Home / Browse projects / Palghar, Maharashtra / VBHC 47 ROWLAND PARK 2

Registration lapsed No litigation declared Others project

VBHC 47 ROWLAND PARK 2

By VBHC MUMBAI VALUE HOMES PRIVATE LIMITED

RG-MH-55246 · RERA P99000034882 · Last updated on MahaRERA portal: 3 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
63 of 77Construction stages doneacross 7 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

VBHC 47 ROWLAND PARK 2 is a Others project by VBHC MUMBAI VALUE HOMES PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000034882 on 28 Apr 2022. Possession was promised by 31 Mar 2025 and is now 19 months past that date.

At a glance

Project

  • NameVBHC 47 ROWLAND PARK 2
  • TypeOthers
  • Location
    • Off Palghar - Manor Highway
    • Abachapada
    • Devkhop
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000034882
  • ReraGenie IDRG-MH-55246

Builder

  • NameVBHC MUMBAI VALUE HOMES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45201KA2010PTC053889
  • GSTIN27AADCV3420H1ZI
  • DirectorsPEDDIREDDY ROYAL REDDY, Charanraj D
  • Other registrations8 more →
  • Completed2 of 9
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects17 →

Key dates

19 months past promisethis monthRegisteredApr 2022PromisedMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Apr 2022
  • Promised completion31 Mar 2025
  • Revised completionNone
  • Buildings7 building records
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1 - A8NA20000
A9 - A16NA20000
B1 - B8NA20000
B9 - B16NA20000
C1 - C8NA20000
C9 - C16NA20000
D1 - D8NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 3 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

63 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Podiums (if any), at 0%.

A1 - A882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A9 - A1682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B1 - B882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B9 - B1682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C1 - C882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C9 - C1682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D1 - D882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,972 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityCollector office
Permissible FSI2580.0
Proposed, not sanctioned2,580 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround floor, Jehangir building, MG road, Fort Mumbai - 400001

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTNS Chakravarthi
EngineerPritam P Mekde
EngineerAmit kumar Pandey
Chartered AccountantP Chandrasekaran
Chartered AccountantArvind Baradwaj Jayaraman
Chartered AccountantKartik Subramanian for R Subramanian and company LLP
Chartered AccountantKARTIK Subramanian
Chartered AccountantGuru & Jana
PartnerRole in project
VBHC MUMBAI VALUE HOMES PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Apr 2025

