ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / SHALIMAR RESIDENCY

Registered No litigation declared Residential / Group Housing project

SHALIMAR RESIDENCY

By SHantee Homes Realty LLP

RG-MH-07683 · RERA P99000076607 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
119 of 119Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

SHALIMAR RESIDENCY is a Residential / Group Housing project by SHantee Homes Realty LLP in Palghar, Maharashtra, registered with MahaRERA as P99000076607 on 18 Jun 2024. Possession is promised by 30 Dec 2029. 0 of the 119 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHALIMAR RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • GOKHIVARE
    • VASAI EAST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • RERA no.P99000076607
  • ReraGenie IDRG-MH-07683

Builder

  • NameSHantee Homes Realty LLP
  • Entity typePartnership
  • GSTIN27ACNFS5210P1ZK
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerNiyaz Abdulsamad Pathan
  • PartnerRAAZ MOHAMMED ABDUL SAMAD PATHAN
  • Other registrations7 more →
  • Completed3 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredJun 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Jun 2024
  • Promised completion30 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Current status

0%0 of 119 units booked
0.0%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHALIMAR RESIDENCY BUILDING NO 11NA13121190119

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

SHALIMAR RESIDENCY BUILDING NO 11: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered21

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,132 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Dec 2025

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNCIAL CORPORATION
Permissible FSI9665.85
Proposed, not sanctioned6,666 sq m
Buildings approved3
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 4 LANDMARK TOWER PUSHPKUNJ COPERATIVE HOUSING SOC OPP BISHOPS HOUSE VASAI ROAD 401202
Estimated costRs 16.00 cr
Work done0.0%
BuildingWingEstimatedIncurred
SHALIMAR RESIDENCY BUILDING NO 11NARs 16.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectENCON
ArchitectMufaddal Merchant
EngineerMohammed shoeb bhati
Chartered AccountantJINESH JOSHI
Chartered AccountantHARESH MEHTA AND ASSOCIATES
PartnerRole in project
SHantee Homes Realty LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2029

