VBHC MUMBAI VALUE HOMES PRIVATE LIMITED has 9 registrations in this build, including VBHC Greenglade and VBHC Greendew. Its filings disclose 17 earlier MahaRERA projects: 5 of 14 past projects completed on time.

9Registrations in this build
17Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
VBHC GreengladePalghar, Maharashtra--Completed
VBHC GreendewPalghar, Maharashtra--Completed
VBHC 47 ROWLAND PARKPalghar, Maharashtra--Registration lapsed
VBHC 47 ROWLAND PARK 2Palghar, Maharashtra--Registration lapsed
VBHC SpringwaterPalghar, Maharashtra20666%Registered
VBHC LANDSCAPEPalghar, Maharashtra1320%Registration lapsed
VBHC LANDSCAPE 4Palghar, Maharashtra1030%Registration lapsed
VBHC LANDSCAPE 2Palghar, Maharashtra930%Registered
VBHC LANDSCAPE 3Palghar, Maharashtra1000%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
VBHC PALMHAVEN
30 Jul 201428 Jul 2015+12 months
VBHC Palmhaven
30 Jul 201428 Jul 2015+12 months
VBHC GREENGLADE
9 Oct 201423 Oct 2014On time
VBHC Greenglade
10 Feb 201510 Feb 2015On time
VBHC PALMHAVEN Phase I
16 Apr 201515 Apr 2015On time
VBHC Greendew
1 Dec 20151 Dec 2015On time
VBHC VAIBHAVA
1 May 20172 Oct 2021+53 months
VBHC GREENDEW
13 Dec 201814 Dec 2018On time
Palmhaven-2 Block-C
3 Apr 201917 Apr 2019On time
Palmhaven-2 Block-C
3 Apr 201917 Apr 2019On time
Palmhaven2 Block C
3 Apr 201917 Apr 2019On time
VBHC Greendew
P99000000515
31 Jul 201914 Dec 2018On time

Frequently asked questions

How do I verify VBHC MUMBAI VALUE HOMES PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with VBHC MUMBAI VALUE HOMES PRIVATE LIMITED?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.