RUKHMINI HEIGHTS
RG-MH-88915 · RERA P51400080917 · Last updated on MahaRERA portal: 27 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Jalna registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RUKHMINI HEIGHTS is a Others project by TIRUPATI INFRA JALNA in Jalna, Maharashtra, registered with MahaRERA as P51400080917 on 14 Aug 2025. Possession is promised by 31 Mar 2031. 0 of the 93 units on this registration are recorded sold or booked, and 6 of 44 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameRUKHMINI HEIGHTS
- TypeOthers
- Location
- BHOKARDAN - RAJUR ROAD
- JALNA
- Jalna (M Cl)
- 431203
- Pincode431203
- RERA no.P51400080917
- ReraGenie IDRG-MH-88915
Builder
- NameTIRUPATI INFRA JALNA
- Entity typePartnership
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Aug 2025
- Promised completion31 Mar 2031
- Revised completionNone
- Buildings4 building records
- Documents filed78 files
Current status
Figures as on 27 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A-1 | NA | 11 | 11 | 26 | 14 | 40 |
| A-2 | NA | 11 | 11 | 28 | 0 | 28 |
| B-1 | NA | 6 | 6 | 11 | 10 | 21 |
| B-2 | NA | 5 | 5 | 4 | 0 | 4 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
A-140%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 35% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15% |
A-240%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 35% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 15% |
B-10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B-20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 25% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed216
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A-1 | 96 | 96 |
| A-2 | 73 | 73 |
| B-1 | 37 | 37 |
| B-2 | 10 | 10 |
Land and ownership8
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MR. SANJAY KACHRULAL RATHI | Jalna (M Cl) | Jalna |
| MR. SHARAD PRALHADJI BAGDIYA | Jalna (M Cl) | Jalna |
| MR. ABHAY LAXMANRAO KULKARNI | Jalna (M Cl) | Jalna |
| MR SHIVRATAN SHRIGOPAL MUNDADA | Jalna (M Cl) | Jalna |
| MRS SARLA SHIVRATAN MUNDADA | Jalna (M Cl) | Jalna |
| MR. PIYUSH SHIVRATAN MUNDADA | Jalna (M Cl) | Jalna |
| MRS POOJA PIYUSH MUNDADA | Jalna (M Cl) | Jalna |
| RADHIKA SHARAD BAGDIYA | Jalna (M Cl) | Jalna |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A-1 | NA | Rs 12.73 cr | Rs 4.23 cr |
| A-2 | NA | Rs 12.73 cr | Rs 4.23 cr |
| B-1 | NA | Rs 3.91 cr | - |
| B-2 | NA | Rs 3.91 cr | - |
| - | NA | Rs 1.36 cr | Rs 45.33 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Sameer Ausekar |
| Engineer | Mr Milind Wadekar |
| Chartered Accountant | Yadkikar & Chandak |
| Partner | Role in project |
|---|---|
| TIRUPATI INFRA JALNA | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| SM12600226 | Mrinal Katkar | TIRUPATI INFRA JALNA | 04/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jun 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Apr 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2031
Documents filed78
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 27 Apr 2026 |
| Form 1File: FORM 1 ARCH Sept 25.pdf | 30 Jan 2026 |
| Form 2File: Form 2 30-09-2025.pdf | 30 Jan 2026 |
| Form 3File: Form 3 Sept 25 - new.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30-09-25.pdf | 30 Jan 2026 |
| Form 1File: Form 1 Dec 2025.pdf | 30 Jan 2026 |
| Form 2File: Form 2 Dec 2025.pdf | 30 Jan 2026 |
| Form 3File: Form 3 Dec 25 - new.pdf | 30 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold 31-12-25.pdf | 30 Jan 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certifcate.PDF | 11 Aug 2025 |
| Other - LegalFile: 35 Allottment Letter No deviation.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: BHAVSAR.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SHAILASH SIR.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ABHAY SIR.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: VAZARKAR.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: PATIL.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DEEPAK.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: APPA.pdf | 16 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: AGRAWAL.pdf | 16 Jul 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: VERIFICATION CC.pdf | 15 Jul 2025 |
| Other - LegalFile: 35 Allottment Letter No deviation.pdf | 15 Jul 2025 |
| Other - LegalFile: 5-7.pdf | 15 Jul 2025 |
| Other - LegalFile: 7-7.pdf | 15 Jul 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.PDF | 15 Jul 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank.pdf | 15 Jul 2025 |
| Other - LegalFile: no deviation allotment .pdf | 14 Jul 2025 |
| Deviation Report with respect to model copy of AgreementFile: no deviation ats.pdf | 14 Jul 2025 |
| Other - LegalFile: ATS.pdf | 12 Jul 2025 |
| Other - LegalFile: CC email.PDF | 8 Jul 2025 |
| Copy of the legal title reportFile: SEARCH - converted.pdf | 25 Jun 2025 |
| Proforma of Allotment letterFile: Rera Allotment Letter.pdf | 19 Jun 2025 |
| Proforma of Agreement for saleFile: Rera ATS.pdf | 19 Jun 2025 |
| Declaration about Commencement CertificateFile: Commencement Certificate Format D.PDF | 18 Apr 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.PDF | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Form A.pdf | 12 Apr 2025 |
| Details of encumbrances concerned to FinanceFile: Regarding Encumbrances.PDF | 11 Apr 2025 |
| Declaration in FORM BFile: Notary Form B_compressed.pdf | 11 Apr 2025 |
| CERSAI detailsFile: Cersai Report.PDF | 11 Apr 2025 |
| Details of encumbrances concerned to LegalFile: Regarding Encumbrances.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Sunilkumar.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Sirsat.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Shivaji.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Shailesh.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Deepak.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Agrawal.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Abhay.PDF | 11 Apr 2025 |
| Other - TechnicalFile: Dhananjay.PDF | 11 Apr 2025 |
| Building plan approvalFile: Map 77_compressed.pdf | 9 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Map 77_compressed.pdf | 9 Apr 2025 |
| Layout approvalFile: Layout_compressed.pdf | 26 Mar 2025 |
| Building plan approvalFile: map 17.pdf | 26 Mar 2025 |
| Building plan approvalFile: map 27.pdf | 26 Mar 2025 |
| Building plan approvalFile: map 37_compressed.pdf | 26 Mar 2025 |
| Building plan approvalFile: map 47_compressed.pdf | 26 Mar 2025 |
| Building plan approvalFile: map 57_compressed.pdf | 26 Mar 2025 |
| Building plan approvalFile: map 67_compressed.pdf | 26 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrances Letter Head.PDF | 26 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance Notory.PDF | 26 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Layout_compressed.pdf | 26 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: map 37_compressed.pdf | 26 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: map 67_compressed.pdf | 26 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: map 57_compressed.pdf | 26 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: map 47_compressed.pdf | 26 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: map 27.pdf | 26 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: map 17.pdf | 26 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance Notory.PDF | 26 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrances Letter Head.PDF | 26 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.PDF | 25 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: From 2A.PDF | 25 Mar 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Discloser For Secured.PDF | 25 Mar 2025 |
| Building plan approvalFile: NA Order.PDF | 20 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 20 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order.PDF | 20 Mar 2025 |
| Other - LegalFile: PR Card_149 To 151.PDF | 20 Mar 2025 |
| PAN CardFile: Pan Card_ Tirupati Infra.PDF | 18 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form - 2A.PDF | 18 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Jalna
Computed across the 100+ Jalna projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- All 78 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep RUKHMINI HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near JALNA100+ in Jalna
VITTHALA TOWERS
TIRUPATI BUILDCON
SHREE SAI CITY PHASE-I
SHREE SAI CITY BUILDERS AND DEVELOPERS
JINDAL GOYAL SQUARE
JINDAL GOYAL REALITY LLP
Krishna Capital
Krishna Capital
Lalbag, Plotting
GO Developers LLP
Anandi Business Complex
RIIVA BUILDERS AND DEVELOPERS LLP
See every Jalna project, with the district possession charts
Builder: TIRUPATI INFRA JALNA
TIRUPATI INFRA JALNA has 1 registration on MahaRERA, including RUKHMINI HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Jalna district page.
Frequently asked questions
What are my rights if RUKHMINI HEIGHTS is delayed beyond 31 Mar 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RUKHMINI HEIGHTS?
The registered promoter entity is TIRUPATI INFRA JALNA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RUKHMINI HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RUKHMINI HEIGHTS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RUKHMINI HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RUKHMINI HEIGHTS?
The professionals named in the filing: Architect: Mr Sameer Ausekar; Engineer: Mr Milind Wadekar; Chartered Accountant: Yadkikar & Chandak. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RUKHMINI HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.