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1- SHALIMAR RESIDENCY.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2- SHALIMAR RESIDENCY.pdf24 Apr 2026
Withdrawal Update Form 3File: FORM-03 SHANTEE HOMES REALTY LLP SHALIMAR.pdf24 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5- SHALIMAR RESIDENCY.pdf17 Feb 2026
Withdrawal Update Form 1File: FORM 1 SHALIMAR RESIDENCY.pdf2 Feb 2026
Withdrawal Update Form 2File: FORM 2 SHALIMAR RESIDENCY.pdf2 Feb 2026
Withdrawal Update Form 3File: FORM 3 SHALIMAR RESIDENCY_compressed.pdf2 Feb 2026
Form 1File: FORM 1 SHALIMAR RESIDENCY BLDG-11.pdf18 Dec 2025
Form 2File: FORM 2 SHALIMAR RESIDENCY BLDG NO 11.pdf18 Dec 2025
Form 3File: FORM 3 SHALIMAR RESIDENCY BLDG 11.pdf18 Dec 2025
Disclosure of Sold and Booked InventoryFile: SHALIMAR SOLD UNSOLD SEPT24.pdf18 Dec 2025
Form 1File: FORM 1 SHALIMAR RESIDENCY BLDG-11.pdf18 Dec 2025
Form 2File: FORM 2 SHALIMAR RESIDENCY BLDG-11.pdf18 Dec 2025
Form 3File: FORM 3 SHALIMAR RESIDENCY.pdf18 Dec 2025
Disclosure of Sold and Booked InventoryFile: SHALIMAR RESIDENCY SOLD UNSOLD.pdf18 Dec 2025
Form 1File: FORM 1 SAPPHIRE MAR 25.pdf15 Dec 2025
Form 2File: FORM 2 SHALIMAR MAR 25.pdf15 Dec 2025
Form 3File: FORM-3 SHALIMAR RESIDENCY.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: SHALIMAR31032025.pdf15 Dec 2025
Form 1File: FORM 1 SHALIMAR.pdf15 Dec 2025
Form 2File: FORM 2 SHALIMAR.pdf15 Dec 2025
Form 3File: FORM 3 SHALIMAR RESIDENCY.pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SHALIMAR31122024.pdf15 Dec 2025
Form 1File: FORM 1 SHALIMAR RESIDENCY.pdf7 Nov 2025
Form 2File: FORM 2 SHALIMAR RESIDENCY.pdf7 Nov 2025
Form 3File: FORM 3 SHALIMAR RESIDENCY_compressed.pdf7 Nov 2025
Disclosure of Sold and Booked InventoryFile: SHALIMAR30092025.pdf7 Nov 2025
Form 1File: FORM-1 SHALIMAR RESIDENCY.pdf6 Aug 2025
Form 2File: FORM-2 SHALIMAR RESIDENCY.pdf6 Aug 2025
Form 3File: FORM-3 SHALIMAR RESIDENCY.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD & UNSOLD (SHALIMAR RESIDENCY).pdf6 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHALIMAR FORM 1.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHALIMAR RESIDENCY FORM 3 REDUCE.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SHALIMAR FORM 2.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHALIMAR RESIDENCY BLDG-11.pdf1 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SHALIMAR RESIDENCY BLDG-11.pdf1 Aug 2024
Disclosure of sold/ booked inventoryFile: SHALIMAR RESIDENCY.pdf1 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHALIMAR RESIDENCYBLDG-11.pdf1 Aug 2024
Proforma of Agreement for saleFile: SALE AGREEMENT SHALIMAR.pdf4 Jun 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION IN SALE AGREEMENT.pdf4 Jun 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION IN SALE AGREEMENT IN TABULAR.pdf24 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST OTHER THEN RAAZ.pdf15 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST OTHER THEN NIYAZ.pdf15 Apr 2024
Other - LegalFile: DECLERATION FOR MULTI REGISTRATION.pdf15 Apr 2024
Other - LegalFile: SHALIMAR CC AUTHENTICATION MAIL RERA.pdf15 Apr 2024
Other - LegalFile: Declaration cum-undertaking Annexure -A-Shalimar resdency.pdf4 Apr 2024
Building plan approvalFile: SHALIMAR APPROVED PLAN 1.pdf20 Mar 2024
Building plan approvalFile: SHALIMAR APPROVED PLAN 2.pdf20 Mar 2024
Layout approvalFile: SHALIMAR LAYOUT PLAN1.pdf20 Mar 2024
Copy of Layout Approval (in case of layout)File: SHALIMAR LAYOUT PLAN1.pdf20 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: SHALIMAR APPROVED PLAN 1.pdf20 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: SHALIMAR APPROVED PLAN 2.pdf20 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: RDP LAYOUT.pdf20 Mar 2024
Declaration about Commencement CertificateFile: DECLERATION FOR MULTI REGISTRATION.pdf20 Mar 2024
Other - TechnicalFile: DECLERATION FOR MULTI REGISTRATION.pdf20 Mar 2024
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCES FREE FORM ALL ENCUMBRANCE.pdf9 Mar 2024
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCES FREE FORM ALL ENCUMBRANCE.pdf9 Mar 2024
Declaration about Commencement CertificateFile: FORMAT D - DECLARATION ABOUT COMMENCEMENT CERTIFIATE.pdf9 Mar 2024
Other - LegalFile: Coneyance 1.pdf2 Mar 2024
Other - LegalFile: Coneyance 2.pdf2 Mar 2024
Other - LegalFile: Conveyance 3.pdf2 Mar 2024
Other - LegalFile: Conveyance 4.pdf2 Mar 2024
Details of encumbrances concerned to FinanceFile: NOENCUMBRANCES CONCERNED TO FINANCE.pdf11 Feb 2024
Details of encumbrances concerned to LegalFile: NOENCUMBRANCES CONCERNED TO FINANCE.pdf11 Feb 2024
Declaration in FORM BFile: FORM B SHALIMAR RESIDENCY.pdf23 Jan 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf23 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A SEPARATE BANK ACCOUNT.pdf23 Jan 2024
Deviation Report with respect to Allotment letterFile: DEVIATION IN ALLOTMENT SHALIMAR RESIDENCY.pdf23 Jan 2024
Other - LegalFile: DECLARATION BUILDING APPROVAL.pdf23 Jan 2024
Copy of the legal title reportFile: FORMAT A TITLE CERTIFICATE.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 SHALIMAR RESIDENCY.pdf20 Jan 2024
PAN CardFile: Shantee Homes LLP Pan Card.pdf19 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE SHALIMAR.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 SHALIMAR RESIDENCY.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 SHALIMAR RESIDENCY.pdf19 Jan 2024
CERSAI detailsFile: CERSAI UNDERTAKING.pdf19 Jan 2024

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

6 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SUNSHINE GREEN PARK PHASE -3P99000017859GOKHIVARE, Palghar180Sep 2018CompletedDec 2026Registered original: Jun 2022Jan 2025
SUNSHINE GREEN PARK PHASE 2P99000001294VASAI EAST, Palghar-Jul 2017CompletedJun 2025Registered original: Mar 2019Jan 2025
SHAMROCK RESIDENCYP99000020998MANICKPUR, Palghar-May 2019CompletedApr 2024Sep 2021
ROMAN RESIDENCYP99000021827WADAVALI, Palghar62Jul 2019CompletedDec 2023Jan 1970
SARGAM RESIDENCYP99000016959NAIGAON, Palghar203Jun 2018CompletedDec 2022Jan 1970
SUNSHINE GREEN PARK PHASE IP99000001370VASAI EAST, Palghar-Jul 2017CompletedMar 2018Late, Jul 2018
SARGAM AVENUEP99000001489Chandrapada, Palghar132Jul 2017CompletedMar 2018Jan 1970

How this compares with Palghar

0%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHALIMAR RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI EAST3,200+ in Palghar

Builder: SHantee Homes Realty LLP

SHantee Homes Realty LLP has 8 registrations on MahaRERA, including SUNSHINE GREEN PARK PHASE I and SUNSHINE GREEN PARK PHASE 2. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SHALIMAR RESIDENCY is delayed beyond 30 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHALIMAR RESIDENCY?

The registered promoter entity is SHantee Homes Realty LLP, a partnership as per the filing. Its GSTIN 27ACNFS5210P1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHALIMAR RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHALIMAR RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHALIMAR RESIDENCY?

The professionals named in the filing: Architect: ENCON; Architect: Mufaddal Merchant; Engineer: Mohammed shoeb bhati; Chartered Accountant: JINESH JOSHI; Chartered Accountant: HARESH MEHTA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHALIMAR RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHALIMAR RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHALIMAR RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.