VIJAY VIHAR
RG-MH-24044 · RERA P52100009408 · Last updated on MahaRERA portal: 11 Feb 2026
Source: official MahaRERA filing
Red flags
- 11 complaints at MahaRERA
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VIJAY VIHAR is a Residential / Group Housing project by COL. RPS RAWAT in Pune, Maharashtra, registered with MahaRERA as P52100009408 on 22 Aug 2017. The registration is recorded completed; possession was promised by 13 Dec 2022. The completion date has moved by 36 months from the original filing. 728 of the 728 units on this registration are recorded sold or booked, and 35 of 165 construction stages are filed complete. 11 complaints are on record with the regulator.
At a glance
Project
- NameVIJAY VIHAR
- TypeResidential / Group Housing
- Location
- WAGHOLI
- Haveli
- Pune
- 412207
- Pincode412207
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100009408
- ReraGenie IDRG-MH-24044
Builder
- NameCOL. RPS RAWAT
- Entity typeOthers
- Named personNIL
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Aug 2017
- Promised completion13 Dec 2022
- Revised completionRevised to 13 Dec 2022 (originally 31 Dec 2019)
- Buildings15 building records
- Documents filed44 files
Current status
Figures as on 11 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER-A | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-B | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-C | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-D | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-E | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-F | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-G | NA | 16 | 15 | 84 | 0 | 84 |
| TOWER-H | NA | 16 | 15 | 84 | 0 | 84 |
| TOWER-J | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-K | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-L | NA | 16 | 15 | 56 | 0 | 56 |
| TOWER-M | NA | 16 | 15 | 56 | 0 | 56 |
| PODIUM | NA | 3 | 2 | 0 | 0 | 0 |
| CLUB | NA | 2 | 2 | 0 | 0 | 0 |
| SHOPPING | NA | 2 | 2 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building15
As on 11 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
35 of 165 construction stages are filed complete across 15 buildings. The stage furthest along is External plumbing and external plaster, at 95%.
TOWER-A52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
TOWER-B42%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-C46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-D39%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 3% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-E40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 2% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-F51%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-G36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 14% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 2% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-H33%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 2% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-J39%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 4% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-K40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 3% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-L45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 2% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TOWER-M35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 1% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PODIUM17%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 1% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 2% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLUB18%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 1% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHOPPING9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1014
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| TOWER-A | 6 | 2 | 8 |
| TOWER-B | 6 | 2 | 8 |
| TOWER-C | 6 | 2 | 8 |
| TOWER-D | 6 | 2 | 8 |
| TOWER-E | 1 | 6 | 7 |
| TOWER-F | 1 | 6 | 7 |
| TOWER-G | 1 | 0 | 1 |
| TOWER-H | 1 | 0 | 1 |
| TOWER-J | 1 | 0 | 1 |
| TOWER-K | 1 | 0 | 1 |
| TOWER-L | 1 | 0 | 1 |
| TOWER-M | 1 | 0 | 1 |
| PODIUM | 944 | 0 | 944 |
| CLUB | 0 | 10 | 10 |
| SHOPPING | 0 | 8 | 8 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | M/s Nivedita and Uday Pande Consultants |
| Engineer | Lokesh Kumar Tyagi |
| Chartered Accountant | MS LUTHRA AND LUTHRA |
| Chartered Accountant | ANJAN AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| COL. RPS RAWAT | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterLANDSCAPE WORKS AND INSTALLATION OF LIFTS ARE PROPOSED TO BE DONE
Reason as filed by the promoterThe project work is 100% completed. We have received Full Occupancy Certificate dated 13/12/2022. We require extension till date of Occupancy Certificate.
Complaints filed with MahaRERA11
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000116861 | Abhishek Chourasia | Project Director | 12/06/2022 |
| CC005000000075088 | Bharat Gupta | Managing Director AWHO | 19/01/2021 |
| CC005000000096069 | Lt Col Mudit Arya & Mrs Ruchi Arya | MD AWHO, VIJAY VIHAR | 29/09/2021 |
| CC005000000096103 | Lt Col Amit Kulkarni | Army Welfare Housiing Organization | 07/10/2021 |
| CC005000000096106 | Lt Col Rajesh Kumar Jha | AWHO Vijaya VIhar | 11/10/2021 |
| CC005000000096120 | Col S. N. Singh | AWHO Vijaya VIhar | 18/10/2021 |
| CC005000000096141 | Lt. Col. Nitesh Kumar | AWHO Vijaya VIhar | 18/10/2021 |
| CC005000000096151 | Lt. Col Kaushik Misra | AWHO | 01/11/2021 |
| CC005000000096159 | Dr. Ajay Arunachalam | AWHO Vijaya VIhar | 22/10/2021 |
| CC005000000106368 | Mosin Adawadkar | AWHO | 20/12/2021 |
| CC005000000096274 | BRIG MOHAN LAL VERMA | COL JS BARGOTI | 19/11/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 19 Nov 2024
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Sanctioned layout NEW-compressed.pdf | 11 Feb 2026 |
| Occupational CertificateFile: OCCUPANCY CERTIFICATE - VIJAY VIHAR.pdf | 6 Nov 2025 |
| Occupational CertificateFile: OC VERIFICATION.pdf | 6 Nov 2025 |
| Occupational CertificateFile: DECLARATION OF VIJAY VIHAR.pdf | 6 Nov 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DECLARATION - QPR.pdf | 21 May 2025 |
| Certificates of CA (Form 3)File: DECLARATION - QPR.pdf | 21 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DECLARATION - QPR.pdf | 21 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 31 Mar 2020.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 31 Mar 2021.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 31 Mar 2022.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 31 Mar 2023.pdf | 8 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 31 Mar 2024.pdf | 8 May 2025 |
| Other - FinanceFile: Resolution PHR for all depts.pdf | 30 Apr 2025 |
| Other - TechnicalFile: Resolution PHR for all depts.pdf | 30 Apr 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM IV.pdf | 27 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC A B C F L M BLOCK.pdf | 19 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM IV.pdf | 13 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART.pdf | 29 Jun 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: fULL.pdf | 29 Jun 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: LETTER FOR SOCIETY FORMATION.pdf | 29 Jun 2023 |
| Status of ConveyanceFile: LETTER FOR CONVEYANCE DEED.pdf | 29 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QUALITY ASSURANCE.pdf | 28 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual_Audit_Report_2018.pdf | 28 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual_Audit_Report_2019.pdf | 28 Dec 2019 |
| Certificates of CA (Form 5)File: CA_2.pdf | 12 Mar 2019 |
| Building plan approvalFile: Download File-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Layout approvalFile: awho_-pmrda_Sheet_1_-_24-12-2015-ilovepdf-compressed.pdf | 31 Jul 2017 |
| PAN CardFile: PAN CARD.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Download File--compressed.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Download File-compressed.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Download File--compressed.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Download File-compressed.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: awho_-pmrda_Sheet_1_-_24-12-2015-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Download File-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: awho_-pmrda_CC_-_24-12-2015--compressed (1).pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Download File.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: C 1.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: C 2.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Download File-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Download File-ilovepdf-compressed.pdf | 31 Jul 2017 |
| OtherFile: SALE DEED 1to 10.pdf | 31 Jul 2017 |
| OtherFile: SALE DEED 11 to20.pdf | 31 Jul 2017 |
| OtherFile: SALE DEED 21 to 26.pdf | 31 Jul 2017 |
| OtherFile: SALE DEED 27 to 32.pdf | 31 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VRINDAVAN AWAS YOJNA | 56 CHAURAHA LAL BAHADUR SHASTRI MARG CANTT LUCKNOW | 220 | Completed | Feb 2019 | Feb 2019 |
| VRINDAVAN AWAS YOJNA | 56 CHAURAHA LAL BAHADUR SHASTRI MARG CANTT LUCKNOW | 336 | Completed | Feb 2019 | Feb 2019 |
| PRATAP VIHAR | PAWAN NAGAR CIDCO NASIK | 132 | Completed | Nov 2014 | Late, Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
Keep VIJAY VIHAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WAGHOLI13,700+ in Pune
Filed coordinates, straight-line distance. 26 registered projects within 2 km.
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
KOHINOOR RIVERDALE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: COL. RPS RAWAT
COL. RPS RAWAT has 1 registration on MahaRERA, including VIJAY VIHAR. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if VIJAY VIHAR is delayed beyond 13 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VIJAY VIHAR?
The registered promoter entity is COL. RPS RAWAT, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VIJAY VIHAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VIJAY VIHAR?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VIJAY VIHAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VIJAY VIHAR?
The professionals named in the filing: Architect: M/s Nivedita and Uday Pande Consultants; Engineer: Lokesh Kumar Tyagi; Chartered Accountant: MS LUTHRA AND LUTHRA; Chartered Accountant: ANJAN AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VIJAY VIHAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback