Registration lapsed No litigation declared Others project

Shreenath Residency Building A-B

By Shreenath Constructions

RG-MH-01846 · RERA P51500010298 · Last updated on MahaRERA portal: 14 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

Shreenath Residency Building A-B is a Others project by Shreenath Constructions in Aurangabad, Maharashtra, registered with MahaRERA as P51500010298 on 24 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameShreenath Residency Building A-B
  • TypeOthers
  • Location
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431003
  • Pincode431003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500010298
  • ReraGenie IDRG-MH-01846

Builder

  • NameShreenath Constructions
  • Entity typePartnership
  • PartnerAvinash Nandkishor Palkar
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed64 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building A-BNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Building A-B: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities16

As on 14 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Compound WallYes100%

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered24
Open Space21

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,371 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Shrikant Narharrao SatarkarAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI9375.31
Proposed, not sanctioned1,371 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchStation Road Aurangabad

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSamil Architects
ArchitectGauravi K Navle
EngineerPrasad Aphale
Chartered AccountantS G Deshmukh & Co
PartnerRole in project
Shreenath Constructions-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500013605Jun 2021 → Jun 2024

Reason as filed by the promoterReasons for delay- i. Initially, this second phase BUILDING A-B of project ‘Shreenath Residency’, was of four storied building having 6 nos of Shops & 12 Nos of Flats in Wing ‘A’ and 12 Nos of Flats in Wing ‘B’ (Total 20 units) and the target date of completion was Dec.,2020. ii. The revised permission was sanctioned in October, 2019 for Seven storied building having 6 nos of Shops & 26 Nos of Flats in Wing ‘A’ and 28 Nos of Flats in Wing ‘B’ and same information was uploaded over the portal. However we did not sought any extension at that time and unfortunately in March, 2020 Covid19 crisis h

EXT51500010020Jun 2021 → Jun 2022

Reason as filed by the promoteri. In 2016, this second phase BUILDING A-B was of four storied building having 6 nos of Shops & 12 Nos of Flats in Wing ‘A’ and 12 Nos of Flats in Wing ‘B’ and the target date of completion was 4 years i.e. up to Dec.,2020. ii. The revised permission was sanctioned in October, 2019 for Seven storied building having 6 nos of Shops & 26 Nos of Flats in Wing ‘A’ and 28 Nos of Flats in Wing ‘B’. With 60 no of units in total, the work load was actually doubled. iii. However we had not taken any extension at that time but unfortunately lock down was declared very soon. iv. Due to COVID-19 pandemic,

EXT51500024518Jun 2021 → Dec 2024

Reason as filed by the promoterDear Sir, We, M/s. Shreenath Constructions, are the Developer of the project “SHREENATH RESIDENCY’, at Gat No.167/1, Harsul, Aurangabad and this is the second phase of the project. We would like to bring to your notice some real facts for your perusal. i. Initially, this second phase BUILDING A-B was of four storied building having 6 nos of Shops & 12 Nos of Flats in Wing ‘A’ and 12 Nos of Flats in Wing ‘B’ and the target date of completion was Dec.,2020. ii. The revised permission was sanctioned in October, 2019 for Seven storied building having 6 nos of Shops & 26 Nos of Flats in Wing ‘A’ an

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 May 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf14 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory Sept 2024.pdf14 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A No 1 June 2023.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A QA No 2 Sept 2023.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A QA No 3 Dec 2023.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A QA No 4 Mar 2024.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A QA No 1 June 2024.pdf9 Aug 2024
CERSAI detailsFile: CERSAI Declaration.pdf9 Aug 2024
Disclosure of sold/ booked inventoryFile: June 2024 Disclosure of Sold or Booked Inventory.pdf9 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A_- Navle.pdf9 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_A_-Palkar.pdf9 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf9 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 Mar 2024.pdf7 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 July 2024.pdf7 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 Mar 2024.pdf7 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 July 2024.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory 2024.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory 2024.pdf7 Aug 2024
Certificates of CA (Form 3)File: Form 3 C A Cert 2023 24.pdf29 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form -5 2023-24.pdf29 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form -5 2023-24.pdf29 Jun 2024
Certificates of CA (Form 3)File: Form 3 2024.pdf17 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2023.pdf17 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of SOLD-BOOKED INVENTORY 2022.pdf26 Dec 2022
Certificates of CA (Form 3)File: FORM 3 2021-22.pdf25 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5 2021-22 CA CERTIFICATE.pdf25 Dec 2022
Building plan approvalFile: Sanctioned Plan 2019-20.pdf5 Aug 2021
Building plan approvalFile: Sanctioned Plan 2019-20.pdf5 Aug 2021
Building Plan Approval (IOD)File: Sanctioned Plan 2019-20.pdf5 Aug 2021
Building Plan Approval (IOD)File: Sanctioned Plan 2019-20.pdf5 Aug 2021
Declaration about Commencement CertificateFile: Declaration of Commencement.pdf5 Aug 2021
Declaration about Commencement CertificateFile: Declaration of Commencement.pdf5 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 Engrs Cert 2019-20.pdf5 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2ACertno1.pdf8 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2ACertno2.pdf8 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2ACertno3.pdf8 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2ACertno4.pdf8 Jul 2021
Certificates of CA (Form 3)File: Form3CACert.pdf8 Jul 2021
Details of Restarting of Construction work post lockdownFile: Application.pdf8 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert 2019-20.pdf3 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert 2020-21.pdf3 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engrs Cert 2019-20.pdf3 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engrs Cert 2020-21.pdf3 Jul 2021
Disclosure of sold/ booked inventoryFile: DIsclosure of Sold- Unsold Inventory 31032021-1.pdf3 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20 C A Cert.pdf3 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21 CA Cert.pdf3 Jul 2021
Building plan approvalFile: Rev Sanctioned Plan sheet1.pdf20 May 2020
PAN CardFile: Shreenath PAN.pdf20 May 2020
Building Plan Approval (IOD)File: Rev Sanctioned Plan sheet1.pdf20 May 2020
Commencement Certificates / NA Order for plotted developmentFile: New Commencement Certi 2016.pdf20 May 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certi 2019.pdf20 May 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA cert AB 2018 19 Form5.pdf20 May 2020
Certificates of CA (Form 5)File: RERA Form5 July 2019.pdf12 Jul 2019
Layout approvalFile: plot layout.pdf31 Jul 2017
Building plan approvalFile: Epson324.pdf31 Jul 2017
Copy of the legal title reportFile: search report (1).pdf31 Jul 2017
Details of encumbrancesFile: Encmbrnc.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: plot layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: Epson324.pdf31 Jul 2017
Declaration in FORM BFile: Form B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate A-B.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate A-B.pdf31 Jul 2017
Certificates of CA (Form 3)File: CA certificate A-B.pdf31 Jul 2017
Proforma of Allotment letterFile: AGREEMENT TO SALE A-B.pdf31 Jul 2017

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 42 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Shreenath Residency Building A-B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Aurangabad (M Corp.)1,400+ in Aurangabad

Builder: Shreenath Constructions

Shreenath Constructions has 4 registrations on MahaRERA, including Building C - D and Shreenath Residency Building A-B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Shreenath Residency Building A-B shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shreenath Residency Building A-B is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shreenath Residency Building A-B?

The registered promoter entity is Shreenath Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shreenath Residency Building A-B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shreenath Residency Building A-B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shreenath Residency Building A-B?

The professionals named in the filing: Architect: Samil Architects; Architect: Gauravi K Navle; Engineer: Prasad Aphale; Chartered Accountant: S G Deshmukh & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shreenath Residency Building A-B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shreenath Residency Building A-B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shreenath Residency Building A-B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.