Godrej Greens
RG-MH-09781 · RERA P52100000985 · Last updated on MahaRERA portal: 14 Jul 2026
Source: official MahaRERA filing
Red flags
- Litigation declared, 19 cases
- 25 complaints at MahaRERA
- Completion date moved by 48 months
- 3 extensions taken
Clear
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Godrej Greens is a Residential / Group Housing project by DREAM WORLD LANDMARKS LLP in Pune, Maharashtra, registered with MahaRERA as P52100000985 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 Sep 2026. The completion date has moved by 48 months from the original filing. 835 of the 952 units on this registration are recorded sold or booked, and 66 of 66 construction stages are filed complete. 25 complaints are on record with the regulator.
At a glance
Project
- NameGodrej Greens
- TypeResidential / Group Housing
- Location
- Undri Handewadi Road
- Undri
- Haveli
- Pune
- 412207
- Pincode412207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100000985
- ReraGenie IDRG-MH-09781
Builder
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on25 Jul 2017
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2022)
- Buildings6 building records
- Documents filed160 files
Current status
Figures as on 14 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B1 | NA | 20 | 17 | 204 | 0 | 204 |
| B2 | NA | 20 | 17 | 136 | 0 | 136 |
| B3 | NA | 20 | 17 | 136 | 0 | 136 |
| B4 | NA | 19 | 17 | 136 | 0 | 136 |
| B5 | NA | 19 | 17 | 136 | 0 | 136 |
| B6 | NA | 19 | 17 | 204 | 0 | 204 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
66 of 66 construction stages are filed complete across 6 buildings.
B1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B6100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2285
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| B1 | 462 | 54 | 516 |
| B2 | 352 | 21 | 373 |
| B3 | 399 | 29 | 428 |
| B4 | 213 | 49 | 262 |
| B5 | 228 | 50 | 278 |
| B6 | 391 | 37 | 428 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHITECTURE COLLECTIVE |
| Architect | Gaurav Sanan |
| Engineer | Gem Engserv Pvt Ltd |
| Engineer | Anil Tukaram Powar |
| Chartered Accountant | M D Deshpande & Co. |
| Chartered Accountant | MADHAV DAMODAR DESHPANDE |
| Chartered Accountant | OMKAR DESHPANDE |
| Chartered Accountant | BSR & Co. LLP |
| Partner | Role in project |
|---|---|
| DREAM WORLD LANDMARKS LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoteron account of (I) COVID-19 Pandemic; (ii) shortage in supply of construction material, hardware, and equipment; and (iii) labour shortage - the overall completion of Project slowed-down. Thus Seeking extension of Registration.
Reason as filed by the promoterIn terms of application, we hereby seek extension of time for Godrej Greens by 6 months.
Reason as filed by the promoterAs per Justification Letter attached
Litigation declared19
| Case | Court | Status |
|---|---|---|
| SCS 440/2017 | Civil Court Senior Division | PENDING |
| SCS 609/2017 | Civil Court Senior Division | PENDING |
| RCS 1936/2016 | Civil Court Junior Division | PENDING |
| Appeal no 4257/2018 | Deputy Director of Land Records | PENDING |
| RCS 4469/2012 | Civil Court Junior Division | PENDING |
| RCC 26/2017 | Judicial Magistrate First Class | PENDING |
| RCS 887/2017 | Civil Court Jr Division Pune | PENDING |
| MCA 146/2018 | District Court | PENDING |
| RCS 259/2019 | Civil Court Junior Division | PENDING |
| CC005000000167630/2022 | RERA MUMBAI | PENDING |
| CC/17/2019/2019 | Consumer disputes redressal forum Bandra | PENDING |
| CC005000000022458/2019 | RERA MUMBAI | PENDING |
| CC005000000106424/2021 | RERA PUNE | PENDING |
| CCOO5OO0OOO106820/2022 | RERA PUNE | PENDING |
| RBT/CC/21/703/2019 | District Consumer Dispute Redressal Commission Pune | PENDING |
| CC/22/174/2022 | District Consumer Dispute Redressal Commission Pune | PENDING |
| CC/22/425/2022 | District Consumer Dispute Redressal Commission Pune | PENDING |
| CC/22/229/2022 | Consumer Dispute Redressal Commission Maharashtra State | PENDING |
| 1936/2016/2016 | Pune District & Session Court | Ongoing |
Complaints filed with MahaRERA25
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000022458 | KEDAR BHANUDAS SHAH | DREAMWORLD LANDMARKS LLP | 18/01/2019 |
| CC005000000043608 | Gaurav Nipen Dutta | Dream World Landmark LLP | 13/11/2019 |
| CC005000000064349 | CHETAN KAUSHAL | DREAM WORLD LANDMARKS LLP | 02/07/2020 |
| CC005000000167630 | Amandeep Singh Bachher | Dream World Landmarks llp | 26/09/2022 |
