Home / Browse projects / Palghar, Maharashtra / Veena Samrajya-Sector-VIII

Registered No litigation declared Residential / Group Housing project

Veena Samrajya-Sector-VIII

By Veena Developers

RG-MH-04298 · RERA P99000021726 · Last updated on MahaRERA portal: 30 May 2026

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 39 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 39 months from the original
73 of 297Construction stages doneacross 27 buildings; furthest along: Slabs of Super Structure, 11%
1,082 of 1,588Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 137 documents Report an error

Veena Samrajya-Sector-VIII is a Residential / Group Housing project by Veena Developers in Palghar, Maharashtra, registered with MahaRERA as P99000021726 on 22 Jul 2019. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 506 of the 1,588 units on this registration are recorded sold or booked, and 73 of 297 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameVeena Samrajya-Sector-VIII
  • TypeResidential / Group Housing
  • Location
    • Chintupada Road
    • Palghar West
    • Mahim
    • Palghar
    • 401404
  • Pincode401404
  • RERA no.P99000021726
  • ReraGenie IDRG-MH-04298

Builder

  • NameVeena Developers
  • Entity typeOthers
  • GSTIN27AAMFN6585H1ZN
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersVEENA Sanghavi, Haresh Natvarlal Sanghavi Sanghavi
  • PartnerNIKUNJ Sanghavi
  • Other registrations6 more →
  • Completed4 of 7
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2019First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jul 2019
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2023)
  • Buildings27 building records
  • Documents filed137 files

Current status

32%506 of 1,588 units booked
49.7%Work done, per cost certificate

Figures as on 30 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing-ANA101067067
Wing-BNA101049049
Wing-CNA10049049
Wing-DNA10049049
Wing-ENA10049049
Wing-FNA10049049
Wing-GNA101067067
Wing-HNA10067067
Wing-INA10067067
Wing-JNA10059059
Wing-KNA10053053
Wing-LNA10059059
Wing-MNA10067067
Wing-NNA10051051
Wing-ONA10062062
Wing-PNA10053053
Wing-QNA10062062
Wing-RNA101051051
Wing-SNA10067067
Wing-TNA10059059
Wing-UNA10062062
Wing-VNA10053053
Wing-WNA10062062
Wing-XNA10059059
Wing-YNA10067067
Wing-ZNA10067067
Wing-ZANA10062062

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 27 buildings; the table lists the first 20.

73 of 297 construction stages are filed complete across 27 buildings. The stage furthest along is Slabs of Super Structure, at 11%.

Wing-A27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-B27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-C27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-D27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-E27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-F27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-G27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-H27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-I9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-J9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-K9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-L9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-M9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-N9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-O9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-P9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-Q9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-R37%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure11%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-S37%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure11%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing-T37%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure11%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area27,422 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Nov 2025

Approvals and building plan

Sanctioning authorityGRAM PANCHAYAT PALGHAR
Permissible FSI81358.0
Proposed, not sanctioned63,358 sq m
Buildings approved27
Buildings sanctioned27

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEverest Square Building, Ground Floor, Shraddhanand Road, Near Shiv Nagar Hotel, Vile Parle East, Mu
Estimated costRs 142.00 cr
Cost incurredRs 70.54 cr
Work done49.68%
BuildingWingEstimatedIncurred
-NARs 14.00 crRs 14.00 cr
Wing-ANARs 5.40 crRs 43.23 lakh
Wing-GNARs 5.40 crRs 43.23 lakh
Wing-HNARs 5.40 crRs 43.23 lakh
Wing-INARs 5.40 crRs 43.23 lakh
Wing-QNARs 5.40 crRs 1.73 cr
Wing-RNARs 5.40 crRs 5.40 cr
Wing-ZNARs 5.40 crRs 5.40 cr
Wing-ZANARs 5.40 crRs 5.40 cr
Wing-MNARs 5.02 crRs 40.14 lakh
Wing-ONARs 5.02 crRs 41.14 lakh
Wing-TNARs 5.02 crRs 5.02 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Wade & Associates
ArchitectKPA
ArchitectNishit Sunil Sanghavi
ArchitectManish M Shah
EngineerArun Singh
EngineerRajeev Ranjan
Chartered AccountantThar & Co.
Chartered AccountantSANJAY K SHARMA AND CO
Chartered AccountantThar Co
PartnerRole in project
Veena Developers-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000018693Dec 2023 → Dec 2024

Reason as filed by the promoterI am writing to bring to your attention the unforeseen challenges faced by our project, Veena Samrajya ¬Sector ¬VIII, specifically relating to Plot No. 942/2/10 at Mahim, Palghar, Palghar, 401404. The project, with Registration No. P99000021726, was initially granted a timeline from 22.07.2019 to 30.12.2023. The completion of our project has been significantly affected by the global COVID-19 pandemic. The imposed lockdowns, government regulations, and disruptions in the supply chain have led to delays in construction activities, labour shortages, and challenges in procuring essential materials

EXT99000027255Dec 2023 → Aug 2025

Reason as filed by the promoter1. We, the promoters of the project “Veena Samrajya Sector VIII,” registered under MahaRERA with Registration No. P99000021726, respectfully submit this request for an extension of the project completion date. 2. We are pleased to inform you that the project is approximately 95% complete, with only minor finishing work remaining. Further, we are in the process of applying for the Occupation Certificate (OC) to the competent authority, and we anticipate that the OC will be granted within the next 3 to 6 months. 3. To substantiate the status of our project, we have uploaded the Architect's Certi

EA18112518352Dec 2023 → Mar 2026

Reason as filed by the promoterM/s. Veena Developers, promoters of the project “Veena Samrajya - Sector VIII” (MahaRERA Registration No. P99000021726).The project has been designated under the Pradhan Mantri Awas Yojana (PMAY) scheme as per an MOU dated 18th October 2019 between PMAY, MHADA, and M/s. Veena Developers.the construction of Buildings 5 and 6 is fully completed, and documents confirming completion are provided (Annexure B). Following this, an application for Occupancy Certificate was submitted on 19th July 2025 to the local Town Planning Department. Prior to the OC application, they also secured the Consent for

EA30032620462Dec 2023 → Mar 2027

Reason as filed by the promoterM/s. Veena Developers, being the promoters of the project titled “Veena Samrajya - Sector VIII” (MahaRERA Registration No. P99000021726), state that the said project has been duly designated under the Pradhan Mantri Awas Yojana (PMAY) Scheme pursuant to a Memorandum of Understanding dated 18th October 2019 executed between PMAY, MHADA, and the Promoters. It is submitted that, upon completion of the requisite construction and compliance with all statutory requirements, the Promoters applied for the Occupancy Certificate (OC) before the jurisdictional Town Planning Department on 19th July 2025.

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000428713Ajay Amrut KambleVeena Developers14/01/2024
CC006000000428839Ketan Ramkrishna KalburgeVeena Developers14/01/2024
CC006000000428934Amit Vijay RaneVeena Developers24/01/2024
CC006000000428841Chandrashekhar Jaypalsingh PathriyaVeena Developers14/01/2024
CC006000000428966Umera Kalim ShaikhVeena Developers24/01/2024
CC006000000428840Vaishali Subhash FulpagarVeena Developers14/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jul 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed137

