Residency - PandharpurPandharpur, 413304 | Dhariwal And Chhoriya Developers LLP | 131 | 78% | 12 Oct 2019 | Registered |
| Chhoriya Township Modnimb G No 139/Part Plottingmodnimb, 413301 | Dhariwal And Chhoriya Buildcon Pvt Ltd | 129 | 94% | 5 Aug 2017 | Completed |
| INDRADHANU-Phase-IVLaxmi Peth, 413001 | M/S Ganesh Ramchandra Apte | 126 | 65% | 11 Jan 2018 | Registered |
| INDRADHANU-Phase-6Laxmi Peth, 413001 | M/S Ganesh Ramchandra Apte | 122 | 77% | 30 Mar 2021 | Registered |
| CENTER-PRIDEYAMAI MANDIR, 413304 | AMOL DATTATRAY NAGTILAK | 117 | 0% | 6 Jan 2020 | Registered |
| MANOMAY VIHARPRATAP NAGAR, 413004 | SUKHAKARTA REALITY | 117 | 26% | 31 Aug 2017 | Completed |
| Aarambha ResidencyISBAVI, 413304 | Aarambha Residency | 109 | 0% | 31 Aug 2026 | Registered |
| Jijau ResidencyAt Murarji Peth Uma Nagari, Solapur 413001, 413001 | Rachana Developers | 109 | 0% | 15 Sep 2025 | Registered |
| ROYAL SYNERGYUMA GRUHNIRMAN SANSTHA MOUJE MURARJI PETH, 413001 | SHREE JAGDAMB DEVELOPERS | 107 | 37% | 10 Feb 2025 | Registered |
| 505 Bahava Row Houses,Open PlotsSolapur (M Corp.), 413001 | Pandhe Infracons Pvt Ltd | 106 | 97% | 31 Aug 2017 | Registration lapsed |
| Chhoriya Township - Plotting Layout VairagVairag, 413402 | Khinvosara and Chhoriya Properties | 106 | 76% | 10 Aug 2017 | Completed |
| Heritage PalmsModel Public School, 413004 | Manoj Kantilal Shah | 99 | 71% | 8 Dec 2017 | Completed |
| Anantkoti SkyvillaSolapur (M Corp.), 413004 | ANANTKOTI BUILDCON | 97 | 25% | 23 Jul 2025 | Registered |
| Mahanandi HeightsShelagi, 413006 | Sneharika Vijayshree Developers | 94 | 0% | 3 Sep 2025 | Registered |
| RAJASHREE HEIGHTSMajrewadi, 413224 | Rajashree Builders | 89 | 13% | 15 May 2023 | Registered |
| HMEMPIRE210211GANGADHAR NAGAR, 413006 | HERIYTAGE MANIYDHARI EMPIRE | 86 | 0% | 25 Sep 2019 | Registration lapsed |
| BRAMHA GALAXYSUMITRA NAGAR, 413006 | BRAMHA BUILDCON | 85 | 87% | 6 Jun 2022 | Registered |
| Tirumala ParadiseJodbhavi Peth, 413002 | Sachin Vitthal Ghanate | 84 | 4% | 15 Jan 2024 | Registered |
| KIMAYA SWAPANASHRUSTHIJULE SOLAPUR, 413004 | KIMAYA CONSTRUCTIONS PVT LTD | 82 | 18% | 27 Mar 2025 | Registered |
| Shree Vasundhara HeightsVishwakarma Residency, 413006 | Kishor Rajendra Sanjekar | 81 | 40% | 11 Jan 2022 | Registered |
| DHANSHREE PARKNEAR MAHILA HOSPITAL, 413305 | KAZI BUILDERS | 78 | 0% | 2 Dec 2025 | Registered |
| TIRUPATI PURAMPANDHARPUR, 413304 | TIRUPATI CONSTRUCTION PRAMOTERS AND DEVELOPERS | 78 | 28% | 16 Apr 2024 | Registered |
| PANJWANI MARKETKasabe Solapur, 413003 | V V SOMSHETTI BUILDERS LLP | 76 | 58% | 6 Dec 2021 | Registered |
| SAMARTH PRASADSOLAPUR, 413004 | JJRV INFRA PRIVATE LIMITED | 76 | 26% | 11 Aug 2025 | Registered |
| FOUR SEASONSSoregaon, 413008 | T6 REALTY PVT LTD | 74 | 47% | 6 Feb 2024 | Completed |
| Gokul ViharNear Sanket Thobade Nagar, 413002 | Aakruti Builders | 74 | 24% | 5 Apr 2023 | Registered |
| Madhuban Paradise Part-IINear Bhavani Temple, 413002 | Madhuri Lature | 74 | 0% | 18 Jun 2019 | Registration lapsed |
| Panchganga Bramhaputra HeightsGandhi Nagar, 413006 | HANMANTU KOMARAYYA BURA | 73 | 99% | 27 Jun 2023 | Registered |
| Sai Suman NagarWidi Gharkul Kumbhari A/B, 413006 | Pandhe Construction Pvt Ltd | 73 | 84% | 19 Aug 2017 | Registration lapsed |
| SAI ICONMurarji Peth, Solapur, 413001 | BJR CONTRUCTIONS PRIVATE LIMITED | 71 | 21% | 2 Feb 2024 | Registered |
| F.F AMORASolapur (M Corp.), 413003 | F F CITY TOWER DEVELOPERS | 68 | 100% | 9 Oct 2017 | Registered |
| Paras ParadiseMurarji Peth, 413001 | Anantkoti Developers | 68 | 47% | 2 Feb 2024 | Registered |
| MAHESH COMPLEXMAHESH SANKRUTIK BHAVAN, NEAR LIC OFFICE, 413304 | SHRI CHAITANYA ADHYATMIK TRUST | 67 | 0% | 29 Jul 2025 | Registered |
| Balaji HeightsRamling Nagar, 413004 | Balaji Infra | 66 | 73% | 1 Sep 2021 | Registered |
| VINAYAK SQUAREGANESH NAGAR, 413001 | SHRI VINAYAK CONSSTRUCTIONS | 65 | 60% | 23 Feb 2018 | Registration lapsed |
| 522Solapur (M Corp.), 413001 | Pandhe Infracons Pvt Ltd | 64 | 66% | 22 Aug 2017 | Registration lapsed |
Developers active in Solapur
M/S Ganesh Ramchandra Apte (8), Dhariwal And Chhoriya Buildcon Pvt Ltd (7), Mohsin Haroon Shaikh (6), Gayatri Developers (5), IMAGE SPACE INCORPORATED (5), Devendra Vasudeo Sangolkar (5). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Solapur projects listed above?
Compare each project against its neighbours, not against the brochure. The median project on this page is 15% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Solapur project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What stamp duty will I pay on a flat in Solapur district?
The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.
What does it mean that some Solapur registrations have lapsed?
A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.
What if a Solapur project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own MahaRERA filings, and we read every report.
Report an errorShare feedbackData from official MahaRERA filings.