Home / Browse projects / Solapur, Maharashtra / NAKSHATRA HEIGHTS
NAKSHATRA HEIGHTS
By GAYATRI BUILDERS AND DEVELOPERS
RG-MH-22518 · RERA P52600031476 · Last updated on MahaRERA portal: 14 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NAKSHATRA HEIGHTS is a Residential / Group Housing project by GAYATRI BUILDERS AND DEVELOPERS in Solapur, Maharashtra, registered with MahaRERA as P52600031476 on 23 Oct 2021. Possession is promised by 31 Dec 2028. 31 of the 141 units on this registration are recorded sold or booked, and 3 of 22 construction stages are filed complete.
At a glance
Project
- NameNAKSHATRA HEIGHTS
- TypeResidential / Group Housing
- Location
- BEHIND SOLAPUR APMC
- KASABE SOLAPUR
- Solapur (M Corp.)
- Solapur North
- Solapur
- 413005
- Pincode413005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52600031476
- ReraGenie IDRG-MH-22518
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Oct 2021
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings2 building records
- Documents filed168 files
Current status
Figures as on 14 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER I WING A | NA | 8 | 8 | 48 | 37 | 85 |
| TOWER II WING B | NA | 8 | 8 | 56 | 0 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 85%.
TOWER I WING A50%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER II WING B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 30% |
| Street Lighting | Yes | 20% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| TOWER I WING A | 29 | 29 |
| TOWER II WING B | 11 | 11 |
Land and ownership5
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| DARYAPPA SHARANNAPPA JAKAPURE | Solapur (M Corp.) | Solapur |
| RAJASHRI DARYAPPA JAKAPURE | Solapur (M Corp.) | Solapur |
| SHARANAPPA KALLAPPA JAKAPURE | Solapur (M Corp.) | Solapur |
| SIDDHARAM SHARANAPPA JAKAPURE | Solapur (M Corp.) | Solapur |
| SHILPA SIDDHARAM JAKAPURE | Solapur (M Corp.) | Solapur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TOWER I WING A | NA | Rs 8.50 cr | Rs 8.03 cr |
| TOWER II WING B | NA | Rs 7.38 cr | - |
| - | NA | Rs 49.34 lakh | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VISHWAMBHAR BALAYYA MAMDYAL BALAYYA MAMDYAL |
| Engineer | RAMESH NAGANSURE |
| Engineer | ROHAN NAGANSURE |
| Engineer | IRESH S ALURE |
| Chartered Accountant | PATIL UDGIRI AND ASSOCIATES |
| Chartered Accountant | HIREMATH PATIL UDGIRI AND ASSOCIATION |
| Chartered Accountant | VIJAY PANCHAPPA & CO |
| Partner | Role in project |
|---|---|
| GAYATRI BUILDERS AND DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Oct 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed168
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 168 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2022-2023)File: Form 2A 20222023.pdf | 14 Aug 2026 |
| Form 2A (FY 2023-2024)File: Form 2A 20232024 alure.pdf | 14 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A 20252026.pdf | 14 Aug 2026 |
| Form 2A (FY 2021-2022)File: Form 2A 20212022.pdf | 14 Aug 2026 |
| Form 5 (FY 2021-2022)File: Form 5 20212022.pdf | 6 Aug 2026 |
| Form 5 (FY 2022-2023)File: Form 5 20222023.pdf | 6 Aug 2026 |
| Form 5 (FY 2023-2024)File: Form 5 20232024.pdf | 6 Aug 2026 |
| Withdrawal Update Form 1File: 01 Form-1 30062026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: 02 Form-2 30062026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: 03 Form 3 30062026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Form-1 31032026.pdf | 21 Apr 2026 |
| Withdrawal Update Form 2File: Form-2 31032026.pdf | 21 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate 31032026.pdf | 21 Apr 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1.pdf | 21 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Certificate of Engineer 31122025.pdf | 21 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate 31122025.pdf | 21 Jan 2026 |
| Form 5 (FY 2024-2025)File: Gayatri Builders and Developers Form 5 2024-2025 Sighned.pdf | 29 Nov 2025 |
| Withdrawal Update Form 1File: 01 Form1 30092025 Sign.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: 02 Form 2 30092025.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: 03 Form 3 30092025.pdf | 20 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2A 2024-2025.pdf | 21 Jul 2025 |
| Form 1File: 01 FORM 1 311221.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 311221.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31122021.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31122021.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 310322.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 310322.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31032022.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31032022.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 300622.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 300622.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30062022.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 30062022.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 300922 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 300922 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30092022.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 30092022.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 311222 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 311222 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31122022.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31122022.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 310323 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 310323 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31032023.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31032023.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 300623 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 300623 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30062023.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 30062023.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 300923 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 300923 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30092023.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 30092023.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 311223 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 311223 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31122023.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31122023.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 310324 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 310324 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31032024.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31032024.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 300624 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 300624 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30062024.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 30062024.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 300924 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 300924 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30092024.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 30092024.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 311224 Head.pdf | 20 Jul 2025 |
| Form 2File: 02 FORM 2 311224 Head.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 31122024.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31122024.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 31032025.pdf | 20 Jul 2025 |
| Form 2File: 02 Form 2 Certificate of Engineer 31032025.pdf | 20 Jul 2025 |
| Form 3File: 03 CA Certificate 31032025.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 04 Booking Stetus 31032025.pdf | 20 Jul 2025 |
| Form 1File: 01 FORM 1 30062025.pdf | 20 Jul 2025 |
| Form 2File: 02 Form 2 Certificate of Engineer 30062025.pdf | 20 Jul 2025 |
| Form 3File: 03 Form 3 CA Certificate 30062025.pdf | 20 Jul 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| SHREE GURURAJ PARK | PLOT NO 2 CTS 140 1 1 KASABE SOLAPUR SOLAPUR 413002 | Completed | May 2023 | May 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Solapur
Computed across the 550+ Solapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 168 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NAKSHATRA HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KASABE SOLAPUR550+ in Solapur
Filed coordinates, straight-line distance. 56 registered projects within 2 km.
Niyojit Shri Somvanshiya Sahastrarjun Kshatriy
Anukarati Homes Private Limited
Kaveri Heights
Gayatri Developers
PADMAWATI REJENCY
GURAPPA MALLIKARJUN KAPSE
SURYA COMPLEX
SURESH AMBADAS MITTHAKOL
PRAJAY HEIGHTS
JAYKANT CONSTRUCTION
VEER KOHINOOR TOWER
VIRENDRA CONSTRUCTIONS
See every Solapur project, with the district possession charts
Builder: GAYATRI BUILDERS AND DEVELOPERS
GAYATRI BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including SHREE GURURAJ PARK and NAKSHATRA HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Solapur district page.
Frequently asked questions
What are my rights if NAKSHATRA HEIGHTS is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NAKSHATRA HEIGHTS?
The registered promoter entity is GAYATRI BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NAKSHATRA HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NAKSHATRA HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NAKSHATRA HEIGHTS?
The professionals named in the filing: Architect: VISHWAMBHAR BALAYYA MAMDYAL BALAYYA MAMDYAL; Engineer: RAMESH NAGANSURE; Engineer: ROHAN NAGANSURE; Engineer: IRESH S ALURE; Chartered Accountant: PATIL UDGIRI AND ASSOCIATES; Chartered Accountant: HIREMATH PATIL UDGIRI AND ASSOCIATION. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NAKSHATRA HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback