Home / Browse projects / Palghar, Maharashtra / VBHC 47 ROWLAND PARK
VBHC 47 ROWLAND PARK
By VBHC MUMBAI VALUE HOMES PRIVATE LIMITED
RG-MH-73126 · RERA P99000031952 · Last updated on MahaRERA portal: 3 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VBHC 47 ROWLAND PARK is a Others project by VBHC MUMBAI VALUE HOMES PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000031952 on 29 Nov 2021. Possession was promised by 31 Dec 2024 and is now 22 months past that date.
At a glance
Project
- NameVBHC 47 ROWLAND PARK
- TypeOthers
- Location
- Off Palghar-Manor Highway
- Abachapada
- Devkhop
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000031952
- ReraGenie IDRG-MH-73126
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Nov 2021
- Promised completion31 Dec 2024
- Revised completionNone
- Buildings9 building records
- Documents filed108 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E1-E8 | NA | 2 | 0 | 0 | 0 | 0 |
| E9-E16 | NA | 2 | 0 | 0 | 0 | 0 |
| F1-F8 | NA | 2 | 0 | 0 | 0 | 0 |
| F9-F16 | NA | 2 | 0 | 0 | 0 | 0 |
| G1-G8 | NA | 2 | 0 | 0 | 0 | 0 |
| G9-G16 | NA | 2 | 0 | 0 | 0 | 0 |
| H1-H4 | NA | 2 | 0 | 0 | 0 | 0 |
| I1-I5 | NA | 2 | 0 | 0 | 0 | 0 |
| J1-J8 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 3 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
81 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Podiums (if any), at 0%.
E1-E882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E9-E1682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F1-F882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F9-F1682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G1-G882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G9-G1682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
H1-H482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I1-I582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
J1-J882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TNS Chakravarthi |
| Engineer | Pritam P Mekde |
| Engineer | Amit Kumar Pandey |
| Chartered Accountant | P Chandrasekaran |
| Chartered Accountant | Kartik subramanian for R Subramanian andcompany LLP |
| Chartered Accountant | KARTIK Subramanian |
| Chartered Accountant | Guru & Jana |
| Partner | Role in project |
|---|---|
| VBHC MUMBAI VALUE HOMES PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Nov 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Nov 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Nov 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Jan 2025
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: VBHC 47 Rowland Park.pdf | 3 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form - 5 CA Cert Fy 2024-25.pdf | 30 Sep 2025 |
| Form 1File: Form - 1 - Architect Certificate - Sep'24.pdf | 25 Jun 2025 |
| Form 2File: Form - 2 - Engineer Certificate - Sep'24.pdf | 25 Jun 2025 |
| Form 3File: Form - 3 - CA Certificate - Sep'24.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: 12 Disclosure of sold_ booked inventory.pdf | 25 Jun 2025 |
| Form 1File: FORM-1 - AR Certificate - Rowland park.pdf | 25 Jun 2025 |
| Form 2File: Form-2 -EC - VBHC 47 Rowland Park 1.pdf | 25 Jun 2025 |
| Form 3File: Form-3 - CA Certificate - Dec'24.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold invetory-Dec'24.pdf | 25 Jun 2025 |
| OthersFile: Row Land Phase 1 OC.pdf | 25 Jun 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form-4 Rowhouses Ph-1.pdf | 7 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Row Land Phase 1 OC.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 - AR Certificate - Rowland park_Dec'24.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - CA Certificate - Dec'24.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 -EC - VBHC 47 Rowland Park 1.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold invetory-Dec'24.pdf | 18 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_ Azhar_Ahmed_VBHC_Mumbai_Private_Limited.pdf | 20 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_ Preethi_Nair_VBHC_Mumbai_Private_Limited.pdf | 20 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VBHC Rowland Park signed APR 24 Latest.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR certificate RP QPR Oct24.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate RP Sept 24 Signed.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER certificate VBHC 47 Rowland Park Oct 24.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold RP Oct 24.pdf | 18 Oct 2024 |
| Form 5 (FY 2023-2024)File: VBHC Rowland Park signed APR 24 Latest.pdf | 30 Sep 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Rowland park Format A.pdf | 3 Aug 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Rowland park.pdf | 3 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Er certificate RP1 June24 Signed.pdf | 15 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA certificate RP park June 24 Signed.pdf | 15 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar certiifcate RL park Jun24 compressed.pdf | 4 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold details RL park Jun24.pdf | 4 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form2 Engineer's certificate RP Mar 24.pdf | 14 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form3 CA RP Mar 24.pdf | 14 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 AR certificate Form1 RP Mar 24 Final.pdf | 12 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 4 RP Sold dtls Mar 24.pdf | 12 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A VBHC 47 Rowland Park Final.pdf | 5 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf | 22 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest Charanraj.pdf | 22 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's certificate Rowlandpark Dec 23_compressed.pdf | 13 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer's certificate Rowlandpark Dec 2023 w.pdf | 13 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold details Rowlandpark Dec23.pdf | 13 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rowland park Dec 23 w.pdf | 13 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Rowland park Sep 23.pdf | 14 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Er certificate Rowland park Sep 23.pdf | 13 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold details - Rowland park Sep 23.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Rowlandpark Sep 23.pdf | 11 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual report on statement of accounts VBHC 47 Rowland park.pdf | 28 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 VBHC 47 ROWLAND PARK Final.pdf | 14 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 47 Rowland park CA June 23 Final_compressed.pdf | 14 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf | 13 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold inventory Rowland park.pdf | 13 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certifcate RP1-compressed.pdf | 10 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rwlnd park 1 CA Mar 23_compressed.pdf | 24 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate for Rowland park march 2023.pdf | 15 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate VBHC Rera Palghar G Phs 1 Mar 23.pdf | 15 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate March 2023.pdf | 14 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance for Row land park -01.pdf | 14 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or booked inventory March 2023.pdf | 14 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf | 3 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate Jan 22.pdf | 22 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate Jan 22.pdf | 22 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's certificate Dec 21.pdf | 22 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Dec 21 Rowland park_compressed.pdf | 22 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Mar 22 Rowland park_compressed.pdf | 22 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Rowland park Jul 22.pdf | 22 Feb 2023 |
| Proforma of Agreement for saleFile: Proforma of Agreement for sale.pdf | 22 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 2 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 47 Rowland park Annual Report- 2022 Form 5.pdf | 24 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Rowland park Dec 2022_compressed.pdf | 13 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate -Rowland park Dec 22.pdf | 12 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate Rowland park Dec 2022.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Invetories Rowland park Dec 2022.pdf | 12 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certifcate Rowland Park.pdf | 14 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate RowlandPark_compressed.pdf | 14 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certifcate Rowland Park_compressed.pdf | 11 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory Rowland Park.pdf | 11 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 47 Rowland park Annual Report- 2022 Form 5.pdf | 21 Sep 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certifcate Form 2 Rowlandpark_compressed.pdf | 14 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 47 Rowland Park_compressed.pdf | 14 Jul 2022 |
Promoter's earlier projects7
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| VBHC SpringwaterP99000051828 | Abachapada, Palghar | 206 | Jul 2023 | Ongoing | Apr 2027 | Not due yet |
| VBHC 47 ROWLAND PARK 2P99000034882 | Abachapada, Palghar | - | Apr 2022 | Ongoing | Mar 2025 | Not delivered |
| VBHC GreengladeP99000000542 | Devkhop Village, Palghar | - | Jul 2017 | Completed | Feb 2023Registered original: Feb 2020 | Apr 2022 |
| VBHC GreendewP99000000515 | Abachapada, Palghar | - | Jul 2017 | Completed | Jul 2019Registered original: Jul 2018 | Dec 2018 |
| Palmhaven-2 Block-C | Kengeri Bangalore | 480 | - | Completed | Apr 2019 | Late, Apr 2019 |
| VBHC VAIBHAVA | Kasaba Hobli Anekal Taluk Bangalore | 1,854 | - | Completed | May 2017 | Late, Oct 2021 |
| VBHC PALMHAVEN Phase I | Kengeri Bangalore | 208 | - | Completed | Apr 2015 | Apr 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VBHC 47 ROWLAND PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Abachapada3,200+ in Palghar
Filed coordinates, straight-line distance. 19 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: VBHC MUMBAI VALUE HOMES PRIVATE LIMITED
VBHC MUMBAI VALUE HOMES PRIVATE LIMITED has 9 registrations on MahaRERA, including VBHC Greenglade and VBHC Greendew. Its filings disclose 17 earlier MahaRERA projects: declares 5 of 14 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that VBHC 47 ROWLAND PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VBHC 47 ROWLAND PARK is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VBHC 47 ROWLAND PARK?
The registered promoter entity is VBHC MUMBAI VALUE HOMES PRIVATE LIMITED, a company as per the filing. Its CIN U45201KA2010PTC053889 and GSTIN 27AADCV3420H1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VBHC 47 ROWLAND PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VBHC 47 ROWLAND PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VBHC 47 ROWLAND PARK?
The professionals named in the filing: Architect: TNS Chakravarthi; Engineer: Pritam P Mekde; Engineer: Amit Kumar Pandey; Chartered Accountant: P Chandrasekaran; Chartered Accountant: Kartik subramanian for R Subramanian andcompany LLP; Chartered Accountant: KARTIK Subramanian. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VBHC 47 ROWLAND PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback