Home / Browse projects / Aurangabad, Maharashtra / NABHRAJ TRILOK HEIGHTS
NABHRAJ TRILOK HEIGHTS
By NABHRAJ BUILDERS AND DEVELOPERS PVT LTD
RG-MH-93707 · RERA P51500032020 · Last updated on MahaRERA portal: 25 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NABHRAJ TRILOK HEIGHTS is a Residential / Group Housing project by NABHRAJ BUILDERS AND DEVELOPERS PVT LTD in Aurangabad, Maharashtra, registered with MahaRERA as P51500032020 on 3 Dec 2021. Possession is promised by 31 Dec 2029. The completion date has moved by 36 months from the original filing.
At a glance
Project
- NameNABHRAJ TRILOK HEIGHTS
- TypeResidential / Group Housing
- Location
- SURVEY NO 27(PART)
- Shahnoorwadi
- Aurangabad
- 431003
- Pincode431003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500032020
- ReraGenie IDRG-MH-93707
Builder
- NameNABHRAJ BUILDERS AND DEVELOPERS PVT LTD
- Entity typeCompany
- CINU70200MH2021PTC360567
- GSTIN27AAHCN6011E1ZR
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Managing DirectorsRAJESH BUTOLE, AKASH BUTOLE
- Other registrations5 more →
- Completed1 of 6
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Dec 2021
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2026)
- Buildings5 building records
- Documents filed84 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING - A | NA | 12 | 11 | 0 | 0 | 0 |
| WING - B | NA | 12 | 11 | 0 | 0 | 0 |
| WING - C | NA | 12 | 12 | 0 | 0 | 0 |
| MHADA BUILDING | NA | 7 | 0 | 0 | 0 | 0 |
| E Wing Cancelled | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 25 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 80%.
WING - A79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
WING - B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
WING - C9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MHADA BUILDING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E Wing Cancelled0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 30% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | Yes | 50% |
Parking filed88
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING - A | 18 | 16 | 34 |
| WING - B | 13 | 10 | 23 |
| WING - C | 13 | 10 | 23 |
| MHADA BUILDING | 0 | 8 | 8 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| TrilokSIngh Tarasingh Jabinda | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manggal Design |
| Architect | Anurag R Butole |
| Engineer | Kailas Laxman Sonawane |
| Engineer | Core Consultant |
| Chartered Accountant | R B Sharma and Co |
| Chartered Accountant | K S B A and Co |
| Chartered Accountant | R. B. Sharma & Co. |
| Partner | Role in project |
|---|---|
| NABHRAJ BUILDERS AND DEVELOPERS PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to technical issues we required extension for the project consent obtained from the allottees
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Nov 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed84
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Trilok Mar 26.pdf | 25 Apr 2026 |
| Form 2File: Form 2 Trilok Mar 26.pdf | 25 Apr 2026 |
| Form 3File: Form 3 Trilok Mar 26.pdf | 25 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Trilok Mar 26.pdf | 25 Apr 2026 |
| Form 1File: Form 01 Trilok Heights.pdf | 25 Feb 2026 |
| Form 2File: Form 02 Trilok Heights.pdf | 25 Feb 2026 |
| Form 3File: Form 03 Trliok Heights.pdf | 25 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold UnSold Trilok Heights.pdf | 25 Feb 2026 |
| Form 1File: Form 1 Arch Trilok Sep 25.pdf | 13 Nov 2025 |
| Form 2File: Form 2 Egg Trilok Sep 25.pdf | 13 Nov 2025 |
| Form 3File: Form 3 Declaration Trilok Sep 25.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SoldUnsold Trilok Sep 25.pdf | 13 Nov 2025 |
| Form 1File: Form 01 Arch Trilok.pdf | 14 Aug 2025 |
| Form 2File: Eng Certificate Trilok June 2025.pdf | 14 Aug 2025 |
| Form 3File: CA Certificate june 2025.pdf | 14 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold UnSold Trilok June 2025.pdf | 14 Aug 2025 |
| Form 1File: Nabhraj Ryan Business Form-1 Dec 24.pdf | 29 May 2025 |
| Form 2File: Nabhraj Ryan Business Form-2 Dec 24.pdf | 29 May 2025 |
| Form 3File: Nabhraj Ryan Business Form-3 DeclarationDec 24.pdf | 29 May 2025 |
| Form 1File: Nabhraj Ryan Business Form-1 March 25.pdf | 29 May 2025 |
| Form 2File: Nabhraj Ryan Business Form-2 March 25.pdf | 29 May 2025 |
| Form 3File: Nabhraj Ryan Business Form-3 Declaration March 25.pdf | 29 May 2025 |
| 1 Form 1 Trilok Dec 24 | 29 Apr 2025 |
| 2 Form 1 Trilok Mar 25 | 29 Apr 2025 |
| 3 Form 2 Trilok Dec 24 | 29 Apr 2025 |
| 4 Form 2 Trilok Mar 25 | 29 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01 Arch Trilok June 24.pdf | 15 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01 Arch Trilok Sep 24.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 Trilok June 24.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 Trilok Sep 24.pdf | 15 Jan 2025 |
| Building plan approvalFile: Plan 1.pdf | 9 Jul 2024 |
| Building plan approvalFile: Wing A.pdf | 9 Jul 2024 |
| Building plan approvalFile: Wing B.pdf | 9 Jul 2024 |
| Building plan approvalFile: Wing C.pdf | 9 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf | 9 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Wing A.pdf | 9 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Wing B.pdf | 9 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Wing C.pdf | 9 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commecment Certificate.pdf | 9 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2023 Trilok Heights.pdf | 8 Jun 2024 |
| Declaration in FORM BFile: Form B.pdf | 30 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 30 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer.pdf | 30 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineer.pdf | 30 May 2024 |
| Disclosure of sold/ booked inventoryFile: trilok heights sold unsold .pdf | 30 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June 2023 Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sep 2023 Form 1.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 2023 Form 1.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Trilok HeightsJune 2023 Engg 2.pdf | 30 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Trilok Heights Sep 2023 Form 2.pdf | 30 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Trilok Heights Dec 2023 Engg 2.pdf | 30 Mar 2024 |
| Details of encumbrancesFile: Encumbraces declaration.pdf | 6 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Trilok Heights 22-23.pdf | 17 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold March 23.pdf | 25 Aug 2023 |
| PAN CardFile: PAN.pdf | 24 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch March 23.pdf | 24 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng March 23.pdf | 24 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 24 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A 22-23.pdf | 24 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Trilok - final_compressed.pdf | 17 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Form 5.pdf | 5 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: soda.pdf | 1 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 1 Dec 2022 |
| Copy of the legal title reportFile: Title Search Latest (1).pdf | 24 Nov 2021 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 24 Nov 2021 |
| Declaration in FORM BFile: Form B Builders.pdf | 13 Nov 2021 |
| Layout approvalFile: HPSCANNER1423 and 24-compressed.pdf | 13 Oct 2021 |
| Layout approvalFile: HPSCANNER1425 and 26-compressed.pdf | 13 Oct 2021 |
| Layout approvalFile: HPSCANNER1427 and 28-compressed.pdf | 13 Oct 2021 |
| Building plan approvalFile: HPSCANNER1423 and 24-compressed.pdf | 13 Oct 2021 |
| Building plan approvalFile: HPSCANNER1425 and 26-compressed.pdf | 13 Oct 2021 |
| Building plan approvalFile: HPSCANNER1427 and 28-compressed.pdf | 13 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: HPSCANNER1423 and 24-compressed.pdf | 13 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: HPSCANNER1425 and 26-compressed.pdf | 13 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: HPSCANNER1427 and 28-compressed.pdf | 13 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER1423 and 24-compressed.pdf | 13 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER1425 and 26-compressed.pdf | 13 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER1427 and 28-compressed.pdf | 13 Oct 2021 |
| Declaration about Commencement CertificateFile: Declaration About Commencement.pdf | 13 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Trilok Heights.pdf | 13 Oct 2021 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Nabhraj RYAN BUSINESS HUBP51500052587 | Mondha, Aurangabad | 160 | Sep 2023 | Ongoing | Dec 2030 | Not due yet |
| NABHRAJ NIKUNJP51500049264 | SHENDRA, Aurangabad | - | Feb 2023 | Ongoing | Dec 2028 | Not due yet |
| NABHRAJ NANDANVAN PHASE IIIP51500021357 | CHIKALTHANA, Aurangabad | 168 | Jun 2019 | Ongoing | Jun 2026Registered original: Jul 2025 | Not delivered |
| Nabhraj TrimurtiP51500047311 | Shreyanagar, Osmanpura, Aurangabad | - | Oct 2022 | Ongoing | Feb 2025 | Not delivered |
| Nabhraj Nandanvan Phase IIP51500003126 | Aurangabad (M Corp.), Aurangabad | - | Aug 2017 | Completed | May 2018 | May 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 84 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NABHRAJ TRILOK HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shahnoorwadi1,400+ in Aurangabad
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
VILLO 67
CHOUDHARY BHAISHREE LANDMARKS LLP
Nabhraj Gharkul
Nabhraj Construction
Gursahani Twin Tower
Shree Hinglajmata Constructions
MADHURA PARK
Madhura Land Developers
VYANKATESH PARADISE
TIRUPATI INFRA
KASLIWAL NIWARA
SANJAY SUGANCHAND KASLIWAL
See every Aurangabad project, with the district possession charts
Builder: NABHRAJ BUILDERS AND DEVELOPERS PVT LTD
NABHRAJ BUILDERS AND DEVELOPERS PVT LTD has 6 registrations on MahaRERA, including NABHRAJ TRILOK HEIGHTS and Nabhraj Trimurti. Its filings disclose 6 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if NABHRAJ TRILOK HEIGHTS is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NABHRAJ TRILOK HEIGHTS?
The registered promoter entity is NABHRAJ BUILDERS AND DEVELOPERS PVT LTD, a company as per the filing. Its CIN U70200MH2021PTC360567 and GSTIN 27AAHCN6011E1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NABHRAJ TRILOK HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NABHRAJ TRILOK HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NABHRAJ TRILOK HEIGHTS?
The professionals named in the filing: Architect: Manggal Design; Architect: Anurag R Butole; Engineer: Kailas Laxman Sonawane; Engineer: Core Consultant; Chartered Accountant: R B Sharma and Co; Chartered Accountant: K S B A and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NABHRAJ TRILOK HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback