Home / Browse projects / Jalna, Maharashtra / KHUSHI PARK

Registration lapsed No litigation declared Residential / Group Housing project

KHUSHI PARK

By AMJAD ALI SYED ALI SYED

RG-MH-08058 · RERA P51400017388 · Last updated on MahaRERA portal: 18 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 51 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.
Jul 2022Possession promised51 months past this date
88 of 88Construction stages doneacross 8 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 33 documents Report an error

KHUSHI PARK is a Residential / Group Housing project by AMJAD ALI SYED ALI SYED in Jalna, Maharashtra, registered with MahaRERA as P51400017388 on 9 Aug 2018. Possession was promised by 19 Jul 2022 and is now 51 months past that date.

At a glance

Project

  • NameKHUSHI PARK
  • TypeResidential / Group Housing
  • Location
    • BEHIND NEW MONDHA
    • NEAR KOTHARI PARK
    • Jalna (M Cl)
    • Jalna
    • 431203
  • Pincode431203
  • RERA no.P51400017388
  • ReraGenie IDRG-MH-08058

Builder

  • NameAMJAD ALI SYED ALI SYED
  • Entity typeIndividual

Key dates

51 months past promisethis monthRegisteredAug 2018PromisedJul 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2018
  • Promised completion19 Jul 2022
  • Revised completionNone
  • Buildings8 building records
  • Documents filed33 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSE-HNA20000
ROW HOUSE ANA20000
ROW HOUSE-BNA20000
ROW HOUSE-CNA20000
ROW HOUSE-DNA20000
ROW HOUSE-ENA20000
ROW HOUSE-FNA20000
ROW HOUSE-GNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 18 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

88 of 88 construction stages are filed complete across 8 buildings.

ROW HOUSE-H100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE-B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE-C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE-D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE-E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE-F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE-G100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered56
BuildingClosed/CoveredTotal
ROW HOUSE-H66
ROW HOUSE A88
ROW HOUSE-B66
ROW HOUSE-C88
ROW HOUSE-D66
ROW HOUSE-E88
ROW HOUSE-F66
ROW HOUSE-G88

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,450 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2133.12
Proposed, not sanctioned2,133 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBADI SADAK JALNA

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSYED TAUSEEF ALI
EngineerMUHAMMAD YUNUS
PartnerRole in project
AMJAD ALI SYED ALI SYED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Aug 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 May 2023

Documents filed33

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclousure Khushi Park.PDF18 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certi_Khushi park.PDF18 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: New Doc May 15, 2023 070736 pm.pdf18 May 2023
Declaration about Commencement CertificateFile: Format - D.PDF1 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-2020_compressed.pdf1 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-2021_compressed.pdf1 Aug 2022
CERSAI detailsFile: Asset Based Search Report.PDF1 Aug 2022
Disclosure of sold/ booked inventoryFile: Sold inventary.PDF1 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019.PDF1 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020_compressed.pdf1 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021_compressed.pdf1 Aug 2022
OtherFile: Layout Map.pdf1 Aug 2022
OtherFile: DECLERATION12.pdf6 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf4 Aug 2018
Layout approvalFile: NA ORDER1 (2 files merged) (1).pdf2 Aug 2018
Copy of Layout Approval (in case of layout)File: NA ORDER1 (2 files merged) (1).pdf2 Aug 2018
Certificates of CA (Form 3)File: 1 (8 files merged) (2).pdf2 Aug 2018
Layout approvalFile: Group housing layout.pdf1 Aug 2018
Building plan approvalFile: building permissionNEW.pdf1 Aug 2018
PAN CardFile: Pan Card.pdf1 Aug 2018
Copy of the legal title reportFile: pdf searca.pdf1 Aug 2018
Details of encumbrancesFile: Non Encumbrance NEW.pdf1 Aug 2018
Copy of Layout Approval (in case of layout)File: Group housing layout.pdf1 Aug 2018
Building Plan Approval (IOD)File: building permissionNEW.pdf1 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMNS.pdf1 Aug 2018
Declaration in FORM BFile: Form B Khushi Park 01 (3 files merged).pdf1 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Scan10008 (4 files merged).pdf1 Aug 2018
Proforma of Allotment letterFile: Kushi Park Agreement to Sale Jalna (RERA) August 2018.pdf1 Aug 2018
OtherFile: 712 Extract.pdf1 Aug 2018
OtherFile: Mutation Copies.pdf1 Aug 2018
OtherFile: PR CARD.pdf1 Aug 2018
OtherFile: Mutation Copies.pdf1 Aug 2018
OtherFile: Sale Deed SNo153 P.pdf1 Aug 2018

How this compares with Jalna

8%of Jalna projects moved their completion datethis one has not
41%of Jalna registrations have lapsed or been cancelledthis one is among them

Computed across the 100+ Jalna projects on ReraGenie, from their own filings.

Keep KHUSHI PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR KOTHARI PARK100+ in Jalna

Builder: AMJAD ALI SYED ALI SYED

AMJAD ALI SYED ALI SYED has 1 registration on MahaRERA, including KHUSHI PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.

Frequently asked questions

What does it mean that KHUSHI PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if KHUSHI PARK is delayed beyond 19 Jul 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KHUSHI PARK?

The registered promoter entity is AMJAD ALI SYED ALI SYED, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KHUSHI PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for KHUSHI PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KHUSHI PARK?

The professionals named in the filing: Architect: SYED TAUSEEF ALI; Engineer: MUHAMMAD YUNUS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KHUSHI PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KHUSHI PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KHUSHI PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.