Home / Browse projects / Jalna, Maharashtra / KRISHNA SUMAN
KRISHNA SUMAN
RG-MH-70202 · RERA P51400077311 · Last updated on MahaRERA portal: 7 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 3 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KRISHNA SUMAN is a Residential / Group Housing project by Krishna Suman in Jalna, Maharashtra, registered with MahaRERA as P51400077311 on 6 Aug 2024. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 3 months from the original filing. 6 of the 56 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.
At a glance
Project
- NameKRISHNA SUMAN
- TypeResidential / Group Housing
- Location
- NEAR MANTHA ROAD
- SUMAN RESIDENCY
- Jalna (M Cl)
- Jalna
- 431203
- Pincode431203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51400077311
- ReraGenie IDRG-MH-70202
Builder
- NameKrishna Suman
- Entity typePartnership
- PartnersBhaishree Infra and Facilities Management LLP, Ritesh Radhesham Mantri, Rahul Murarilal Gupta
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Aug 2024
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 30 Jun 2026)
- Buildings2 building records
- Documents filed75 files
Current status
Figures as on 7 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 8 | 0 | 36 | 0 | 36 |
| B | NA | 7 | 0 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 7 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
A71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 7 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed102
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| A | 67 | 67 |
| B | 35 | 35 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Sumandevi Bhagwandas Soni | Jalna (M Cl) | Jalna |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 8.46 cr | Rs 3.27 cr |
| B | NA | Rs 5.30 cr | Rs 2.05 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Hemant Rajmane |
| Engineer | Ravindra Bansode |
| Engineer | Karan Agrawal |
| Chartered Accountant | Pankaj Gilda |
| Partner | Role in project |
|---|---|
| Krishna Suman | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDelay in Supply of Vitrified Tiles due to Irregular Gas supply to tiles factories in Morbi
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Jul 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed75
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 KRISHNA SUMAN.pdf | 7 Aug 2026 |
| Withdrawal Update Form 2File: FORM 2 KRISHNA SUMAN.pdf | 7 Aug 2026 |
| Withdrawal Update Form 3File: FORM 3 KRISHNA SUMAN NEW.pdf | 7 Aug 2026 |
| Form 5 (FY 2025-2026)File: FORM 5 2026.pdf | 11 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 KRISHNA SUMAN.pdf | 10 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 KRISHNA SUMAN.pdf | 10 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 KRISHNA SUMAN.pdf | 10 Jul 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A KRISHNA SUMAN 2025.pdf | 10 Jul 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A KRISHNA SUMAN 2026.pdf | 10 Jul 2026 |
| Form 1File: KRISHNA SUMAN FORM 1.pdf | 14 May 2026 |
| Form 2File: KRISHNA SUMAN FORM 2.pdf | 14 May 2026 |
| Form 3File: KRISHNA SUMAN FORM 3.pdf | 14 May 2026 |
| Disclosure of Sold and Booked InventoryFile: KRISHNA SUMAN SOLD UNSOLD.pdf | 14 May 2026 |
| Form 1File: KRISHNA SUMAN FORM 1.pdf | 14 May 2026 |
| Form 2File: KRISHNA SUMAN FORM 2.pdf | 14 May 2026 |
| Form 3File: KRISHNA SUMAN FORM 3.pdf | 14 May 2026 |
| Disclosure of Sold and Booked InventoryFile: KRISHNA SUMAN SOLD UNSOLD.pdf | 14 May 2026 |
| Form 1File: Form 1 SUMAN.pdf | 14 May 2026 |
| Form 2File: FORM 2.pdf | 14 May 2026 |
| Form 3File: FORM 3.pdf | 14 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Krishna Suman Sold Unsold.pdf | 14 May 2026 |
| Form 1File: FORM 1.pdf | 14 May 2026 |
| Form 2File: Form 2.pdf | 14 May 2026 |
| Form 3File: Form 3.pdf | 14 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Krishna Suman Sold Unsold.pdf | 14 May 2026 |
| Form 1File: FORM 1 KRISHNA SUMAN.pdf | 31 Dec 2025 |
| Form 2File: FORM 2 KRISHNA SUMAN.pdf | 31 Dec 2025 |
| Form 3File: FORM 3 KRISHNA SUMAN.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: KRISHNA SUMAN SOLD UNSOLD.pdf | 31 Dec 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 KRISHNA SUMAN.pdf | 31 Dec 2025 |
| Withdrawal Update Form 1File: FORM 1 KRISHNA SUMAN.pdf | 26 Aug 2025 |
| Withdrawal Update Form 1File: FORM 1 KRISHNA SUMAN.pdf | 26 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 26 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 26 Aug 2025 |