| CC005000000106424 | MAYURESH SANJAY PATIL | DREAM WORLD LANDMARKS LLP | 28/12/2021 |
| CC005000000106820 | Sofia Bernard Swamy | Godrej Properties Limited | 24/03/2022 |
| CC005000000177713 | Satyajit Anirudha Patil | Dream World Landmarks LPP | 04/03/2023 |
| CC005000000177750 | NAZIR BASHIR SHAIKH | GODREJ PROPERTIES | 03/11/2022 |
| CC005000000228441 | Anuradha Ashutosh Kichambare | Dream World landmarks LLP | 04/03/2023 |
| CC005000000258925 | Shzaine Miranda | Dream world Landmarks LIp | 28/05/2023 |
| CC005000000310578 | Shzaine Miranda | Godrej Properties Limited | 08/03/2024 |
| CC005000000258924 | Kayzia Miranda | Dream world landmarks LLP | 28/05/2023 |
| CC005000000258928 | Mandar Moreshwar Pawar | Dream World Landmarks LLP | 29/05/2023 |
| CC005000000259227 | Snehalata Bhogte | Dream World Landmarks LLP | 30/07/2023 |
| CC005000000279838 | Shelza Pratik Chirania | Dreamworld Landmarks LLP | 12/12/2023 |
| CC12602819 | DREAM WORLD LANDMARKS LLP | Gyanendra Kumar Trivedi | 14/05/2026 |
| CC12602820 | DREAM WORLD LANDMARKS LLP | ABDUL FAIZ SHEIKH | 14/05/2026 |
| CC12602822 | DREAM WORLD LANDMARKS LLP | AMITKUMAR JAGDISH ASWANI | 14/05/2026 |
| CC12602823 | DREAM WORLD LANDMARKS LLP | ANILKUMAR FAKIRCHAND AGARWAL | 14/05/2026 |
| CC12602824 | DREAM WORLD LANDMARKS LLP | DEEPAK KUMAR BIND | 14/05/2026 |
| CC12602825 | DREAM WORLD LANDMARKS LLP | FAHAD AASAM MUKADAM | 14/05/2026 |
| CC12602826 | DREAM WORLD LANDMARKS LLP | Mansoor Ali Abshir Ahmed Khot | 14/05/2026 |
| CC12602827 | DREAM WORLD LANDMARKS LLP | RIYAZ AHMED IBRAHIM GITAY | 14/05/2026 |
| CC12602828 | DREAM WORLD LANDMARKS LLP | SANAPALA BALAKRISHNA | 14/05/2026 |
| CC12602829 | DREAM WORLD LANDMARKS LLP | SOMESHWAR BASANT LAL VISHWAKARMA | 14/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jun 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Feb 2024
Documents filed160
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: OC dated 02-08-2023.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Layout Plan.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Sanction Plan-1-6.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Sanction Plan-7-13.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Sanction Plan-14-26.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Sanction Plan-27-39.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Sanction Plan-40-52.pdf | 14 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A.pdf | 13 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A.pdf | 13 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 13 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 4 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 4 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 4 Jul 2026 |
| Building plan approvalFile: Sanction Plan-1-6.pdf | 30 Jun 2026 |
| Building plan approvalFile: Sanction Plan-7-13.pdf | 30 Jun 2026 |
| Building plan approvalFile: Sanction Plan-14-26.pdf | 30 Jun 2026 |
| Building plan approvalFile: Sanction Plan-27-39.pdf | 30 Jun 2026 |
| Building plan approvalFile: Sanction Plan-40-52.pdf | 30 Jun 2026 |
| Layout approvalFile: Layout Plan.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 19 May 2026 |
| Form 1File: Form-1 _ ARCHITECTS CERTIFICATE (JUNE-23).pdf | 24 Feb 2026 |
| Form 2File: Form-2 _ ENGINEERS CERTIFICATE (JUNE-23).pdf | 24 Feb 2026 |
| Form 3File: Form-3 _ CA Certificate (June-2023)_compressed.pdf | 24 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Units (Jun-23).pdf | 24 Feb 2026 |
| Form 1File: Form 1 (Architects certificate Sep23).pdf | 24 Feb 2026 |
| Form 2File: Form 2 (Engineers certificate Sep23).pdf | 24 Feb 2026 |
| Form 3File: Form 3 (CA certificate Sep23).pdf | 24 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory - Godrej Greens (as on 30-Sep-23).pdf | 24 Feb 2026 |