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4.pdf30 May 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf30 May 2026
Withdrawal Update Form 3File: Form 3 Q4-compressed.pdf30 May 2026
Withdrawal Update Form 1File: Rera Form-1 (Dec-2025) Veena.pdf30 Mar 2026
Withdrawal Update Form 2File: RERA Form 2 (Q3) 2025-26.pdf30 Mar 2026
Withdrawal Update Form 3File: Form 03 Samrajya Q3 (1).pdf30 Mar 2026
Withdrawal Update Form 1File: Work Completion Certificate 31082024 comp.pdf18 Nov 2025
Withdrawal Update Form 2File: Form2 310825 Comp.pdf18 Nov 2025
Withdrawal Update Form 3File: Form3 aug 25.pdf18 Nov 2025
Form 5 (FY 2024-2025)File: Form5.pdf18 Nov 2025
Withdrawal Update Form 1File: FORM 1 30 June 2025.pdf17 Nov 2025
Withdrawal Update Form 2File: FORM 2 june 25.pdf17 Nov 2025
Withdrawal Update Form 3File: Form 3 Jun 25Samrajya.pdf17 Nov 2025
Form 2A (FY 2024-2025)File: form 2a.pdf17 Nov 2025
Form 1File: Form 1.pdf4 Aug 2025
Form 2File: Form 2.pdf4 Aug 2025
Form 3File: Disclosure.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf4 Aug 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Adobe Scan 11 Apr 2025.pdf11 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Adobe Scan 11 Apr 2025.pdf11 Apr 2025
Certificates of CA (Form 3)File: Form 3 Samrajya Dec 24.pdf4 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q3 Veena Samrajya_opt digital.pdf26 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf25 Mar 2025
Disclosure of sold/ booked inventoryFile: Information For Inventories Details Samrajya 25march.pdf25 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 02A Samrajya fy 23-24.pdf25 Mar 2025
Declaration in FORM BFile: P99000021726_FileName_0 (3).pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventories Veena Samrajya dec24.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Inventories Veena Samrajya dec24 340.pdf24 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: 2454793_FurtherCC_signed.pdf25 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Work Completion Certificate 01-08-2024 Q1.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Work Completion Certificate 01-10-2024 Q2.pdf17 Jan 2025
Certificates of CA (Form 3)File: ilovepdf_merged (7)_11zon.pdf17 Jan 2025
Certificates of CA (Form 3)File: ilovepdf_merged (8)_11zon (1).pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 02 Veena Samrajya Q1_opt.pdf17 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 02 Veena Samrajya Q2_opt.pdf17 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form-1 (June-2024).pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form-1 (Sep-2024).pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form-1 (June-2024).pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form-1 (Sep-2024).pdf14 Oct 2024
Certificates of CA (Form 3)File: Form-3.pdf10 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2.pdf10 Oct 2024
Certificates of CA (Form 3)File: Form-3.pdf10 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2.pdf10 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf6 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf6 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate_11zon.pdf6 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineer Certificate DSC.pdf6 Aug 2024
Certificates of CA (Form 3)File: Form 3 - C A Certificate as 15-01-2024_11zon.pdf6 Aug 2024
Certificates of CA (Form 3)File: Form 3.pdf6 Aug 2024
Declaration in FORM BFile: Form_B_veena samrajya sector viii.pdf25 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_veena samrajya sector viii.pdf25 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory as on 150124_veena samrajya sector viii_11zon.pdf25 Jan 2024
Other - LegalFile: P99000021726_FileName_0.pdf25 Jan 2024
Certificates of CA (Form 3)File: Form-3 Samrajya Q-1 21 12 023_11zon.pdf23 Dec 2023
Certificates of CA (Form 3)File: Form-3 Samrajya Q-2 21 12 2023_11zon.pdf23 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Samrajya Q-1 30 06 2023.pdf12 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Samrajya Q-2 30 09 2023.pdf12 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Samrajya Q-1 23 08 2023.pdf12 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Samrajya Q-2 27 11 2023.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Veena Samrajya - Form-5 FY 2022-23.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Veena Samrajya - Form-5 FY 2021-22.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A Certificate Veena Samrajya From 5 2021 22 24 11 2023.pdf11 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A Certificate Veena Samrajya From 5 2022 23 24 11 2023.pdf11 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Work Completio Certificate 31032023.pdf7 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Veena Samrajya A to ZA 3103202311zon.pdf7 Nov 2023
Certificates of CA (Form 3)File: Form 3 Veena Samrajya 31032023_11zon (1).pdf7 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Veena Samrajya Form 5 - 31-03-2020.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Veena Samrajya Form 5 - 31-03-2021.pdf19 Oct 2023
Certificates of CA (Form 3)File: Form_3_Q1_1.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_2.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_3.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_4.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_5.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_6.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_7.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_Q1_8.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_30-09-2022_1.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_30-09-2022_2.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_30-09-2022_3.pdf10 Jul 2023
Certificates of CA (Form 3)File: Form_3_30-09-2022_3.pdf10 Jul 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
VEENA SKY HEIGHTSVILLAGE KANDIVALI AT MAHAVIR NAGAR KANDIVALI WEST79CompletedJan 2017Jan 2017
VEENA ROYAL VILLASHANKAR LANE KANDIVALI WEST7CompletedNov 2016Nov 2016
VEENA SAHIL VILLASHANKAR LANE KANDIVALI10CompletedDec 2012Dec 2012

How this compares with Palghar

32%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 39 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Veena Samrajya-Sector-VIII on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Palghar West3,200+ in Palghar

Builder: Veena Developers

Veena Developers has 7 registrations on MahaRERA, including VEENA SANTOOR PHASE II and VEENA SIGNATURE. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Veena Samrajya-Sector-VIII is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Veena Samrajya-Sector-VIII?

The registered promoter entity is Veena Developers, an others as per the filing. Its GSTIN 27AAMFN6585H1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Veena Samrajya-Sector-VIII?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Veena Samrajya-Sector-VIII?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Veena Samrajya-Sector-VIII?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Veena Samrajya-Sector-VIII?

The professionals named in the filing: Architect: Ajay Wade & Associates; Architect: KPA; Architect: Nishit Sunil Sanghavi; Architect: Manish M Shah; Engineer: Arun Singh; Engineer: Rajeev Ranjan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Veena Samrajya-Sector-VIII?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Veena Samrajya-Sector-VIII. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Veena Samrajya-Sector-VIII to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.