Home / Areas / Jalna

New projects and RERA data in Jalna district, Maharashtra

101 projects are registered in Jalna district: 2,869 units across them, 3 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.

101Projects covered
3Registered, last 12 months
2,869Units declared
2,407Units not yet booked
9Completion dates revised
0With declared litigation

Of the 101 covered registrations, 9 have revised their promised completion date and 0 declare litigation. The median project here is 0% booked as of the current data. Every figure comes from the projects' own MahaRERA filings.

Also free on ReraGenie: a monthly RERA report for the seven biggest markets in Maharashtra (Pune, Mumbai, Thane, Navi Mumbai, Nagpur, Nashik and Vasai-Virar): what registered that month, the possession pipeline and the busiest pincodes, from the filings. See the latest editions.

When Jalna projects promise possession

Promised possession year as filed by the builder with MahaRERA, split by what the registration says today. Of 101 projects with a promised date, 36 are recorded delivered, 23 are still on the register and 42 have a registration that has lapsed or been cancelled.

DeliveredOn the registerRegistration lapsed or cancelled

05101520today2018: 4 projects, delivered2018: 2 projects, registration lapsed or cancelled’182019: 6 projects, delivered’192020: 5 projects, delivered2020: 3 projects, registration lapsed or cancelled’202021: 2 projects, delivered2021: 2 projects, registration lapsed or cancelled’212022: 5 projects, delivered2022: 8 projects, registration lapsed or cancelled’222023: 5 projects, delivered2023: 7 projects, registration lapsed or cancelled’232024: 5 projects, delivered2024: 8 projects, registration lapsed or cancelled’242025: 2 projects, delivered2025: 8 projects, registration lapsed or cancelled’252026: 3 projects, on the register2026: 4 projects, registration lapsed or cancelled’262027: 6 projects, on the register’272028: 2 projects, delivered2028: 4 projects, on the register’282029: 4 projects, on the register’292031: 4 projects, on the register’312032: 1 projects, on the register’322033: 1 projects, on the register’33

29 projects promise possession in 2026 or later. Facts as per filings on RERA website.

02505007501,000today’182019: 168 flats, delivered (only 2 of 6 projects filed a flat count)’19’202021: 2 flats, registration lapsed or cancelled’212022: 347 flats, delivered (only 4 of 13 projects filed a flat count)2022: 131 flats, registration lapsed or cancelled (only 4 of 13 projects filed a flat count)’222023: 82 flats, registration lapsed or cancelled (only 1 of 12 projects filed a flat count)’23’242025: 373 flats, registration lapsed or cancelled (only 3 of 10 projects filed a flat count)’252026: 56 flats, on the register (only 3 of 7 projects filed a flat count)2026: 188 flats, registration lapsed or cancelled (only 3 of 7 projects filed a flat count)’262027: 247 flats, on the register (only 1 of 6 projects filed a flat count)’272028: 2 flats, delivered2028: 39 flats, on the register’282029: 709 flats, on the register’292031: 228 flats, on the register’312032: 218 flats, on the register’322033: 79 flats, on the register’33

1,766 flats are promised in 2026 or later, across the 52% of those projects that file a flat count. Hatched years are ones where most builders never filed a count, so the bar understates real supply and cannot be compared with the years beside it. Facts as per filings on RERA website.

How far Jalna possession dates have moved

Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 9 of 100 projects (9%) have moved at least once; the median move is 18 months and the longest is 81 months.

Kept the original dateMoved by under 2 yearsMoved by 2 years or more

05101520Originally due 2018: 6 projects kept the original date, 86% of the yearOriginally due 2018: 1 projects moved by under 2 years, 14% of the year’18Originally due 2019: 5 projects kept the original date, 62% of the yearOriginally due 2019: 2 projects moved by under 2 years, 25% of the yearOriginally due 2019: 1 projects moved by 2 years or more, 12% of the year’19Originally due 2020: 6 projects kept the original date, 86% of the yearOriginally due 2020: 1 projects moved by 2 years or more, 14% of the year’20Originally due 2021: 4 projects kept the original date, 80% of the yearOriginally due 2021: 1 projects moved by under 2 years, 20% of the year’21Originally due 2022: 11 projects kept the original date, 100% of the year’22Originally due 2023: 12 projects kept the original date, 86% of the yearOriginally due 2023: 1 projects moved by under 2 years, 7% of the yearOriginally due 2023: 1 projects moved by 2 years or more, 7% of the year’23Originally due 2024: 12 projects kept the original date, 100% of the year’24Originally due 2025: 10 projects kept the original date, 100% of the year’25Originally due 2026: 6 projects kept the original date, 86% of the yearOriginally due 2026: 1 projects moved by under 2 years, 14% of the year’26Originally due 2027: 5 projects kept the original date, 100% of the year’27Originally due 2028: 4 projects kept the original date, 100% of the year’28Originally due 2029: 4 projects kept the original date, 100% of the year’29Originally due 2031: 4 projects kept the original date, 100% of the year’31Originally due 2032: 1 projects kept the original date, 100% of the year’32Originally due 2033: 1 projects kept the original date, 100% of the year’33

Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

02505007501,000’18Originally due 2019: 168 flats kept the original date, 62% of the year (only 2 of 8 projects filed a flat count)’19Originally due 2020: 247 flats moved by 2 years or more, 14% of the year (only 1 of 7 projects filed a flat count)’20Originally due 2021: 2 flats kept the original date, 80% of the year (only 2 of 5 projects filed a flat count)’21Originally due 2022: 478 flats kept the original date, 100% of the year (only 4 of 11 projects filed a flat count)’22Originally due 2023: 82 flats kept the original date, 86% of the year (only 1 of 14 projects filed a flat count)’23’24Originally due 2025: 373 flats kept the original date, 100% of the year (only 3 of 10 projects filed a flat count)’25Originally due 2026: 188 flats kept the original date, 86% of the year (only 3 of 7 projects filed a flat count)Originally due 2026: 56 flats moved by under 2 years, 14% of the year (only 3 of 7 projects filed a flat count)’26’27Originally due 2028: 40 flats kept the original date, 100% of the year’28Originally due 2029: 709 flats kept the original date, 100% of the year’29Originally due 2031: 228 flats kept the original date, 100% of the year’31Originally due 2032: 218 flats kept the original date, 100% of the year’32Originally due 2033: 79 flats kept the original date, 100% of the year’33

Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.

Permissions and land in Jalna

Whose name the land is in

Every one of the 101 registrations on this page answers this: on 63 the promoter is the only owner named; on 35 the promoter is an owner with other names on the file, which is what a joint development looks like on paper; on 3 the promoter is not an owner. Where other names are on the file, ask which of them signs your agreement for sale. A landowner who is not a party to it is a question for your lawyer before you pay, not a defect in the project.

Where in Jalna: projects by taluka

101 of the 101 registrations on this page name their taluka.

TalukaProjectsShare
Jalna8786%
Partur55%
Ghansawangi44%
4 other talukas55%

Projects in Jalna

Showing 1 to 60 of 101 projects.

Largest first, by the unit count in the filing.

