Home / Browse projects / Palghar, Maharashtra / Suraksha Smart City - Phase I

Registered Litigation declared Residential / Group Housing project

Suraksha Smart City - Phase I

By Conceptual Advisory Services LLP

RG-MH-21684 · RERA P99000023396 · Last updated on MahaRERA portal: 8 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 24 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken
  • Rs 390.01 crore secured on the land, in favour of KOTAK MAHINDRA BANK LIMITED

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
50 of 110Construction stages doneacross 10 buildings; furthest along: Internal walls, 97%
1,543 of 7,552Units unsoldnot recorded sold or booked
24Complaints at MahaRERAon this registration
Jump to the 464 documents Report an error

Suraksha Smart City - Phase I is a Residential / Group Housing project by Conceptual Advisory Services LLP in Palghar, Maharashtra, registered with MahaRERA as P99000023396 on 12 Dec 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 6,009 of the 7,552 units on this registration are recorded sold or booked, and 50 of 110 construction stages are filed complete. 24 complaints are on record with the regulator.

At a glance

Project

  • NameSuraksha Smart City - Phase I
  • TypeResidential / Group Housing
  • Location
    • RAJAVALI VILLAGE
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000023396
  • ReraGenie IDRG-MH-21684

Builder

  • NameConceptual Advisory Services LLP
  • Entity typePartnership
  • GSTIN27AANFC1396C1ZG
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerBhushan Prakashbhai Mehta
  • Designated PartnerRAJ JAYSINGH KARIYA
  • Other registrations2 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredDec 2019First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Dec 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
  • Buildings10 building records
  • Documents filed464 files

Current status

80%6009 of 7,552 units booked
77.9%Work done, per cost certificate

Figures as on 8 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 17NA25259279936
Building No 18NA252563225657
Building No 19NA252581214826
Building No 20NA252590017917
Building No 8NA252563218650
Building No 9NA25258120812
Building No 10NA25256320632
Building No 14NA252563225657
Building No 15NA252581214826
Building No 16NA25256327639

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Internal walls, at 97%.

Building No 1751%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
Building No 1882%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 1980%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%
Building No 2082%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building No 853%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises58%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
Building No 951%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises58%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1027%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1456%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Building No 1561%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
Building No 1656%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises83%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.28%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes46%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes26%
Landscaping & Tree PlantingYes25%
Street LightingYes25%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes30%
Water conservation /Rain water harvestingYes30%
Energy managemcntYes25%
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed471

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots471
Closed/Covered471
BuildingClosed/CoveredTotal
Building No 17118118
Building No 189292
Building No 199696
Building No 20100100
Building No 86060
Building No 911
Building No 1011
Building No 1411
Building No 1511
Building No 1611

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area18,134 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofKOTAK MAHINDRA BANK LIMITED
Secured amountRs 390.01 crore
CERSAI search filedYes
Declared on2 Dec 2025

Approvals and building plan

Sanctioning authorityVasai Virar City Municipal Corporation
Permissible FSI209650.37
Proposed, not sanctioned209,650 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTrans Trade Centre, Near Floral Deck Plaza, Seepz, Midc Andheri East, Mumbai- 400 093
Estimated costRs 1,241.85 cr
Cost incurredRs 967.00 cr
Work done77.87%
BuildingWingEstimatedIncurred
Building No 20NARs 146.15 crRs 145.57 cr
Building No 17NARs 145.82 crRs 107.16 cr
Building No 9NARs 130.02 crRs 91.64 cr
Building No 15NARs 129.86 crRs 103.25 cr
Building No 19NARs 128.79 crRs 123.05 cr
Building No 10NARs 98.76 crRs 18.05 cr
Building No 14NARs 98.74 crRs 78.42 cr
Building No 8NARs 98.69 crRs 70.00 cr
Building No 16NARs 98.67 crRs 76.92 cr
Building No 18NARs 98.23 crRs 97.74 cr
-NARs 68.12 crRs 55.20 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanat Mehta
EngineerMukesh Kumar
EngineerAnand Gupta
Chartered AccountantVipul Jain
Chartered AccountantGohel & Associates LLP
PartnerRole in project
Conceptual Advisory Services LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000018101Dec 2024 → Dec 2026

Reason as filed by the promoter1. WE WERE PLANNING TO AMEND OUR PROJECT PLANS DUE TO WHICH OUR PROJECT EXECUTION PLANNING GOT DELAYED.; 2. WE HAVE NOT SOLD UNITS IN 4 BUILDINGS, THEREFORE WE COULD NOT COMPLETE THE WORK FOR 4 BUILDINGS AS ORIGNINALLY PLANNED. ; 3. DELAY DUE TO COVID 19 OUTBREAK. WE HAVE UPLOADED COVERING PAGE AT SR. NO. 71 (SR. NO. 1 OF DOCUMENT CATEGORY- OTHERS) DUE TO SIZE RESTRICTION, WE HAVE UPLOADED SERIALLY ARRANGED CONSENTS IN MULTIPLE PDF FILE. KINDLY NOTE THAT WE HAVE OBTAINED CONSENT FROM 67.64 PERCENT (MORE THAN 51%) ALLOTTEES FOR EXTENSION OF PROJECT COMPLETION DATE AND WE HAVE ALREADY UPDATED TH

Litigation declared3

CaseCourtStatus
106/2021Vasai CourtOngoing
TNC/39/2018Revenue courtOngoing
9432/2024Bombay High CourtOngoing

Complaints filed with MahaRERA24

Case no.ComplainantRespondentFiled
CC12501174ANAND JOSEPH ALMEIDAConceptual Advisory Services LLP08/04/2025
CC12600846Pankaj Pandurang GholeConceptual Advisory Services LLP15/02/2026
CC12502442ROHIT RAMESH DESAIConceptual Advisory Services LLP17/07/2025
CC12502647CHANDAN ROYConceptual Advisory Services LLP31/07/2025
CC12504513VIVEKKUMAR VINODKUMAR GUPTAConceptual Advisory Services LLP17/12/2025
CC12503284Rajesh Chhotelal GuptaConceptual Advisory Services LLP14/09/2025
CC12601998Vaibhav Jaywant LadConceptual Advisory Services LLP04/04/2026
CC12504124Roshan Uraban DsilvaConceptual Advisory Services LLP22/11/2025
CC12504295ZAKIR KADAR BASHAConceptual Advisory Services LLP05/12/2025
CC12600441vinod PatwaConceptual Advisory Services LLP24/01/2026
CC12602935Sandesh Kishor TitwalkarConceptual Advisory Services LLP19/05/2026
CC12602096Bhushan Kashiram DhuriSuraksha Realty Limited (Promoter of Suraksha Smart City Project)09/04/2026
CC12601711Anushka Akash AcharekarConceptual Advisory Services LLP25/03/2026
CC12602106Suresh Arjun KonarConceptual Advisory Services LLP10/04/2026
CC12602489Farhan Mohd Nasim KhanConceptual Advisory Services LLP28/04/2026
CC12602169srikanth GidlaConceptual Advisory Services LLP13/04/2026
CC12602715Aman Arun NikamConceptual Advisory Services LLP10/05/2026
CC12602950PRANAY SANTOSH PAWARConceptual Advisory Services LLP19/05/2026
CC12603343ASHFAQ AHMED SHAIKHConceptual Advisory Services LLP01/06/2026
CC12603199Amit PrajapatiConceptual Advisory Services LLP28/05/2026
CC12603701Bhavika Jethalal ThakkarConceptual Advisory Services LLP15/06/2026
CC12603900Jigar Paresh MistryConceptual Advisory Services LLP24/06/2026
CC12603798Rundhadevi VinodKumar VishwakarmaConceptual Advisory Services LLP19/06/2026
CC12604353Devendra Mani TiwariConceptual Advisory Services LLP12/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed464

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 464 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2019-2020)File: Form 5_CASLLP_FY19-20.pdf8 Jun 2026
Form 5 (FY 2020-2021)File: Conceptual - Form - 5_FY2021.pdf8 Jun 2026
Form 5 (FY 2021-2022)File: Conceptual - Annual Report FY 2122.pdf8 Jun 2026
Form 5 (FY 2022-2023)File: Form No 5 2223.pdf8 Jun 2026
Form 5 (FY 2023-2024)File: FORM 5_FY2324.pdf8 Jun 2026
Withdrawal Update Form 1File: Merged Form 3.pdf4 Jun 2026
Withdrawal Update Form 1File: Merged Form 3.pdf4 Jun 2026
Withdrawal Update Form 2File: Form 2 Mar 26 Phase 1.pdf4 Jun 2026
Withdrawal Update Form 2File: Form 2 Mar 26 Phase 1.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3 Phase 1 Mar 26.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3 Phase 1 Mar 26.pdf4 Jun 2026
Withdrawal Update Form 1File: Form 1 merged June 25.pdf13 Mar 2026
Withdrawal Update Form 1File: Form 1 Merged Sep 25.pdf13 Mar 2026
Withdrawal Update Form 1File: Form 1 merged Dec 25.pdf13 Mar 2026
Withdrawal Update Form 2File: FORM-2-PHASE-1.pdf13 Mar 2026
Withdrawal Update Form 2File: Form 2 Phase I As on 30092025.pdf13 Mar 2026
Withdrawal Update Form 2File: Form 2 Phase I ason 31122025.pdf13 Mar 2026
Withdrawal Update Form 3File: Form 3 Compressed Jun 25.pdf13 Mar 2026
Withdrawal Update Form 3File: Form 3 Compressed Sep 25.pdf13 Mar 2026
Withdrawal Update Form 3File: Form 3 Compressed Dec 25.pdf13 Mar 2026
Layout approvalFile: MASTER LAYOUT PLAN 160224 compressed.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-08-SHEET NO-1 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-08-SHEET NO-2 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-08-SHEET NO-3 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-08-SHEET NO-4 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-09-SHEET NO-1 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-09-SHEET NO-2 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-09-SHEET NO-3 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-09-SHEET NO-4 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-10-SHEET NO-1 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-10-SHEET NO-2 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-10-SHEET NO-3 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-10-SHEET NO-4 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-14-SHEET NO-1 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-14-SHEET NO-2 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-14-SHEET NO-3 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-14-SHEET NO-4 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-15-SHEET NO 1 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-15-SHEET NO-2 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-15-SHEET NO-3 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-15-SHEET NO-4 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-16-SHEET NO 1 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-16-SHEET NO 2 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-16-SHEET NO-3 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR NO-IV A-BLDG NO-16-SHEET NO-4 OF 4.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 17 SHEET 1-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 17 SHEET 2-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 17 SHEET 3-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 17 SHEET 4-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 17 SHEET 5-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 18 SHEET 1-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 18 SHEET 2-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 18 SHEET 3-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 18 SHEET 4-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 18 SHEET 5-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 19 SHEET 1-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 19 SHEET 2-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 19 SHEET 3-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 19 SHEET 4-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 19 SHEET 5-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 20 SHEET 1-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 20 SHEET 2-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 20 SHEET 3-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 20 SHEET 4-5.pdf5 Jan 2026
Building plan approvalFile: SECTOR IV BLDG NO 20 SHEET 5-5.pdf5 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf2 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf2 Dec 2025
Withdrawal Update Form 2File: FORM-2-PHASE-1.pdf2 Dec 2025
Withdrawal Update Form 2File: FORM-2-PHASE-1.pdf2 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf2 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf2 Dec 2025
Form 5 (FY 2024-2025)File: Form 5_Mar2025_Signed.pdf2 Dec 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 part 1_Ssigned.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Part 2_signed.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Part 3_signed.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Part 4-signed.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 IS NOT REQUIRED TO BE UPLOADED FOR PERIOD.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 IS NOT REQUIRED TO BE UPLOADED FOR PERIOD.pdf7 Feb 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Suraksha Smart City - Phase IIIP99000081050Rajivali Village, Palghar1,808Nov 2025OngoingDec 2029Not due yet

How this compares with Palghar

80%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Suraksha Smart City - Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAJAVALI VILLAGE3,200+ in Palghar

2 kmSuraksha Smart City - PhCompleted 17Lapsed / revoked 13Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 78 registered projects within 2 km.

Builder: Conceptual Advisory Services LLP

Conceptual Advisory Services LLP has 3 registrations on MahaRERA, including Suraksha Smart City - Phase I and Suraksha Smart City - Phase III. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Suraksha Smart City - Phase I is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Suraksha Smart City - Phase I?

The registered promoter entity is Conceptual Advisory Services LLP, a partnership as per the filing. Its GSTIN 27AANFC1396C1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Suraksha Smart City - Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Suraksha Smart City - Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Suraksha Smart City - Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Suraksha Smart City - Phase I?

The professionals named in the filing: Architect: Sanat Mehta; Engineer: Mukesh Kumar; Engineer: Anand Gupta; Chartered Accountant: Vipul Jain; Chartered Accountant: Gohel & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Suraksha Smart City - Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Suraksha Smart City - Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Suraksha Smart City - Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.