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: VBHC 47 Rowland Park 2.pdf3 Oct 2025
Form 5 (FY 2024-2025)File: Form - 5 Fy 2024-25.pdf30 Sep 2025
Form 1File: FORM-1 - AR Certificate - Rowland park 2.pdf25 Jun 2025
Form 2File: Form-2 - EC - VBHC 47 Rowland Park 2.pdf25 Jun 2025
Form 3File: Form-3 - CA Certificate - Dec'24.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventory - Dec'24.pdf25 Jun 2025
Form 1File: Form-1 - Architect Certificate - Mar'25.pdf25 Jun 2025
Form 2File: Form-2 - Engineer Certificate - Mar'25.pdf25 Jun 2025
Form 3File: Form-3 - CA Certificate - Mar'25.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold inventory - Rowland Park 2 - Mar'25.pdf25 Jun 2025
OthersFile: Occupency Certificate _VBHC Row Land Park 2_.pdf25 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 - Architect Certificate - Mar'25.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - CA Certificate - Mar'25.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 - Engineer Certificate - Mar'25.pdf20 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupency Certificate _VBHC Row Land Park 2_.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Interest - Rowland Park 2 - Mar'25.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 - AR Certificate - Rowland park 2.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 - CA Certificate - Dec'24.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 - EC - VBHC 47 Rowland Park 2.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold unsold inventory - Dec'24.pdf18 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_ Azhar_Ahmed_VBHC_Mumbai_Private_Limited.pdf20 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest_ Preethi_Nair_VBHC_Mumbai_Private_Limited.pdf20 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VBHC Rowland Park 2 signed APR 24.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR certificate RP2 Oct 24.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate RP2 Sept 24.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER certificate VBHC Rowland Park 2 Oct 24.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold RP2 Oct24.pdf18 Oct 2024
Form 5 (FY 2023-2024)File: VBHC Rowland Park 2 signed APR 24.pdf30 Sep 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Rowland park 2 Format A.pdf3 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Rowland park 2.pdf3 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Er certificate RP2 June24 Signed.pdf15 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA certificate RL park2 June 24 Signed.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate RL park2 Jun 24.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold details RL park2 jun24.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form2 Engineer's certificate RP 2 Mar 24.pdf14 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 Rowland park 2 CA Mar 24.pdf14 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 RP2 Form1AR certificate Mar 24.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: 4 RP2 Sold dtls Mar 24.pdf12 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A VBHC 47 Rowland Park 2 Final.pdf5 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest Charanraj.pdf22 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's certificate Rowland park2 Dec 23.pdf13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer's certificate Dec 2023 Rowland park2 w.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold details Rowland park 2 Dec 23.pdf13 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rowland park 2 Dec 23 w.pdf13 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Rowlandpark 2 Sep 23 Final.pdf14 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Er certificate Rowland park 2 Sep 23.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold details - Rowland park 2.pdf13 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Rowlandpark2 Sep23.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual report on statement of accounts VBHC 47 Rowland park 2.pdf28 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Form 2 - VBHC 47 ROWLAND PARK 2 Final.pdf14 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 47 Rowland park 2 CA June 23 Final_compressed.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf13 Jul 2023
Disclosure of sold/ booked inventoryFile: 47 Rowlandpark 2 Sold inventory.pdf13 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certifcate RP2.pdf10 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rwlnd park 2 CA Mar 23_compressed.pdf24 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate for Rowland park 2 march 2023.pdf15 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate VBHC Rera Palghar G Phs 2 March 23 Qtr.pdf15 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate march 2023.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance for Rowland park 2.pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked inventory March 2023.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf3 Apr 2023
Proforma of Agreement for saleFile: Proforma of Agreement for sale.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Rowland park 2 Dec 2022_compressed.pdf13 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Rowland park 2 Dec 22.pdf12 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate Rowland park 2 Dec 2022.pdf12 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Booked Inventories Rowland Park 2 Dec 22.pdf12 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginner's Certifcate Rowland Park 2.pdf14 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Rowland park 2_compressed.pdf14 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Rowland Park 2.pdf11 Oct 2022
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory RowLandPark2.pdf11 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Er Certificate Form 2 Rowlandpark 2_compressed.pdf14 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certiifcate RowlandPark 2_compressed.pdf14 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 47 Rowload Park 2.pdf13 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 47 Rowland Park 2 Form 2A.pdf13 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold Booked Inventories - 47 Rowland park 2.pdf13 Jul 2022
Layout approvalFile: 1 Layout plan.pdf22 Apr 2022
Layout approvalFile: 3 Revised Row house Phase 02.pdf22 Apr 2022
Building plan approvalFile: Building Plan 47 Rowland Park.pdf22 Apr 2022
Copy of the legal title reportFile: Revised Legal title report 19042022.pdf22 Apr 2022

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 delivered late1 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VBHC SpringwaterP99000051828Abachapada, Palghar206Jul 2023OngoingApr 2027Not due yet
VBHC 47 ROWLAND PARKP99000031952Abachapada, Palghar-Nov 2021OngoingDec 2024Not delivered
Palmhaven-2 Block-CKengeri Bangalore--CompletedApr 2019Late, Apr 2019
VBHC GreendewP99000000515Abachapada, Palghar-Jul 2017CompletedDec 2018Registered original: Jul 2018Late, Dec 2018
VBHC VAIBHAVAKasaba Hobli Anekal Taluk Bangalore--CompletedMay 2017Late, Oct 2021
VBHC PALMHAVEN Phase IKengeri Bangalore--CompletedApr 2015Apr 2015
VBHC GreengladeP99000000542Devkhop Village, Palghar-Jul 2017CompletedOct 2014Late, Oct 2014

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VBHC 47 ROWLAND PARK 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Abachapada3,200+ in Palghar

2 kmVBHC 47 ROWLAND PARK 2Completed 11Lapsed / revoked 4Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: VBHC MUMBAI VALUE HOMES PRIVATE LIMITED

VBHC MUMBAI VALUE HOMES PRIVATE LIMITED has 9 registrations on MahaRERA, including VBHC Greenglade and VBHC Greendew. Its filings disclose 17 earlier MahaRERA projects: declares 5 of 14 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that VBHC 47 ROWLAND PARK 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if VBHC 47 ROWLAND PARK 2 is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VBHC 47 ROWLAND PARK 2?

The registered promoter entity is VBHC MUMBAI VALUE HOMES PRIVATE LIMITED, a company as per the filing. Its CIN U45201KA2010PTC053889 and GSTIN 27AADCV3420H1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VBHC 47 ROWLAND PARK 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VBHC 47 ROWLAND PARK 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VBHC 47 ROWLAND PARK 2?

The professionals named in the filing: Architect: TNS Chakravarthi; Engineer: Pritam P Mekde; Engineer: Amit kumar Pandey; Chartered Accountant: P Chandrasekaran; Chartered Accountant: Arvind Baradwaj Jayaraman; Chartered Accountant: Kartik Subramanian for R Subramanian and company LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VBHC 47 ROWLAND PARK 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VBHC 47 ROWLAND PARK 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VBHC 47 ROWLAND PARK 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.