ReraGenieLog inGet a buyer report

Home / Browse projects / Jalna, Maharashtra / Deven Renuka Puram

Registration lapsed No litigation declared Residential / Group Housing project

Deven Renuka Puram

By Deven Renukapuram

RG-MH-54090 · RERA P51400030480 · Last updated on MahaRERA portal: 24 Feb 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 3 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
9 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

Deven Renuka Puram is a Residential / Group Housing project by Deven Renukapuram in Jalna, Maharashtra, registered with MahaRERA as P51400030480 on 25 Aug 2021. Possession was promised by 11 Jul 2026 and is now 3 months past that date.

At a glance

Project

  • NameDeven Renuka Puram
  • TypeResidential / Group Housing
  • Location
    • Ambad Road
    • Ghansawangi
    • Jalna
    • 431209
  • Pincode431209
  • RERA no.P51400030480
  • ReraGenie IDRG-MH-54090

Builder

  • NameDeven Renukapuram
  • Entity typePartnership
  • PartnersBalkrishna Dasrao Bhakre, Deven Balkrishna Bhakre

Key dates

3 months past promisethis monthRegisteredAug 2021PromisedJul 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Aug 2021
  • Promised completion11 Jul 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Deven Renuka Puram 1 TO 8NA20000
Deven Renuka Puram 9 TO 15NA20000
Deven Renuka Puram 16 TO 22NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

Deven Renuka Puram 1 TO 882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Deven Renuka Puram 9 TO 150%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Deven Renuka Puram 16 TO 220%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,489 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4170.13
Proposed, not sanctioned1,158 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDISHA SQAURE , SUTGIRNI CHOWK, GARKHEDA AREA, AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMIRKUTE ARCHITECTS & IUNTERIOR DESIGNERS
EngineerAJAY KOTGIRE
Chartered AccountantVAIBHAV DANDE
PartnerRole in project
Deven Renukapuram-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Feb 2024

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Cancellation.pdf24 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate period ended 31-03-2022.pdf21 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 Engineer Certificate period ended 31-12-2023.pdf21 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate 31-03-2022.PDF3 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA Certificate 31-12-2022.PDF3 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.PDF3 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1)_11zon.pdf31 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (2).pdf31 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (21-22)_11zon.pdf31 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 31 March 2022.pdf2 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Account Declaration.pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect's Certificate .pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold-Booked Inventory .pdf21 Apr 2023
Details of encumbrances concerned to FinanceFile: B Details of encumbrances concerned to Legal _page-0001.pdf14 Apr 2023
Details of encumbrances concerned to LegalFile: B Details of encumbrances concerned to Legal _page-0001.pdf14 Apr 2023
Declaration about Commencement CertificateFile: Declaration About Commencement certificate .pdf14 Apr 2023
Declaration about Commencement CertificateFile: Decleration of Commencement Certificate_page-0001.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf14 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest In Other Real Estate Organizations .pdf14 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of intrest in other Real Estate organisation (1).pdf14 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged_11zon.pdf14 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupency Certificate.pdf14 Apr 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter_page-0001.pdf14 Apr 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement_page-0001.pdf14 Apr 2023
Copy of the legal title reportFile: Title report.PDF20 Aug 2021
Declaration in FORM BFile: Form B Renukapuram.pdf16 Aug 2021
Declaration about Commencement CertificateFile: Renukapuram Commencement Certificate.pdf13 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf27 Jul 2021
Proforma of Allotment letterFile: ATS.pdf27 Jul 2021
Layout approvalFile: Sanction Layout_compressed.pdf22 Jul 2021
Building plan approvalFile: Sanction Drawing Row House No 01 to 08_compressed.pdf22 Jul 2021
Building plan approvalFile: Sanction Drawing Row House No 09 to 15_compressed.pdf22 Jul 2021
Building plan approvalFile: Sanction Drawing Row House No 16 to 22_compressed.pdf22 Jul 2021
PAN CardFile: Deven Renuka Puram PAN.pdf22 Jul 2021
Details of encumbrancesFile: Renuka Puram Non encambrance.pdf22 Jul 2021
Copy of Layout Approval (in case of layout)File: Sanction Layout_compressed.pdf22 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Sanction Drawing Row House No 01 to 08_compressed.pdf22 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Sanction Drawing Row House No 09 to 15_compressed.pdf22 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: Sanction Drawing Row House No 16 to 22_compressed.pdf22 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Bandhkam Parvangi.pdf22 Jul 2021
Declaration about Commencement CertificateFile: Bandhkam Parvangi.pdf22 Jul 2021
Proforma of Allotment letterFile: Allotment letter.pdf22 Jul 2021

How this compares with Jalna

8%of Jalna projects moved their completion datethis one has not
41%of Jalna registrations have lapsed or been cancelledthis one is among them

Computed across the 100+ Jalna projects on ReraGenie, from their own filings.

Keep Deven Renuka Puram on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghansawangi100+ in Jalna

Builder: Deven Renukapuram

Deven Renukapuram has 1 registration on MahaRERA, including Deven Renuka Puram. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.

Frequently asked questions

What does it mean that Deven Renuka Puram shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Deven Renuka Puram is delayed beyond 11 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Deven Renuka Puram?

The registered promoter entity is Deven Renukapuram, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Deven Renuka Puram?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Deven Renuka Puram?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Deven Renuka Puram?

The professionals named in the filing: Architect: MIRKUTE ARCHITECTS & IUNTERIOR DESIGNERS; Engineer: AJAY KOTGIRE; Chartered Accountant: VAIBHAV DANDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Deven Renuka Puram?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Deven Renuka Puram. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Deven Renuka Puram to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.