AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA): RERA track record

Public Authority ยท attribution by exact filing name, entity resolution in progress

AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) has 9 registrations on MahaRERA, including 364 EWS T/S UNDER PMAY AT JALNA DIS JALNA and CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD. Its filings disclose 8 earlier MahaRERA projects: declares 1 of 3 past projects completed on time.

9RERA registrations
8Past projects disclosed
+14 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 9 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Construction of 1056 EWS Tenements on Gut No 9 Part at Nakshtrawadi,Chhatrapati SambhajinagarP51500080227Opposite of Khivsara Plotting Nakshtrawadi, Aurangabad, 43100211040%9 May 2025Registered
Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, BeedP52300049313Ambejogai, Beed, 43151731448%7 Feb 2023Registration lapsed
Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist HingoliP51200027577hingoli, Hingoli, 4315131800%16 Dec 2020Registration lapsed
364 EWS T/S UNDER PMAY AT JALNA DIS JALNAP51400012018jalna, Jalna, 431213--1 Sep 2017Registration lapsed
736 EWS TS AND 256 MIG TS AT PLOT NO R-1 ADDITIONAL MIDC LATURP52400017486ADD. MIDC, Latur, 413512--23 Aug 2018Registration lapsed
CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABADP51500013212NAKSHATRAWADI, Aurangabad, 431001--21 Sep 2017Completed
CONSTRUCTION OF 368 EWS T/S UNDER PMAY AND 168 MIG ON S.NO.68 AT PADHEGOAN ,DIST-AURANGABADP51500026531AURANGABAD, Aurangabad, 431001--30 Sep 2020Completed
CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABADP51500034364OPPSITE AURANGABAD AIRPORT CHIKALTHANA, Aurangabad, 431001--4 Apr 2022Registered
Proposed construction of 60 L.I.G. T/s Scheme on Plot No. 03, Gut No. 736/Part, Chikalthana, AurangP51500054769Plot No. 03, Gut No. 736/Part, Chikalthana, Aurangabad, Aurangabad, 431001--12 Feb 2024Registered

What this promoter declares as its own experience

AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) declares experience on 8 earlier projects. 8 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

8 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD
P51500013212
20 Apr 201931 Dec 2020+20 months
364 EWS T/S UNDER PMAY AT JALNA DIS JALNA
P51400012018
2 Jul 20191 Sep 2020+14 months
736 EWS TS AND 256 MIG TS AT PLOT NO R-1 ADDITIONAL MIDC LATUR
P52400017486
30 Dec 2022Not completed yetOngoing
Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli
P51200027577
10 Mar 2025Not completed yetOngoing
Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, Beed
P52300049313
31 Dec 2025Not completed yetOngoing
CONSTRUCTION OF 368 EWS T/S UNDER PMAY AND 168 MIG ON S.NO.68 AT PADHEGOAN ,DIST-AURANGABAD
P51500026531
2 Mar 20267 Jul 2024On time
CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD
P51500034364
31 Dec 2027Not completed yetOngoing
Proposed construction of 60 L.I.G. T/s Scheme on Plot No. 03, Gut No. 736/Part, Chikalthana, Aurang
P51500054769
31 Dec 2029Not completed yetOngoing

Frequently asked questions

How do I verify AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.