Home / Browse projects / Aurangabad, Maharashtra / CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD
CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD
By AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
RG-MH-39387 · RERA P51500034364 · Last updated on MahaRERA portal: 28 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD is a Others project by AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) in Aurangabad, Maharashtra, registered with MahaRERA as P51500034364 on 4 Apr 2022. Possession is promised by 31 Dec 2027.
At a glance
Project
- NameCONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD
- TypeOthers
- Location
- GUT NO 708 JALNA ROAD AURANGABAD
- OPPSITE AURANGABAD AIRPORT CHIKALTHANA
- Aurangabad (M Corp.)
- Aurangabad
- 431001
- Pincode431001
- RERA no.P51500034364
- ReraGenie IDRG-MH-39387
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Apr 2022
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings10 building records
- Documents filed41 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING - A | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - B | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - C | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING -D | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - E | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - F | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - G | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING -H | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - I | NA | 11 | 0 | 0 | 0 | 0 |
| BUILDING - J | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building10
As on 28 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
75 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 80%.
BUILDING - A88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
BUILDING - B83%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
BUILDING - C86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
BUILDING -D89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
BUILDING - E87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
BUILDING - F80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
BUILDING - G78%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
BUILDING -H77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
BUILDING - I35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING - J45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 28 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
| LIFT | Yes | 40% |
Parking filed420
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| BUILDING - A | 42 | 42 |
| BUILDING - B | 42 | 42 |
| BUILDING - C | 42 | 42 |
| BUILDING -D | 42 | 42 |
| BUILDING - E | 42 | 42 |
| BUILDING - F | 42 | 42 |
| BUILDING - G | 42 | 42 |
| BUILDING -H | 42 | 42 |
| BUILDING - I | 42 | 42 |
| BUILDING - J | 42 | 42 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANTOSH SAKHARE |
| Engineer | JV STRUCTURAK ENGINEER |
| Chartered Accountant | CHIEF ACCOUNT OFFICER MHADA AURANGABAD |
| Partner | Role in project |
|---|---|
| CHHATRAPATI SAMBHAJINAGAR HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed41
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2File: form2 390 lig_0001.pdf | 28 Apr 2026 |
| Form 1File: Chikalthana Form 1_compressed_compressed (1).pdf | 28 Apr 2026 |
| Self-declaration of Quarterly ProgressFile: qpr declare_0001-4.pdf | 28 Apr 2026 |
| Form 3File: Form - 3 390 Chikalthana_compressed (3).pdf | 28 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: 390 LIG 16 Shops Chikalthana sold_compressed (1).pdf | 28 Apr 2026 |
| Form 1File: Chikalthana Form 1_compressed_compressed.pdf | 12 Feb 2026 |
| Form 2File: form2 390 lig_0001_compressed.pdf | 12 Feb 2026 |
| Form 3File: Form - 3 390 Chikalthana_compressed (2).pdf | 12 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: 390 LIG 16 Shops Chikalthana sold_compressed.pdf | 12 Feb 2026 |
| Self-declaration of Quarterly ProgressFile: 390 lig.pdf | 12 Feb 2026 |
| Form 1File: Chikalthana Form 1_compressed.pdf | 16 Jan 2026 |
| Form 2File: form2 390 lig_0001.pdf | 16 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 390 LIG 16 Shops Chikalthana sold.pdf | 16 Jan 2026 |
| Form 3File: Form - 3 390 Chikalthana_compressed (1).pdf | 16 Jan 2026 |
| Self-declaration of Quarterly ProgressFile: 390.pdf | 16 Jan 2026 |
| Form 1File: Chikalthana Form 1_compressed.pdf | 18 Jul 2025 |
| Form 2File: form2 390 lig_0001.pdf | 18 Jul 2025 |
| Form 3File: Form - 3 390 Chikalthana_compressed.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 390 LIG & 16 Shops Chikalthana.pdf | 18 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: QPR 390 Chikalthana.pdf | 18 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera Certificate_compressed.pdf | 23 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf | 8 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 8 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: P51500034364.pdf | 20 May 2024 |
| Copy of the legal title reportFile: TITLE SEARCH REPORT_ASRAR (2).pdf | 26 Mar 2022 |
| Copy of the legal title reportFile: FINAL RERA TSR.pdf | 26 Mar 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200232529245_For_Debtor_Based_Search_15_03_2022_20_01_12_820.pdf | 26 Mar 2022 |
| Layout approvalFile: MHADA LAYOUT PLAN.pdf | 18 Feb 2022 |
| Building plan approvalFile: MHADA PERMISSION.pdf | 18 Feb 2022 |
| Details of encumbrancesFile: MHADA NON ENCUMBRANCE.pdf | 18 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: MHADA LAYOUT PLAN.pdf | 18 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: MHADA PERMISSION.pdf | 18 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: MHADA COMMENCEMENT CHIKALTHANA.pdf | 18 Feb 2022 |
| Declaration about Commencement CertificateFile: MHADA FORM B DECLARATION.pdf | 18 Feb 2022 |
| Declaration in FORM BFile: MHADA FORM B DECLARATION.pdf | 18 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MHADA ARCH CERTIFICATE.pdf | 18 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG 2 A.pdf | 18 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: MHADA FORM 2A-.pdf | 18 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERTIFICATE.pdf | 18 Feb 2022 |
| Proforma of Allotment letterFile: ATS MHADA.pdf | 18 Feb 2022 |
| Proforma of Allotment letterFile: MHADA ALLOTMENT LETTER.pdf | 18 Feb 2022 |
Promoter's earlier projects7
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Proposed construction of 60 L.I.G. T/s Scheme on Plot No. 03, Gut No. 736/Part, Chikalthana, AurangP51500054769 | Plot No. 03, Gut No. 736/Part, Chikalthana, Aurangabad, Aurangabad | 60 | Feb 2024 | Ongoing | Dec 2029 | Not due yet |
| CONSTRUCTION OF 368 EWS T/S UNDER PMAY AND 168 MIG ON S.NO.68 AT PADHEGOAN ,DIST-AURANGABADP51500026531 | AURANGABAD, Aurangabad | 536 | Sep 2020 | Completed | Mar 2026 | Jul 2024 |
| Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, BeedP52300049313 | Ambejogai, Beed | 244 | Feb 2023 | Ongoing | Dec 2025 | Not delivered |
| Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist HingoliP51200027577 | hingoli, Hingoli | 180 | Dec 2020 | Ongoing | Mar 2025 | Not delivered |
| 736 EWS TS AND 256 MIG TS AT PLOT NO R-1 ADDITIONAL MIDC LATURP52400017486 | ADD. MIDC, Latur | - | Aug 2018 | Ongoing | Dec 2022 | Not delivered |
| 364 EWS T/S UNDER PMAY AT JALNA DIS JALNAP51400012018 | jalna, Jalna | 80 | Sep 2017 | Completed | Jul 2019 | Late, Sep 2020 |
| CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABADP51500013212 | NAKSHATRAWADI, Aurangabad | 240 | Sep 2017 | Completed | Apr 2019 | Late, Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 8 other registrations, which the RERA portal never shows together
- All 41 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near OPPSITE AURANGABAD AIRPORT CHIKALTHANA1,400+ in Aurangabad
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
AMRUT SAI PLAZA PH 2
Shree Amrut Sai Developer Pvt.Ltd
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
See every Aurangabad project, with the district possession charts
Builder: AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) has 9 registrations on MahaRERA, including 364 EWS T/S UNDER PMAY AT JALNA DIS JALNA and CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD. Its filings disclose 8 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD?
The registered promoter entity is AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA), a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD?
The professionals named in the filing: Architect: SANTOSH SAKHARE; Engineer: JV STRUCTURAK ENGINEER; Chartered Accountant: CHIEF ACCOUNT OFFICER MHADA AURANGABAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABAD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback