Completed No litigation declared Others project

Gursahani Twin Tower

By Shree Hinglajmata Constructions

RG-MH-13233 · RERA P51500048239 · Last updated on MahaRERA portal: 4 Mar 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
33 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Gursahani Twin Tower is a Others project by Shree Hinglajmata Constructions in Aurangabad, Maharashtra, registered with MahaRERA as P51500048239 on 19 Dec 2022. The registration is recorded completed; possession was promised by 5 Oct 2026. The completion date has moved by 24 months from the original filing. 16 of the 49 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameGursahani Twin Tower
  • TypeOthers
  • Location
    • Plot No. 138
    • Survey No. 15
    • N4 Cidco
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431003
  • Pincode431003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500048239
  • ReraGenie IDRG-MH-13233

Builder

  • NameShree Hinglajmata Constructions
  • Entity typePartnership
  • PartnerHiroo Chimandas Gursahani

Key dates

this monthRegisteredDec 2022First promiseOct 2024Revised toOct 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Dec 2022
  • Promised completion5 Oct 2026
  • Revised completionRevised to 5 Oct 2026 (originally 6 Oct 2024)
  • Buildings1 building record
  • Documents filed73 files

Current status

33%16 of 49 units booked
96.9%Work done, per cost certificate

Figures as on 4 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Gursahani Twin TowersNA98193049

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Gursahani Twin Towers: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed139

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots139
Closed/Covered139

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,257 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Sep 2024
LandownerVillageDistrict
Hiroo Chimandas GursahaniAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityCHHATRAPATI SAMBHAJINAGAR MUNICIPAL CORPORATION
Permissible FSI3434.92
Proposed, not sanctioned3,435 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIT Hospital N4 Cidco Aurangabad
Estimated costRs 8.00 cr
Cost incurredRs 7.75 cr
Work done96.88%
BuildingWingEstimatedIncurred
Gursahani Twin TowersNARs 8.00 crRs 7.75 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJadhav RS
ArchitectRajaram Sahebrao Jadhav
EngineerNamdeo Govind Karkhane
EngineerDevendra A Deshpande
Chartered AccountantShrikant Thorat
Chartered AccountantAshok Patil & Associates
Chartered AccountantSaurabh Agrawal
PartnerRole in project
Shree Hinglajmata Constructions-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500024526Oct 2024 → Oct 2026

Reason as filed by the promoterWe have experienced delays in completion due to difference between the demand we anticipated during registration and the actual market response. The initial project timeline was based on our assessment of demand at the time of registration. However, as we progressed, the actual response differed from our expectations. This has necessitated adjustments in our construction schedule, resulting in an completion timeline. We understand the importance of adhering to RERA guidelines and are committed to completing the project while maintaining quality standards. Therefore, we kindly request an extens

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Gmail - 110 03 SANTION OC POROPSAL 29122025.pdf4 Mar 2026
Occupational CertificateFile: OC.pdf12 Feb 2026
Occupational CertificateFile: OC Plan.pdf12 Feb 2026
Occupational CertificateFile: Form 4.pdf12 Feb 2026
Occupational CertificateFile: Rejection Note.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1_merged.pdf2 Feb 2026
Withdrawal Update Form 2File: Form 2_merged.pdf2 Feb 2026
Withdrawal Update Form 3File: Form 3_merged.pdf2 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf23 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf23 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf23 Dec 2025
Form 5 (FY 2024-2025)File: Hinglajmata Form 5 24-25.pdf28 Oct 2025
Form 1File: Form 1.pdf15 Oct 2025
Form 2File: Form 2.pdf15 Oct 2025
Form 3File: Form 3.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: Form 3.pdf15 Oct 2025
Form 1File: Form 1.pdf19 Jul 2025
Form 2File: Form 2.pdf19 Jul 2025
Form 3File: Signed Form 3.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Declaration.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf7 Oct 2024
Form 5 (FY 2022-2023)File: Form 5 22 -23 .pdf23 Sep 2024
Form 5 (FY 2023-2024)File: Form 5 23-24 .pdf23 Sep 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 .pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23 SIGN.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11.pdf22 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 22.pdf22 Jul 2023
Disclosure of sold/ booked inventoryFile: 33.pdf22 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf22 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate.pdf17 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf17 Mar 2023
Proforma of Agreement for saleFile: RERA Agreement copy .pdf12 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Hinglajmata No Deviation.pdf12 Dec 2022
Proforma of Allotment letterFile: Allotment Letter.pdf19 Nov 2022
Deviation Report with respect to Allotment letterFile: Deviation AL.pdf19 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Encumberance Revised Shree.pdf14 Oct 2022
Declaration in FORM BFile: Form B.pdf6 Oct 2022
Layout approvalFile: Merged Building Plan compressed _compressed.pdf4 Oct 2022
Building plan approvalFile: Merged Building Plan compressed _compressed.pdf4 Oct 2022
PAN CardFile: Pan Card.pdf4 Oct 2022
Copy of the legal title reportFile: Legal Title Report_compressed (2).pdf4 Oct 2022
Details of encumbrances concerned to FinanceFile: E Finance.pdf4 Oct 2022
Details of encumbrances concerned to LegalFile: E Legal.pdf4 Oct 2022
Copy of Layout Approval (in case of layout)File: Merged Building Plan compressed _compressed.pdf4 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Merged Building Plan compressed _compressed.pdf4 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf4 Oct 2022
Declaration about Commencement CertificateFile: Decleration About Commencement Format D.pdf4 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf4 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate_compressed.pdf4 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf4 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_organized_compressed.pdf4 Oct 2022

How this compares with Aurangabad

33%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 24 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Gursahani Twin Tower on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near N4 Cidco1,400+ in Aurangabad

2 kmGursahani Twin TowerCompleted 42Lapsed / revoked 31Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 106 registered projects within 2 km.

Builder: Shree Hinglajmata Constructions

Shree Hinglajmata Constructions has 1 registration on MahaRERA, including Gursahani Twin Tower. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Gursahani Twin Tower is delayed beyond 5 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gursahani Twin Tower?

The registered promoter entity is Shree Hinglajmata Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gursahani Twin Tower?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Gursahani Twin Tower?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gursahani Twin Tower?

The professionals named in the filing: Architect: Jadhav RS; Architect: Rajaram Sahebrao Jadhav; Engineer: Namdeo Govind Karkhane; Engineer: Devendra A Deshpande; Chartered Accountant: Shrikant Thorat; Chartered Accountant: Ashok Patil & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gursahani Twin Tower?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gursahani Twin Tower. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gursahani Twin Tower to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.