| Architect’s Certificate on Completion of Project (Form 4)File: Godrej Greens _ Form4 (31Dec24).pdf | 6 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej Greens _ Q3 _ Form-1.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: Godrej Greens _ Q3 _ Form-3.pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej Greens _ Q3 _ Form-2.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Godrej Greens _ Q3 _ sold unsold units.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect's Certificate Sep-24 _ Signed.pdf | 11 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer's Certificate Sep-24 _ Signed.pdf | 11 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3_ CA Certificate (DWLLP) Sept 2024 _ Signed.pdf | 11 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold units Sep-24 _ Signed.pdf | 11 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect's Certificate Sep-24 _ Signed.pdf | 11 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3_ CA Certificate (DWLLP) Sept 2024 _ Signed.pdf | 11 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer's Certificate Sep-24 _ Signed.pdf | 11 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold units Sep-24 _ Signed.pdf | 11 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DWLLP Form-5.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DWLLP Form-5.pdf | 9 Oct 2024 |
| Form 5 (FY 2023-2024)File: DWLLP Form-5.pdf | 27 Sep 2024 |
| Certificates of CA (Form 5)File: CA Certificate_Godrej Greens (Jun-24).pdf | 17 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate (Jun-24).pdf | 16 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate (Jun-24).pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Greens _ Sold unsold units (Jun-24).pdf | 16 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greens _ Engineers Certificate (Mar-24).pdf | 18 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greens _ Architect's Certificate (Mar-24).pdf | 17 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Greens _ Quality Assurance Certificate (Mar-24).pdf | 17 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Greens _ Sold Unsold Units (March-24)_compressed_compressed_11zon.pdf | 17 Apr 2024 |
| Certificates of CA (Form 3)File: Greens _ CA Certificate (Mar-24)_compressed.pdf | 16 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Godrej Greens _ OC copy.pdf | 28 Feb 2024 |
| Certificates of CA (Form 3)File: Undri _ CA certificate (Dec-23).pdf | 12 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate (Dec-23).pdf | 11 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate (Dec-23).pdf | 11 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold units (Dec-23).pdf | 11 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Engineers certificate Sep23).pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed (1).pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3-final compressed 1_11zon.pdf | 20 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Dream World FY22 - Godrej Greens signed.pdf | 21 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Dreamworld - Greens SIGNED.pdf | 21 Sep 2023 |
| Certificates of CA (Form 3)File: Greens_CA final_11zon.pdf | 19 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: greens_architect certificate.pdf | 10 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greens_engineer certificate.pdf | 10 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: greens_disclosure of inventory_compressed_11zon.pdf | 10 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf | 20 Apr 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Godrej PranaP52100001372 | UNDRI, Pune | 667 | Jul 2017 | Ongoing | Sep 2020 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 160 filed documents as one ZIP, foldered, with a manifest
Keep Godrej Greens on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Undri13,700+ in Pune
Filed coordinates, straight-line distance. 140 registered projects within 2 km.
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
KOHINOOR RIVERDALE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: DREAM WORLD LANDMARKS LLP
DREAM WORLD LANDMARKS LLP has 3 registrations on MahaRERA, including Godrej Greens and Godrej Prana. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Godrej Greens is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Godrej Greens?
The registered promoter entity is DREAM WORLD LANDMARKS LLP, an others as per the filing. Its GSTIN 27AAIFD5398J1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Godrej Greens?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Godrej Greens?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Godrej Greens?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Godrej Greens?
The professionals named in the filing: Architect: ARCHITECTURE COLLECTIVE; Architect: Gaurav Sanan; Engineer: Gem Engserv Pvt Ltd; Engineer: Anil Tukaram Powar; Chartered Accountant: M D Deshpande & Co.; Chartered Accountant: MADHAV DAMODAR DESHPANDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Godrej Greens?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback