Home / Browse projects / Pune, Maharashtra / Godrej Greens

Completed Litigation declared Residential / Group Housing project

Godrej Greens

By DREAM WORLD LANDMARKS LLP

RG-MH-09781 · RERA P52100000985 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 19 cases
  • 25 complaints at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promisedregistration recorded completed
66 of 66Construction stages doneacross 6 buildings; every applicable stage filed complete
117 of 952Units unsoldnot recorded sold or booked
25Complaints at MahaRERAon this registration
Jump to the 160 documents Report an error

Godrej Greens is a Residential / Group Housing project by DREAM WORLD LANDMARKS LLP in Pune, Maharashtra, registered with MahaRERA as P52100000985 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 Sep 2026. The completion date has moved by 48 months from the original filing. 835 of the 952 units on this registration are recorded sold or booked, and 66 of 66 construction stages are filed complete. 25 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Greens
  • TypeResidential / Group Housing
  • Location
    • Undri Handewadi Road
    • Undri
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000985
  • ReraGenie IDRG-MH-09781

Builder

  • NameDREAM WORLD LANDMARKS LLP
  • Entity typeOthers
  • GSTIN27AAIFD5398J1ZV
  • PartnersPARIJAT LAND DEVELOPERS LLP NA, SANSKRITI LAND DEVELOPERS LLP NA, DEVI HILL PARADISE LLP NA, LOTUS LAND DEVELOPERS LLP NA, GODREJ PROPERTIES LIMITED NA
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017First promiseSep 2022Revised toSep 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Jul 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2022)
  • Buildings6 building records
  • Documents filed160 files

Current status

88%835 of 952 units booked

Figures as on 14 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1NA20172040204
B2NA20171360136
B3NA20171360136
B4NA19171360136
B5NA19171360136
B6NA19172040204

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

66 of 66 construction stages are filed complete across 6 buildings.

B1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B5100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B6100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed2285

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2,285
Closed/Covered2,045
Open Space240
BuildingClosed/CoveredOpen SpaceTotal
B146254516
B235221373
B339929428
B421349262
B522850278
B639137428

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area42,691 sq m
Land owned byThe promoter
Named landownersNone
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityPune Municipal Corporation (PMC)
Permissible FSI80110.5
Proposed, not sanctioned80,110 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANEKJI WADIA BLDG GROUND FLOOR NANIK MOTWANI MARG FORT MUMBAI - 400001

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECTURE COLLECTIVE
ArchitectGaurav Sanan
EngineerGem Engserv Pvt Ltd
EngineerAnil Tukaram Powar
Chartered AccountantM D Deshpande & Co.
Chartered AccountantMADHAV DAMODAR DESHPANDE
Chartered AccountantOMKAR DESHPANDE
Chartered AccountantBSR & Co. LLP
PartnerRole in project
DREAM WORLD LANDMARKS LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012601Sep 2022 → Mar 2023

Reason as filed by the promoteron account of (I) COVID-19 Pandemic; (ii) shortage in supply of construction material, hardware, and equipment; and (iii) labour shortage - the overall completion of Project slowed-down. Thus Seeking extension of Registration.

EXT52100015109Sep 2022 → Sep 2023

Reason as filed by the promoterIn terms of application, we hereby seek extension of time for Godrej Greens by 6 months.

EA05032620098Sep 2022 → Sep 2026

Reason as filed by the promoterAs per Justification Letter attached

Litigation declared19

CaseCourtStatus
SCS 440/2017Civil Court Senior DivisionPENDING
SCS 609/2017Civil Court Senior DivisionPENDING
RCS 1936/2016Civil Court Junior DivisionPENDING
Appeal no 4257/2018Deputy Director of Land RecordsPENDING
RCS 4469/2012Civil Court Junior DivisionPENDING
RCC 26/2017Judicial Magistrate First ClassPENDING
RCS 887/2017Civil Court Jr Division PunePENDING
MCA 146/2018District CourtPENDING
RCS 259/2019Civil Court Junior DivisionPENDING
CC005000000167630/2022RERA MUMBAIPENDING
CC/17/2019/2019Consumer disputes redressal forum BandraPENDING
CC005000000022458/2019RERA MUMBAIPENDING
CC005000000106424/2021RERA PUNEPENDING
CCOO5OO0OOO106820/2022RERA PUNEPENDING
RBT/CC/21/703/2019District Consumer Dispute Redressal Commission PunePENDING
CC/22/174/2022District Consumer Dispute Redressal Commission PunePENDING
CC/22/425/2022District Consumer Dispute Redressal Commission PunePENDING
CC/22/229/2022Consumer Dispute Redressal Commission Maharashtra StatePENDING
1936/2016/2016Pune District & Session CourtOngoing

Complaints filed with MahaRERA25

Case no.ComplainantRespondentFiled
CC005000000022458KEDAR BHANUDAS SHAHDREAMWORLD LANDMARKS LLP18/01/2019
CC005000000043608Gaurav Nipen DuttaDream World Landmark LLP13/11/2019
CC005000000064349CHETAN KAUSHALDREAM WORLD LANDMARKS LLP02/07/2020
CC005000000167630Amandeep Singh BachherDream World Landmarks llp26/09/2022
CC005000000106424MAYURESH SANJAY PATILDREAM WORLD LANDMARKS LLP28/12/2021
CC005000000106820Sofia Bernard SwamyGodrej Properties Limited24/03/2022
CC005000000177713Satyajit Anirudha PatilDream World Landmarks LPP04/03/2023
CC005000000177750NAZIR BASHIR SHAIKHGODREJ PROPERTIES03/11/2022
CC005000000228441Anuradha Ashutosh KichambareDream World landmarks LLP04/03/2023
CC005000000258925Shzaine MirandaDream world Landmarks LIp28/05/2023
CC005000000310578Shzaine MirandaGodrej Properties Limited08/03/2024
CC005000000258924Kayzia MirandaDream world landmarks LLP28/05/2023
CC005000000258928Mandar Moreshwar PawarDream World Landmarks LLP29/05/2023
CC005000000259227Snehalata BhogteDream World Landmarks LLP30/07/2023
CC005000000279838Shelza Pratik ChiraniaDreamworld Landmarks LLP12/12/2023
CC12602819DREAM WORLD LANDMARKS LLPGyanendra Kumar Trivedi14/05/2026
CC12602820DREAM WORLD LANDMARKS LLPABDUL FAIZ SHEIKH14/05/2026
CC12602822DREAM WORLD LANDMARKS LLPAMITKUMAR JAGDISH ASWANI14/05/2026
CC12602823DREAM WORLD LANDMARKS LLPANILKUMAR FAKIRCHAND AGARWAL14/05/2026
CC12602824DREAM WORLD LANDMARKS LLPDEEPAK KUMAR BIND14/05/2026
CC12602825DREAM WORLD LANDMARKS LLPFAHAD AASAM MUKADAM14/05/2026
CC12602826DREAM WORLD LANDMARKS LLPMansoor Ali Abshir Ahmed Khot14/05/2026
CC12602827DREAM WORLD LANDMARKS LLPRIYAZ AHMED IBRAHIM GITAY14/05/2026
CC12602828DREAM WORLD LANDMARKS LLPSANAPALA BALAKRISHNA14/05/2026
CC12602829DREAM WORLD LANDMARKS LLPSOMESHWAR BASANT LAL VISHWAKARMA14/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Feb 2024

Documents filed160

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: OC dated 02-08-2023.pdf14 Jul 2026
Occupational CertificateFile: Layout Plan.pdf14 Jul 2026
Occupational CertificateFile: Sanction Plan-1-6.pdf14 Jul 2026
Occupational CertificateFile: Sanction Plan-7-13.pdf14 Jul 2026
Occupational CertificateFile: Sanction Plan-14-26.pdf14 Jul 2026
Occupational CertificateFile: Sanction Plan-27-39.pdf14 Jul 2026
Occupational CertificateFile: Sanction Plan-40-52.pdf14 Jul 2026
Form 2A (FY 2023-2024)File: Form 2A.pdf13 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf13 Jul 2026
Form 5 (FY 2024-2025)File: Form 5.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf4 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf4 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf4 Jul 2026
Building plan approvalFile: Sanction Plan-1-6.pdf30 Jun 2026
Building plan approvalFile: Sanction Plan-7-13.pdf30 Jun 2026
Building plan approvalFile: Sanction Plan-14-26.pdf30 Jun 2026
Building plan approvalFile: Sanction Plan-27-39.pdf30 Jun 2026
Building plan approvalFile: Sanction Plan-40-52.pdf30 Jun 2026
Layout approvalFile: Layout Plan.pdf30 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Form 1File: Form-1 _ ARCHITECTS CERTIFICATE (JUNE-23).pdf24 Feb 2026
Form 2File: Form-2 _ ENGINEERS CERTIFICATE (JUNE-23).pdf24 Feb 2026
Form 3File: Form-3 _ CA Certificate (June-2023)_compressed.pdf24 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Units (Jun-23).pdf24 Feb 2026
Form 1File: Form 1 (Architects certificate Sep23).pdf24 Feb 2026
Form 2File: Form 2 (Engineers certificate Sep23).pdf24 Feb 2026
Form 3File: Form 3 (CA certificate Sep23).pdf24 Feb 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory - Godrej Greens (as on 30-Sep-23).pdf24 Feb 2026
Architect’s Certificate on Completion of Project (Form 4)File: Godrej Greens _ Form4 (31Dec24).pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej Greens _ Q3 _ Form-1.pdf20 Jan 2025
Certificates of CA (Form 3)File: Godrej Greens _ Q3 _ Form-3.pdf20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej Greens _ Q3 _ Form-2.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Godrej Greens _ Q3 _ sold unsold units.pdf20 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect's Certificate Sep-24 _ Signed.pdf11 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer's Certificate Sep-24 _ Signed.pdf11 Oct 2024
Certificates of CA (Form 3)File: Form 3_ CA Certificate (DWLLP) Sept 2024 _ Signed.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold unsold units Sep-24 _ Signed.pdf11 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect's Certificate Sep-24 _ Signed.pdf11 Oct 2024
Certificates of CA (Form 3)File: Form 3_ CA Certificate (DWLLP) Sept 2024 _ Signed.pdf11 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer's Certificate Sep-24 _ Signed.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold unsold units Sep-24 _ Signed.pdf11 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DWLLP Form-5.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: DWLLP Form-5.pdf9 Oct 2024
Form 5 (FY 2023-2024)File: DWLLP Form-5.pdf27 Sep 2024
Certificates of CA (Form 5)File: CA Certificate_Godrej Greens (Jun-24).pdf17 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate (Jun-24).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate (Jun-24).pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: Greens _ Sold unsold units (Jun-24).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greens _ Engineers Certificate (Mar-24).pdf18 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Greens _ Architect's Certificate (Mar-24).pdf17 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Greens _ Quality Assurance Certificate (Mar-24).pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Greens _ Sold Unsold Units (March-24)_compressed_compressed_11zon.pdf17 Apr 2024
Certificates of CA (Form 3)File: Greens _ CA Certificate (Mar-24)_compressed.pdf16 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Godrej Greens _ OC copy.pdf28 Feb 2024
Certificates of CA (Form 3)File: Undri _ CA certificate (Dec-23).pdf12 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate (Dec-23).pdf11 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate (Dec-23).pdf11 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold units (Dec-23).pdf11 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 (Engineers certificate Sep23).pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_compressed (1).pdf20 Oct 2023
Certificates of CA (Form 3)File: Form 3-final compressed 1_11zon.pdf20 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Dream World FY22 - Godrej Greens signed.pdf21 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Dreamworld - Greens SIGNED.pdf21 Sep 2023
Certificates of CA (Form 3)File: Greens_CA final_11zon.pdf19 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: greens_architect certificate.pdf10 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Greens_engineer certificate.pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: greens_disclosure of inventory_compressed_11zon.pdf10 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf20 Apr 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Godrej PranaP52100001372UNDRI, Pune667Jul 2017OngoingSep 2020Not delivered

How this compares with Pune

88%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Undri13,700+ in Pune

2 kmGodrej GreensCompleted 66Lapsed / revoked 27Other 47Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: DREAM WORLD LANDMARKS LLP

DREAM WORLD LANDMARKS LLP has 3 registrations on MahaRERA, including Godrej Greens and Godrej Prana. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej Greens is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej Greens?

The registered promoter entity is DREAM WORLD LANDMARKS LLP, an others as per the filing. Its GSTIN 27AAIFD5398J1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Greens?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej Greens?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej Greens?

The professionals named in the filing: Architect: ARCHITECTURE COLLECTIVE; Architect: Gaurav Sanan; Engineer: Gem Engserv Pvt Ltd; Engineer: Anil Tukaram Powar; Chartered Accountant: M D Deshpande & Co.; Chartered Accountant: MADHAV DAMODAR DESHPANDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Greens. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Greens to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.