Home / Browse projects / Jalna, Maharashtra / ABAD PRIDE CITY

Registration lapsed No litigation declared Others project

ABAD PRIDE CITY

By ABAD ESTATE AOP

RG-MH-01325 · RERA P51400002893 · Last updated on MahaRERA portal: 26 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 49 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.
Sep 2022Possession promised49 months past this date
50 of 55Construction stages doneacross 5 buildings; furthest along: Internal walls, 75%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

ABAD PRIDE CITY is a Others project by ABAD ESTATE AOP in Jalna, Maharashtra, registered with MahaRERA as P51400002893 on 4 Aug 2017. Possession was promised by 29 Sep 2022 and is now 49 months past that date. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameABAD PRIDE CITY
  • TypeOthers
  • Location
    • Main Road
    • Mama Square
    • Jalna (M Cl)
    • Jalna
    • 431203
  • Pincode431203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51400002893
  • ReraGenie IDRG-MH-01325

Builder

  • NameABAD ESTATE AOP
  • Entity typeOthers
  • Named personNARENDRAKUMAR KACHARULAL ABAD (HUF)
  • Other registrations8 more →
  • Completed7 of 9
  • No longer live2 lapsed, de-registered or revoked

Key dates

49 months past promisethis monthRegisteredAug 2017First promiseMar 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion29 Sep 2022
  • Revised completionRevised to 29 Sep 2022 (originally 30 Mar 2021)
  • Buildings5 building records
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GODAVARINA20000
NARMADANA20000
SARASWATINA20000
BRAMHAPUTRANA20000
KRISHNA PHASE INA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 26 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 75%.

GODAVARI100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
NARMADA100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SARASWATI100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BRAMHAPUTRA100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
KRISHNA PHASE I79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 26 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes25%
Street LightingYes15%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,525 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5525.04
Proposed, not sanctioned5,525 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAshok Niwas Mama Chowk, Jalna 431203

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSYED MAHBOOB
EngineerIZHAR AHMED
PartnerRole in project
ABAD ESTATE AOP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51400009116Mar 2021 → Mar 2022

Reason as filed by the promoterThe said project is delayed because of market conditions and Covid 19 problems we all faced

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B.PDF26 Jul 2024
Disclosure of sold/ booked inventoryFile: All Sold Inventory.pdf16 Jul 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Form B.PDF16 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.PDF21 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: N A order.PDF21 Jun 2024
Certificates of CA (Form 3)File: Form 3.PDF21 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A_ 2023-24.PDF20 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure - A_ N K Abad.PDF20 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure - A_ S A Abad.PDF20 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A - A Abad.PDF20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_ 22-23.PDF20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 _2023-24.PDF20 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A_ Bank.PDF20 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation of Allotment.PDF20 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement.PDF20 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINERRS FORM 2.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD AND BOOKED INVENTORY (1).pdf17 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 18-19.pdf17 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20.pdf17 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: C A Form 5 20-21.pdf17 May 2023
Proforma of Agreement for saleFile: Model_Agreement Ffor Sale_in_English.pdf17 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 year 21 to 22.pdf7 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer certificate 20 21.pdf22 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: engineer's certificate 21 22.pdf22 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200228900492_Rahul Vilas Pramilabai HDFC.pdf22 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: C A Certificate 17 18.pdf22 Mar 2023
PAN CardFile: 1 PAN Card (1).pdf2 Jan 2023
Details of encumbrances concerned to FinanceFile: 1 Details of encumbrances.pdf2 Jan 2023
Details of encumbrances concerned to LegalFile: 1 Details of encumbrances.pdf2 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development.pdf2 Jan 2023
Declaration about Commencement CertificateFile: declaration about commncement certificate.pdf2 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer certificate From 2A Q A .pdf2 Jan 2023
Disclosure of sold/ booked inventoryFile: sold unsold inventory FINAL.pdf2 Jan 2023
OtherFile: Bank Name Change 2893.pdf17 Feb 2020
Layout approvalFile: APCITY LAYOUT COPY.pdf30 Jul 2017
Building plan approvalFile: Apcity Building plan1.pdf30 Jul 2017
Building plan approvalFile: Apcity Plan2.pdf30 Jul 2017
Building plan approvalFile: Apcity plan 3.pdf30 Jul 2017
Building plan approvalFile: Apcity plan 4.pdf30 Jul 2017
Building plan approvalFile: Apcity plan 5.pdf30 Jul 2017
Copy of the legal title reportFile: TITLE SEARCH REPORT.pdf30 Jul 2017
Details of encumbrancesFile: Apcity ENCUM.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: APCITY LAYOUT COPY.pdf30 Jul 2017
Building Plan Approval (IOD)File: Apcity Building plan1.pdf30 Jul 2017
Building Plan Approval (IOD)File: Apcity Plan2.pdf30 Jul 2017
Building Plan Approval (IOD)File: Apcity plan 3.pdf30 Jul 2017
Building Plan Approval (IOD)File: Apcity plan 4.pdf30 Jul 2017
Building Plan Approval (IOD)File: Apcity plan 5.pdf30 Jul 2017
Declaration in FORM BFile: Affidivate Form B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate.pdf30 Jul 2017
Certificates of CA (Form 3)File: Apcity CA certificate.pdf30 Jul 2017
Proforma of Allotment letterFile: proforma final.pdf30 Jul 2017

How this compares with Jalna

8%of Jalna projects moved their completion datethis one moved by 18 months
41%of Jalna registrations have lapsed or been cancelledthis one is among them

Computed across the 100+ Jalna projects on ReraGenie, from their own filings.

Keep ABAD PRIDE CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mama Square100+ in Jalna

Builder: ABAD ESTATE AOP

ABAD ESTATE AOP has 9 registrations on MahaRERA, including Pride Phoenix Building - A and PRIDE PHOENIX BUILDING D. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.

Frequently asked questions

What does it mean that ABAD PRIDE CITY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ABAD PRIDE CITY is delayed beyond 29 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ABAD PRIDE CITY?

The registered promoter entity is ABAD ESTATE AOP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ABAD PRIDE CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ABAD PRIDE CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ABAD PRIDE CITY?

The professionals named in the filing: Architect: SYED MAHBOOB; Engineer: IZHAR AHMED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABAD PRIDE CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABAD PRIDE CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABAD PRIDE CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.