SUNSHINE GREEN PARK PHASE 2

By SHantee Homes Realty LLP

RG-MH-10971 · RERA P99000001294 · Last updated on MahaRERA portal: 24 Jan 2025

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 75 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
26 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 0%
3Complaints at MahaRERAon this registration
Jump to the 102 documents Report an error

SUNSHINE GREEN PARK PHASE 2 is a Others project by SHantee Homes Realty LLP in Palghar, Maharashtra, registered with MahaRERA as P99000001294 on 27 Jul 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 75 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSUNSHINE GREEN PARK PHASE 2
  • TypeOthers
  • Location
    • GOKHIVARE
    • VASAI EAST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000001294
  • ReraGenie IDRG-MH-10971

Builder

  • NameSHantee Homes Realty LLP
  • Entity typePartnership
  • GSTIN27ACNFS5210P1ZK
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerNiyaz Abdulsamad Pathan
  • Other registrations7 more →
  • Completed3 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredJul 2017First promiseMar 2019Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Mar 2019)
  • Buildings5 building records
  • Documents filed102 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUNSHINE GREEN PARK BLDG No 06NA80000
SUNSHINE GREEN PARK BLDG No 07NA100000
PROPOSEDNA50000
PROPOSEDNA50000
Proposed buildingNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.

SUNSHINE GREEN PARK BLDG No 0691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SUNSHINE GREEN PARK BLDG No 0791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
PROPOSED27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PROPOSED27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Proposed building0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed54

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots54
Open Space54
BuildingOpen SpaceTotal
SUNSHINE GREEN PARK BLDG No 061414
SUNSHINE GREEN PARK BLDG No 071212
PROPOSED1212
PROPOSED1212
Proposed building44

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9783.0
Proposed, not sanctioned6,711 sq m
Buildings approved5
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS NO 637 A SHIVALAYA CHANDA VARKAR ROAD BORIVALI

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectENCON
ArchitectMufaddal Merchant
EngineerMohammed shoeb bhati
Chartered AccountantJINESH JOSHI
PartnerRole in project
SHantee Homes Realty LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000010700Mar 2019 → Dec 2024

Reason as filed by the promoterDate: 25/07/2021 To, The Chairman MahaRera REF: NAME OF PROJECT : - SUNSHINE GREEN PARK PHASE-2 COMPANY NAME: M/S SHANTEE HOMES REALTY LLP SUBJECT : MAHARERA PROJECT DATE EXTENSION MAHA RERA NO. P99000001294 Respect Sir, There is amendment in the approved plan and Commencement Certificate no. VVCMC/TP/RDP/VP-5545/328/2021-22 DT 19/07/2021 Additional floor added in the revised development permission due to this amendment the amended part will be completed upto 31st Dec 2024. We request your goodself to please consider our request and extend project MahaRera date to 31st Dec 2024. FOR SHANTEE HO

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000192589Anita RanabhatRaaz Abdulsamad pathan Niyaz Abdulsamad Pathan13/02/2020
CC006000000193372Akhtar Hussain ShaikhShantee Homes Realty LLP02/07/2020
CC006000000193385dipak modakShantee Housing Reality LLP05/07/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Jan 2025

Documents filed102

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GREEN PARK PH-II FORM 1.pdf24 Jan 2025
Certificates of CA (Form 3)File: GREEN PARK BLDG 6_7 FORM 3 REDUCE.pdf24 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GREEN PARK PH-II FORM 2.pdf24 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM-4 SUNHINE GREEN PARK BLDG 6_7.pdf11 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A GREEN PARK BLDG-6 AND 7 31032022.pdf11 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A GREEN PARK BLDG-6 AND 7 31032023.pdf11 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A GREEN PARK BLDG-6 AND 7 31032024.pdf11 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 GREEN PARK BLDG NO 6_7.pdf11 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOC REGN CERT GREEN PARK BLDG NO- 6.pdf8 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate 25112022.pdf8 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Green Park Bldg 6_7_8_10.pdf8 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GREEN PARK BLDG 6.pdf25 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GREEN PARK BLDG 7.pdf25 Nov 2024
Certificates of CA (Form 3)File: SUNSHINE GREEN PARK BULD NO 6 AND 7.pdf25 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SUNSHINE GREEN PARK BLDG NO 6.pdf25 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SUNSHINE GREEN PARK BLDG NO 7.pdf25 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SUNSHINE GREEN PARK BLDG-6AND7.pdf29 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SUNSHINE GREEN PARK BLDG-6AND7.pdf29 Jul 2024
Disclosure of sold/ booked inventoryFile: GREEN PARK 6AND7.pdf29 Jul 2024
Details of encumbrancesFile: ENCUMBRANCE GREEN PARK PH-II.pdf21 Jun 2024
Details of encumbrancesFile: ENCUMBRANCE ENCLAVE.pdf20 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 SUNSHINE GREEN PARK BLDG-6.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 SUNSHINE GREEN PARK BLDG-7.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 SUNSHINE ENCLAVE BLDG-9.pdf29 Apr 2024
Disclosure of sold/ booked inventoryFile: GREEN PARK 6 7.pdf29 Apr 2024
Certificates of CA (Form 3)File: FORM-3 SUNSHINE GREEN PARK 6 and 7.pdf29 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 SUNSHINE GREEN PARK BLDG 6-7.pdf23 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 SUNSHINE GREEN PARK BLDG-6.pdf5 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 SUNSHINE GREEN PARK BLDG-7.pdf5 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 GREEN PARK BLDG-6.pdf5 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 GREEN PARK BLDG-7.pdf5 Feb 2024
Certificates of CA (Form 3)File: FORM-3 SUNSHINE GREEN PARK BLDG-6-7.pdf5 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 LLP 2020-21.pdf7 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-5 LLP 2021-22.pdf7 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED DEVELOPMENT PERMISION31082023.pdf13 Nov 2023
Disclosure of sold/ booked inventoryFile: SUNSHINE GREEN PARK BLDG 6 7.pdf13 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 SUNSHINE GREEN PARK BLDG-6.pdf6 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SUNSHINE GREEN PARK BLDG-7.pdf6 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 SUNSHINE GREEN PARK BLDG-6.pdf6 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 SUNSHINE GREEN PARK BLDG-7.pdf6 Nov 2023
Certificates of CA (Form 3)File: FORM-3 SUNSHINE GREEN PARK 6-7.pdf6 Nov 2023
Proforma of Agreement for saleFile: BLDG NO 6 AGG.pdf11 Apr 2023
Proforma of Agreement for saleFile: BLDG NO 7 AGG.pdf11 Apr 2023
Details of encumbrancesFile: BLDG NO 06 AND 07 ENCUMBRANCE.pdf14 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GREEN PARK BLDG-6.pdf25 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GREEN PARK BLDG-7.pdf25 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GREEN PARK BLDG-6.pdf25 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GREEN PARK BLDG-7.pdf25 Feb 2023
Certificates of CA (Form 3)File: GREEN PARK BLDG 6 7.pdf25 Feb 2023
Details of encumbrancesFile: encumbrance letter- phase 2.pdf17 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED DEV PERMISSION.pdf2 Jul 2022
Disclosure of sold/ booked inventoryFile: GREEN PARK BLDG-6 - 7.pdf10 Mar 2022
Disclosure of sold/ booked inventoryFile: SUNSHINE GREEN PARK PH-2 BLDG-6-7.pdf10 Mar 2022
Form 2AFile: FORM 2A RAHUL GREEN PH2.pdf8 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: REVISED DEVELOPMENT PERMISSION.pdf3 Sep 2021
Declaration in FORM BFile: GREEN PARK PH-II FORM- 2A-20-02-20.pdf6 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: LLP FORM 2A PH-II MAR 21.pdf6 Aug 2021
Form 2AFile: GREEN PARK PH-II FORM 2A RAHUL.pdf6 Aug 2021
Form 2AFile: GREEN PARK PH-II FORM 2A RAHUL.pdf6 Aug 2021
Form 2AFile: LLP FORM 2A PH-II MAR 21.pdf6 Aug 2021
Form 2AFile: GREEN PARK FORM 2A 30-06-2021.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GREEN PARK PH-II FORM 2A RAHUL.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GREEN PARK PH-II FORM 2A RAHUL.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: GREEN PARK PH-II FORM- 2A-20-02-20.pdf6 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: LLP FORM 2A PH-II MAR 21.pdf6 Aug 2021
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD DISCOLOSURE PH-2.pdf6 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 SUNSHINE GREEN PARK PH-2.PDF6 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION FORMAT D PH III.pdf5 Aug 2021
Declaration in FORM BFile: FORM B GREEN PARK PH-2.pdf5 Aug 2021
Form 2AFile: GREEN PARK PH-II FORM 2A 30062019.pdf5 Aug 2021
Form 2AFile: FORM-2A GREEN PARK PH II.pdf5 Aug 2021
Form 2AFile: FORM-2A GREEN PARK PH II.pdf5 Aug 2021
Form 2AFile: FORM-2 LLP PH-2.pdf5 Aug 2021
Form 2AFile: GREEN PARK PH-II FORM 2A RAHUL.pdf5 Aug 2021
Disclosure of sold/ booked inventoryFile: GREEN PARK SOLD AND UNSOLD.pdf5 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SUNSHINE GREEN PARK RERA AUDIT PH-II_013.pdf8 Apr 2021
Certificates of CA (Form 5)File: SUNSHINE GREEN PARK PH-II FORM 5.PDF7 Mar 2020
Form 2AFile: FORM-4 GREEN PARK 6,7.pdf13 Feb 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM-4 GREEN PARK 6 AND 7.pdf5 Jan 2020
OtherFile: GP INWARD.pdf17 Jun 2019

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SUNSHINE GREEN PARK PHASE -3P99000017859GOKHIVARE, Palghar180Sep 2018CompletedDec 2026Registered original: Jun 2022Jan 2025
SHAMROCK RESIDENCYP99000020998MANICKPUR, Palghar-May 2019CompletedApr 2024Sep 2021
ROMAN RESIDENCYP99000021827WADAVALI, Palghar62Jul 2019CompletedDec 2023Jan 1970
SARGAM RESIDENCYP99000016959NAIGAON, Palghar203Jun 2018CompletedDec 2022Jan 1970
SUNSHINE GREEN PARK PHASE IP99000001370VASAI EAST, Palghar-Jul 2017CompletedMar 2018Late, Jul 2018
SARGAM AVENUEP99000001489Chandrapada, Palghar132Jul 2017CompletedMar 2018Jan 1970

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 75 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUNSHINE GREEN PARK PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI EAST3,200+ in Palghar

2 kmSUNSHINE GREEN PARK PHASCompleted 34Lapsed / revoked 17Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: SHantee Homes Realty LLP

SHantee Homes Realty LLP has 8 registrations on MahaRERA, including SUNSHINE GREEN PARK PHASE I and SUNSHINE GREEN PARK PHASE 2. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SUNSHINE GREEN PARK PHASE 2 is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUNSHINE GREEN PARK PHASE 2?

The registered promoter entity is SHantee Homes Realty LLP, a partnership as per the filing. Its GSTIN 27ACNFS5210P1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUNSHINE GREEN PARK PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUNSHINE GREEN PARK PHASE 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUNSHINE GREEN PARK PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUNSHINE GREEN PARK PHASE 2?

The professionals named in the filing: Architect: ENCON; Architect: Mufaddal Merchant; Engineer: Mohammed shoeb bhati; Chartered Accountant: JINESH JOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUNSHINE GREEN PARK PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUNSHINE GREEN PARK PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUNSHINE GREEN PARK PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.