| Withdrawal Update Form 3File: FORM 3 KRISHNA SUMAN.pdf | 26 Aug 2025 |
| Withdrawal Update Form 3File: FORM 3 KRISHNA SUMAN.pdf | 26 Aug 2025 |
| Form 1File: Form 1 Krishna Suman.pdf | 1 Jul 2025 |
| Form 2File: FORM 2 KRISHNA SUMAN.pdf | 1 Jul 2025 |
| Form 3File: FORM 3.pdf | 1 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Krishna Suman Sold Unsold.pdf | 1 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Suman form 2.pdf | 8 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 7 8 24.pdf | 31 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 28 12 24.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 9 12 24.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 7 8 2024.pdf | 31 Jan 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B BANK LETTER NEW.pdf | 1 Aug 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A New.pdf | 1 Aug 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Secured unsecured declaration.pdf | 27 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 New Suman.pdf | 27 Jul 2024 |
| Deviation Report with respect to Allotment letterFile: NO Devaialtion allotment.pdf | 23 Jul 2024 |
| Deviation Report with respect to model copy of AgreementFile: No deviation copy of agreement.pdf | 23 Jul 2024 |
| Declaration in FORM BFile: Form B RM.pdf | 12 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 12 Jul 2024 |
| Other - LegalFile: IMG_0001.pdf | 12 Jul 2024 |
| Other - TechnicalFile: IMG_0001.pdf | 12 Jul 2024 |
| CERSAI detailsFile: Cersai R.pdf | 11 Jul 2024 |
| Copy of the legal title reportFile: Search report new.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 pdf.pdf | 10 Jul 2024 |
| Proforma of Allotment letterFile: Model Form of allotment letter New Format PDF.pdf | 10 Jul 2024 |
| Declaration about Commencement CertificateFile: Declaration abt cmmncmrnt.pdf | 9 Jul 2024 |
| Layout approvalFile: Layout Permission Suman (2 files merged) - converted-2.pdf | 7 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: Layout Permission Suman (2 files merged) - converted-2.pdf | 7 Jul 2024 |
| Proforma of Agreement for saleFile: RERA agreement to sale draft pdf.pdf | 7 Jul 2024 |
| Building plan approvalFile: Building Plan Joint.pdf | 4 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrancess.pdf | 4 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrancess.pdf | 4 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan Joint.pdf | 4 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate - converted.pdf | 4 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Ritesh Mantri.pdf | 4 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Rahul Gupta.pdf | 4 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A_ Rameshbhai C Patel.pdf | 4 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A_ Bhavesh R Patel.pdf | 4 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A_ Taraben R Patel.pdf | 4 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A_ Kajal B Patel.pdf | 4 Jul 2024 |
| PAN CardFile: Krishna Suman PAN Card.pdf | 27 Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jalna
Computed across the 100+ Jalna projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 75 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KRISHNA SUMAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SUMAN RESIDENCY100+ in Jalna
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
VITTHALA TOWERS
TIRUPATI BUILDCON
SHREE SAI CITY PHASE-I
SHREE SAI CITY BUILDERS AND DEVELOPERS
JINDAL GOYAL SQUARE
JINDAL GOYAL REALITY LLP
Krishna Capital
Krishna Capital
Lalbag, Plotting
GO Developers LLP
RUKHMINI HEIGHTS
TIRUPATI INFRA JALNA
See every Jalna project, with the district possession charts
Builder: Krishna Suman
Krishna Suman has 1 registration on MahaRERA, including KRISHNA SUMAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.
Frequently asked questions
What are my rights if KRISHNA SUMAN is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KRISHNA SUMAN?
The registered promoter entity is Krishna Suman, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KRISHNA SUMAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KRISHNA SUMAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KRISHNA SUMAN?
The professionals named in the filing: Architect: Hemant Rajmane; Engineer: Ravindra Bansode; Engineer: Karan Agrawal; Chartered Accountant: Pankaj Gilda. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRISHNA SUMAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback