Home / Browse projects / Pune, Maharashtra / Ivy Estate-Nia

Registration lapsed No litigation declared Others project

Ivy Estate-Nia

By KOLTE-PATIL DEVELOPERS LIMITED

RG-MH-38820 · RERA P52100017955 · Last updated on MahaRERA portal: 5 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 13 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
162 of 198Construction stages doneacross 18 buildings; furthest along: External plumbing and external plaster, 90%
2Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

Ivy Estate-Nia is a Others project by KOLTE-PATIL DEVELOPERS LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100017955 on 28 Sep 2018. Possession was promised by 29 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameIvy Estate-Nia
  • TypeOthers
  • Location
    • WAGHOLI
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • RERA no.P52100017955
  • ReraGenie IDRG-MH-38820

Builder

  • NameKOLTE-PATIL DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200PN1991PLC129428
  • GSTIN27AAACK7310G1ZT
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Joint Managing DirectorYashvardhan Rajesh Patil
  • Executive DirectorMilind Digambar Kolte
  • Other registrations63 more →
  • Completed14 of 64
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

34 months past promisethis monthRegisteredSep 2018First promiseDec 2022Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Sep 2018
  • Promised completion29 Dec 2023
  • Revised completionRevised to 29 Dec 2023 (originally 30 Dec 2022)
  • Buildings18 building records
  • Documents filed64 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
G1 Ground Floor to First FloorNA20000
G2 Ground Floor to Six FloorNA70000
G3NA120000
G4NA120000
G5NA120000
G6NA120000
G7NA120000
G8NA120000
H1 Ground Floor to First FloorNA20000
H2 Ground Floor to First FloorNA20000
H3 Ground Floor to First FloorNA20000
Parking Ground floorNA10000
G1 2nd Floor to 11 FloorNA100000
G2 07th Floor to 11th FloorNA50000
H1 02nd Floor to 11th FloorNA100000
H2 02nd Floor to 11th FloorNA100000
H3 2nd Floor to 11th FloorNA100000
Parking BuildingNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building18

As on 5 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

162 of 198 construction stages are filed complete across 18 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

G1 Ground Floor to First Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G2 Ground Floor to Six Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H1 Ground Floor to First Floor91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H2 Ground Floor to First Floor91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H3 Ground Floor to First Floor91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Parking Ground floor62%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
G1 2nd Floor to 11 Floor73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G2 07th Floor to 11th Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H1 02nd Floor to 11th Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H2 02nd Floor to 11th Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H3 2nd Floor to 11th Floor82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Parking Building80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes10%
Open ParkingNoNot applicable

Parking filed1089

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,089
Closed/Covered553
Open Space536
BuildingClosed/CoveredOpen SpaceTotal
G1 Ground Floor to First Floor444387
G2 Ground Floor to Six Floor444387
G3444387
G4444387
G5444387
G6563187
G7563187
G8563187
H1 Ground Floor to First Floor5576131
H2 Ground Floor to First Floor5576131
H3 Ground Floor to First Floor5576131

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,971 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI62943.8
Proposed, not sanctioned38,427 sq m
Buildings approved18
Buildings sanctioned18

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchA-Wing, Shangrila Gardens, Bund Garden Road Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSammer Valimbe
EngineerSpace Designers Syndicate
Chartered AccountantVIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS
PartnerRole in project
KOLTE-PATIL DEVELOPERS LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013286Dec 2022 → Dec 2023

Reason as filed by the promoteras per attached application

Litigation declared2

CaseCourtStatus
RCS 89/2015/2015CJJDPending for Argument on Application for withdrawal of Suit
Spl C S 1093/2020/2020Civil CourtFiling of written statement

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000106771Balasaheb Yashwant KuteKolte Patil14/03/2022
CC005000000228359-Kolte Patil Developers Limited21/02/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Sep 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Sep 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Feb 2025

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Ivy Nia.pdf5 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ivy Nia.pdf5 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 - Ivy Nia.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: IVY ESTATE NIA.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: IVY ESTATE NIA.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Ivy Estate Nia .pdf29 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: IVY NIA.pdf20 Jul 2023
Certificates of CA (Form 3)File: Ivy NIA_compressed.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ivy Nia.pdf19 Jul 2023
Proforma of Allotment letterFile: Post OC-FINAL-Ivy Estate NIA.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: IVY NIA.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Ivy Nia Final Inventory Declaration.pdf20 Apr 2023
CERSAI detailsFile: Cersai Details KPDL.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ivy nia.pdf15 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Signed certificate IVY Nia March 19.pdf28 Mar 2023
Proforma of Agreement for saleFile: AFS Agreement.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Ivy Estate Nia.pdf20 Jan 2023
Certificates of CA (Form 3)File: From3 Ivy Nia final.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Ivy Nia.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Ivy nia.pdf18 Jan 2023
Declaration about Commencement CertificateFile: Declaration Commencement.pdf16 Jan 2023
CERSAI detailsFile: Final File Cersai.pdf16 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclsoure in other entities.pdf13 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Ivy Estate Nia.pdf10 Jan 2023
Proforma of Agreement for saleFile: AFS.pdf21 Nov 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Covering Letter with Index II.pdf21 Nov 2022
Disclosure of sold/ booked inventoryFile: Ivy Nia Inventory.pdf20 Oct 2022
Certificates of CA (Form 3)File: IVY NIA_compressed.pdf20 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ivy Nia architect cert___.pdf19 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ivy Nia.pdf18 Oct 2022
CERSAI detailsFile: Cersai Report.pdf18 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 11080 06 10 Ivy Nia Form 5.pdf30 Sep 2022
Proforma of Allotment letterFile: AFS Ivy Nia.pdf18 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 IVY Nia June 2022.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: Inventory Declaration Ivy Nia.pdf7 Jul 2022
Certificates of CA (Form 3)File: CA - Ivy Nia_compressed.pdf7 Jul 2022
Details of encumbrancesFile: Ivy Estate and Nia.pdf4 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Ivy Estate Nia_compressed.pdf4 Jul 2022
CERSAI detailsFile: Final Cersai.pdf4 Jul 2022
Certificates of CA (Form 3)File: CA_Ivy nia-compressed.pdf7 Apr 2022
CERSAI detailsFile: KPDL Cersai-compressed.pdf6 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Ivy Estate Nia.pdf20 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nia.pdf18 Jan 2022
Disclosure of sold/ booked inventoryFile: Ivy Nia G1-compressed.pdf14 Jan 2022
CERSAI detailsFile: KPDL Merge File-compressed.pdf7 Jan 2022
Certificates of CA (Form 3)File: Ivy Nia Estate-compressed.pdf7 Jan 2022
Proforma of Allotment letterFile: Final -Ivy Estate Project 3- NIA- AFS - 01-11-2021.pdf8 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Certificate- IVY Nia.pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Certificate- IVY Nia.pdf30 Sep 2020
Proforma of Allotment letterFile: Final -Ivy Estate Project 3- NIA- AFS - 17-12-2019.pdf7 Jan 2020
Annual Audit Report of Statutory CA (Form 5)File: Signed certificate IVY Nia March 19.pdf29 Sep 2019
Proforma of Allotment letterFile: AFS Ivy Nia.pdf16 Nov 2018
Details of encumbrancesFile: encumbrances Ivy Estate Nia.pdf24 Oct 2018
Proforma of Allotment letterFile: Revised Allotment Letter and Application Letter.pdf11 Oct 2018
Details of encumbrancesFile: Details of Encumbrances Ivy Estate Nia.pdf24 Sep 2018
Declaration in FORM BFile: Affidavit Cum Declaration Ivy Estate Nia.pdf24 Sep 2018
Proforma of Allotment letterFile: Self Declaration Agreement Ivy Estate Nia.pdf24 Sep 2018
Building plan approvalFile: Layout Approval.pdf21 Sep 2018
Layout approvalFile: Layout Approval.pdf21 Sep 2018
Copy of the legal title reportFile: Search and Title Certificate Ivy Estate Nia.pdf21 Sep 2018
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf21 Sep 2018
Building Plan Approval (IOD)File: Layout Approval.pdf21 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Ivy Estate Nia.pdf21 Sep 2018
Certificates of CA (Form 3)File: CA Certificate RERA - IVY ESTATE NIA.pdf21 Sep 2018

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

13 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
EVARAP51800026949Borivali, Mumbai Suburban-Nov 2020CompletedOct 2024Oct 2024
24K Stargaze - J BuildingP52100027791Bavdhan, Pune-Jan 2021CompletedJun 2024Jun 2024
Western AvenueP52100000917Wakad, Pune-Jul 2017CompletedDec 2023Registered original: Dec 2022Jan 2023
24K StargazeP52100018473Bavdhan, Pune-Nov 2018CompletedMar 2023Mar 2023
Redevelopment of Jai Vijay CHSL - Phase IP51800004446Vile-Parle (East), Mumbai Suburban-Aug 2017CompletedSep 2022Registered original: Sep 2019Sep 2022
24K ATRIAP52100000428Vishal Nagar, Pimple Nilakh, Pune-Jul 2017CompletedDec 2021Dec 2021
STARGAZEP52100009722Bavadhan BK, Pune-Aug 2017CompletedDec 2018Dec 2018
Ivy Estate Umang PremierP52100000655WAGHOLI, Pune-Jul 2017CompletedSep 2018Sep 2018
GLITTERATIP52100006257Pimpri Chinchawad (M Corp.), Pune-Aug 2017CompletedJun 2018Jun 2018
GLITTERATI IIP52100000319Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedApr 2018Registered original: Dec 2017Apr 2018
Redevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase IP51800008272Andheri, Mumbai Suburban-Aug 2017CompletedMar 2018Registered original: Dec 2017Mar 2018
GlitteratiPimple Nilakh Pune - 411014187-CompletedApr 2016Apr 2016
City BayDhole-Patil road Pune-41100127-CompletedApr 2014Apr 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ivy Estate-Nia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGHOLI13,700+ in Pune

Builder: KOLTE-PATIL DEVELOPERS LIMITED

KOLTE-PATIL DEVELOPERS LIMITED has 64 registrations on MahaRERA, including 24K OPULA and 24K ATRIA. Its filings disclose 14 earlier MahaRERA projects: declares 13 of 14 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Ivy Estate-Nia shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ivy Estate-Nia is delayed beyond 29 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ivy Estate-Nia?

The registered promoter entity is KOLTE-PATIL DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200PN1991PLC129428 and GSTIN 27AAACK7310G1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ivy Estate-Nia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ivy Estate-Nia?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ivy Estate-Nia?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ivy Estate-Nia?

The professionals named in the filing: Architect: Sammer Valimbe; Engineer: Space Designers Syndicate; Chartered Accountant: VIDHI S SHAH & ASSOCIATES CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ivy Estate-Nia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ivy Estate-Nia. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ivy Estate-Nia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.