ProjectDeveloperUnitsBookedRegisteredStatus
Nandigram TownshipAt post Daregaon, 431214Anandi Buildcon47028%20 Aug 2024Registered
SECTOR 101DEOGAON, 431202MANISH RAMNIRANJAN AGRAWAL3470%13 May 2020Completed
VITTHALA TOWERSANANDI GINNING, 431203TIRUPATI BUILDCON31947%16 Sep 2019Registration lapsed
SHREE SAI CITY PHASE-IJALNA, 431203SHREE SAI CITY BUILDERS AND DEVELOPERS24764%19 Aug 2017Registered
JINDAL GOYAL SQUAREMANTHA ROAD MANTHA CIRCLE, 431203JINDAL GOYAL REALITY LLP2180%29 Sep 2025Registered
Krishna CapitalSorti Nagar, 431203Krishna Capital1790%29 May 2026Registered
Lalbag, PlottingJalna (M Cl), 431203GO Developers LLP1350%11 Aug 2017Completed
MUKTAINAGARWATUR, 431501MEERA SUBHASH HAJARE1339%3 Jan 2021Registration lapsed
RUKHMINI HEIGHTSJALNA, 431203TIRUPATI INFRA JALNA930%14 Aug 2025Registered
SANT TUKARAM NAGARPARTUR, 431501Jyotibai Devidas Ambhure820%12 Mar 2020Registration lapsed
Anandi Business ComplexJALNA, 431203RIIVA BUILDERS AND DEVELOPERS LLP790%6 Aug 2024Registered
P C VIHARVILLAGE / MOUJE PANSHENDRA, 431203CHECHANI DEVELOPERS690%24 Dec 2025Registered
PC CarnivalJalna (M Cl), 431203Chechani Developers660%31 Oct 2025Registered
Mangalmurti ResidencyS NO 473 (P), 431203Mangalmurti Infra600%26 Sep 2025Registered
SITANAND PARKANANDWADI, 431501SATYANARAYAN RAMESHWAR AGRAWAL580%21 Jul 2020Registration lapsed
RAMRAO VAIDYA NAGARGhansawangi, 431209RAVIKANT RAMRAO VAIDYA AND ARUN RAMRAO VAIDYA570%9 Mar 2020Registration lapsed
KRISHNA SUMANSUMAN RESIDENCY, 431203Krishna Suman5611%6 Aug 2024Registered
RENUKANAGARWATUR, 431501Dilip uttamrao hajare550%25 Dec 2020Registration lapsed
Aurika VistaJalna, 431203Kundan Developers390%22 Jul 2025Registered
MANOR HILLSTATION BUNGALOW PLOTS PHASE 1ANANDGADH, 431203ANANT MUKUND KULKARNI330%6 May 2019Completed
UTKARSH VIHARJalna, 431203UTKARSH CONSTRUCTIONS AOP310%8 Mar 2021Registration lapsed
HARIDARSHAN APARTMENTCTS NO 14676 AND 77 JALNA, 431203SHREEPATI CONSTRUCTION2330%5 Apr 2022Registration lapsed
SITANAND PARKANANDWADI, 431501RUKHMANI DEEPAKKUMAR AGRAWAL160%21 Jul 2020Registration lapsed
Krishna ParkNear Sut GIrni, 431203Krishna Park Developers10%17 Apr 2023Completed
PATIL NAGARKUMBHAR PIMPALGAON, 431211DATTA SAMPATRAO KANTULE AND VISHNU BANSIDHAR KANTULE10%20 Jan 2020Registration lapsed
SHIVAJI NAGARKUMBHAR PIMPALGAON, 431211SHIVAJI EKNATHRAO KANTULE10%20 Jan 2020Registration lapsed
Shriram HeightsBhorkheda, 523453Sadhana new PA changed1100%2 May 2025Completed
364 EWS T/S UNDER PMAY AT JALNA DIS JALNAjalna, 431213AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)--1 Sep 2017Registration lapsed
72 GREENSGUT NO 73, 431202A M PATEL INFRA--5 Apr 2019Registration lapsed
ABAD HEIGHTSJalna (M Cl), 431203ABHAYKUMAR KACHARULAL ABAD--18 Aug 2017Registration lapsed
ABAD PRIDE CITYMama Square, 431203ABAD ESTATE AOP--4 Aug 2017Registration lapsed
ABAD PRIDE CITY PHASE IIABAD ESTATE, 431203ABAD ESTATE AOP--22 Jan 2018Registration lapsed
ABHINAV SUPER MARKETambad, 431204RAMESH NANDLAL SODANI--24 Aug 2017Completed
ADEP BUILDCONKESHAV VIHAR-II, 431203SHIVRATNAM RAJENDRA ADEP--22 Jun 2022Registration lapsed
ANJANEY RESIDENCYJalna (M Cl), 431203ANJANEY LANDMARKS LLP--19 Aug 2017Completed
Ashirwad HomesNear Addl. MIDC Phase-1, 431203Golden Facets Developers Private Limited--9 Jun 2022Registered
Ashtavinayak CityAshtavinayak City, 431203Manoj Dhruwkumar Peety--9 May 2023Completed
Ayeshakiran TownshipJalna (M Cl), 431203Ayesha Township--9 Aug 2017Completed
BRAMHAPURI RESIDENCYJalna, 431203UTKARSH CONSTRUCTIONS AOP--1 Sep 2017Registration lapsed
DATTAKRUPA RESIDENCYJalna (M Cl), 431203CHAYA SUDHAKAR PHAD--27 Oct 2017Completed
Deepak Viharindewadi, 431203Deepak health and wellness ltd--17 Aug 2021Registration lapsed
Deven Renuka PuramGhansawangi, 431209Deven Renukapuram--25 Aug 2021Registration lapsed
FRIENDS CAPITALOLD JALNA, 431203ABDUL SALIM QURESHI--29 Dec 2021Registration lapsed
GOKULDHAM APARTMENTNEAR KINGS COLLEGE, 431203RAJESH BHAGULAL DHAMONE--16 Mar 2018Completed
GURUKRUPA APARTMENTSTATION ROAD, 431203SANDESH JIVANLAL KAKKAD--20 Apr 2022Registration lapsed
GURUKRUPA PLAZAOLD JALNA, 431203SANDESH JIVANLAL KAKKAD--3 Jan 2020Registration lapsed
GURUKRUPA RESIDENCY---, 431203VIGHNAHARTA BUILDCON PRIVATE LIMITED--15 Feb 2023Registered
JAY SHRI KRISHNA TOWERSPLOT NO 3, 431203JAY SHRI KRISHNNA BUILDERS AND DEVELOPERS--15 Jan 2018Registration lapsed
JINDAL CAPITALJalna (M Cl), 431203JINDAL PROP BUILDERS AND DEVELOPERS LLP--7 Nov 2017Completed
JINDAL PRIDEFINE LIVING CO-OP SOCIETY, 431203JINDAL PROP BUILDERS AND DEVELOPERS LLP--28 Aug 2018Completed
KESHAV VIHARINDEWADI, 431203RAJENDRA ADEP--21 Nov 2018Registration lapsed
KHUSHI PARKNEAR KOTHARI PARK, 431203AMJAD ALI SYED ALI SYED--9 Aug 2018Registration lapsed
KRISHA PARKMATOSHREE GREENS, 431203MAHENDRA SHARADCHANDRA DESHPANDE--17 Mar 2025Registered
Krishna ArcadeBansilal Nagar, 431213Krishna Arcade Developers--5 Jun 2018Completed
krishna business centeropp. krishna vatika, 431203krishna business center--27 Feb 2018Completed
Krishna GreensIndewadi, 431203Krishna Greens--15 Jun 2022Registration lapsed
Krishna Heightsbehind krishna mall, 431203Krishna Heights--31 Jul 2024Registered
Krishna Kunj Phase IIIBuypass Road, 431203Krishna developr--14 Dec 2020Completed
Krishna Kunj Phase IVBypass Road, 431203Krishna developr--27 Mar 2023Completed
Krishna LandmarkSaklecha Nagar, 431203PRAPTI BUILDCON LLP--28 Feb 2025Registered
Planning a launch in Jalna? The area market report packs one pincode's whole filed market into one document: every registration and what it has become, when the active stock promises to land, what the market absorbs, the operators and who finances them. A flat Rs 2,999 per pincode. Area report · Rs 2,999  Read a full sample

Developers active in Jalna

Krishna developr (4), CHECHANI DEVELOPERS (3), SHREE SAI CITY BUILDERS AND DEVELOPERS (2), UTKARSH CONSTRUCTIONS AOP (2), ABAD ESTATE AOP (2), SANDESH JIVANLAL KAKKAD (2). Each link opens the promoter's track record built from their own filings.

Frequently asked questions

How do I shortlist among the Jalna projects listed above?

Compare each project against its neighbours, not against the brochure. The median project on this page is 0% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.

What does a revised completion date on a Jalna project actually mean?

The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.

What stamp duty will I pay on a flat in Jalna district?

The rate depends on the local body: roughly 6 to 7 percent inside municipal corporations, 4 percent in municipal council areas and 3 percent in gram panchayat areas, with women buying in their sole name paying 1 percent less. The registration fee is 1 percent of value, capped at Rs 30,000. Duty is charged on the higher of your agreement value and the ready reckoner value. ReraGenie has a free Maharashtra stamp duty calculator under Tools.

What does it mean that some Jalna registrations have lapsed?

A RERA registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then, the registration lapses and the project stops being a registered project: the promoter may not legally market or sell in it, and the Authority can act under section 7 against a defaulting promoter. It does not cancel your agreement for sale or your section 18 rights if you have already booked, and it does not mean construction has stopped. Ask the promoter for the current registration position in writing, and verify it on the MahaRERA portal before you pay any further instalment.

What if a Jalna project shows strong sales but slow construction?

That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.

Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own MahaRERA filings, and we read every report.

Report an errorShare feedback

Data from official MahaRERA filings.

Report an error or share feedback

About Jalna district. Every figure on this page is summed from the projects' own filings, so if a number looks wrong it helps to say which one.