Home / Browse projects / Jalna, Maharashtra / ABAD PRIDE CITY PHASE II

Registration lapsed No litigation declared Others project

ABAD PRIDE CITY PHASE II

By ABAD ESTATE AOP

RG-MH-02648 · RERA P51400015046 · Last updated on MahaRERA portal: 26 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 33 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.
Jan 2024Possession promised33 months past this date
8 of 77Construction stages doneacross 7 buildings; furthest along: Basement (if any), 60%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

ABAD PRIDE CITY PHASE II is a Others project by ABAD ESTATE AOP in Jalna, Maharashtra, registered with MahaRERA as P51400015046 on 22 Jan 2018. Possession was promised by 30 Jan 2024 and is now 33 months past that date.

At a glance

Project

  • NameABAD PRIDE CITY PHASE II
  • TypeOthers
  • Location
    • MANTHA ROAD
    • ABAD ESTATE
    • Jalna (M Cl)
    • Jalna
    • 431203
  • Pincode431203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51400015046
  • ReraGenie IDRG-MH-02648

Builder

  • NameABAD ESTATE AOP
  • Entity typeOthers
  • Named personsABHAYKUMAR KACHRULAL ABAD (HUF), ANILKUMAR KACHARULALJI ABAD (HUF), NARENDRAKUMAR KACHARULAL ABAD (HUF), ABAD ESTATE LLP
  • Other registrations8 more →
  • Completed7 of 9
  • No longer live2 lapsed, de-registered or revoked

Key dates

33 months past promisethis monthRegisteredJan 2018PromisedJan 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Jan 2018
  • Promised completion30 Jan 2024
  • Revised completionNone
  • Buildings7 building records
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JHELUMNA20000
INDUSNA20000
YAMUNANA20000
GANGANA20000
TAPI I AND IINA10000
KAVERI I AND IINA60000
KRISHNA PHASE INA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 26 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Basement (if any), at 60%.

JHELUM0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
INDUS0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
YAMUNA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
GANGA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TAPI I AND II34%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
KAVERI I AND II0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
KRISHNA PHASE I55%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes35%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes40%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,736 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6736.28
Proposed, not sanctioned6,736 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAMA CHOWK, BHAGWAN MAHAVEER MARG, JALNA

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSYED MEHBOOB
EngineerIZHARAHMED
Chartered AccountantSACHIN TOTALA
PartnerRole in project
ABAD ESTATE AOP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: All Sold Inventory.pdf26 Jul 2024
Details of encumbrances concerned to FinanceFile: GetUserDocumentFileContent.pdf19 Jun 2024
Details of encumbrances concerned to FinanceFile: Self Declaration.PDF19 Jun 2024
Details of encumbrances concerned to LegalFile: GetUserDocumentFileContent.pdf19 Jun 2024
Details of encumbrances concerned to LegalFile: Self Declaration.PDF19 Jun 2024
Declaration about Commencement CertificateFile: Format D.PDF19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A_ 2019-20.PDF19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A_ 2020-21.PDF19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A_ 2021-22.PDF19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A_ 2022-23.PDF19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A_ 2023-24.PDF19 Jun 2024
CERSAI detailsFile: cersai report.PDF19 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_ A K Abad.PDF19 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_ N K Abad.PDF19 Jun 2024
Certificates of CA (Form 5)File: Annexure A_ S A Abad.PDF19 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.PDF19 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation of Allotment.PDF19 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement.PDF19 Jun 2024
OtherFile: Bank Name Change 15046.pdf17 Feb 2020
PAN CardFile: Pan card .pdf18 Jun 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf11 Apr 2018
Details of encumbrancesFile: New Doc 2018-01-13.pdf13 Jan 2018
Declaration in FORM BFile: New Doc 2018-01-13.pdf13 Jan 2018
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf13 Jan 2018
Certificates of CA (Form 5)File: SACHIN TOTALA.pdf13 Jan 2018
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf13 Jan 2018
Building plan approvalFile: final3_1.pdf12 Jan 2018
Building plan approvalFile: final4_1.pdf12 Jan 2018
Layout approvalFile: APCITY LAYOUT COPY.pdf12 Jan 2018
Building plan approvalFile: krishna_1.pdf12 Jan 2018
Building plan approvalFile: final2_1.pdf12 Jan 2018
Copy of the legal title reportFile: Legal search report sr no 548.pdf12 Jan 2018
Copy of Layout Approval (in case of layout)File: APCITY LAYOUT COPY.pdf12 Jan 2018
Building Plan Approval (IOD)File: krishna_1.pdf12 Jan 2018
Building Plan Approval (IOD)File: final2_1.pdf12 Jan 2018
Building Plan Approval (IOD)File: final3_1.pdf12 Jan 2018
Building Plan Approval (IOD)File: final4_1.pdf12 Jan 2018

How this compares with Jalna

8%of Jalna projects moved their completion datethis one has not
41%of Jalna registrations have lapsed or been cancelledthis one is among them

Computed across the 100+ Jalna projects on ReraGenie, from their own filings.

Keep ABAD PRIDE CITY PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ABAD ESTATE100+ in Jalna

Builder: ABAD ESTATE AOP

ABAD ESTATE AOP has 9 registrations on MahaRERA, including Pride Phoenix Building - A and PRIDE PHOENIX BUILDING D. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.

Frequently asked questions

What does it mean that ABAD PRIDE CITY PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ABAD PRIDE CITY PHASE II is delayed beyond 30 Jan 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ABAD PRIDE CITY PHASE II?

The registered promoter entity is ABAD ESTATE AOP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ABAD PRIDE CITY PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ABAD PRIDE CITY PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ABAD PRIDE CITY PHASE II?

The professionals named in the filing: Architect: SYED MEHBOOB; Engineer: IZHARAHMED; Chartered Accountant: SACHIN TOTALA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABAD PRIDE CITY PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABAD PRIDE CITY PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABAD PRIDE CITY PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.