Home / Browse projects / Aurangabad, Maharashtra / AQ TOWN

Registered No litigation declared Residential / Group Housing project

AQ TOWN

By AQ INFRASTRUCTURE PRIVATE LIMITED

RG-MH-02196 · RERA P51500012659 · Last updated on MahaRERA portal: 21 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 120 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Aug 2035Possession promisedmoved 120 months from the original
187 of 429Construction stages doneacross 39 buildings; furthest along: Excavation, 80%
320 of 384Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 234 documents Report an error

AQ TOWN is a Residential / Group Housing project by AQ INFRASTRUCTURE PRIVATE LIMITED in Aurangabad, Maharashtra, registered with MahaRERA as P51500012659 on 7 Sep 2017. Possession is promised by 28 Aug 2035. The completion date has moved by 120 months from the original filing. 64 of the 384 units on this registration are recorded sold or booked, and 187 of 429 construction stages are filed complete.

At a glance

Project

  • NameAQ TOWN
  • TypeResidential / Group Housing
  • Location
    • JALAN NAGAR
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500012659
  • ReraGenie IDRG-MH-02196

Builder

  • NameAQ INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorSYED ABDUL GAFFAR QUADRI
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2017First promiseAug 2025Revised toAug 2035

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Sep 2017
  • Promised completion28 Aug 2035
  • Revised completionRevised to 28 Aug 2035 (originally 28 Aug 2025)
  • Buildings39 building records
  • Documents filed234 files

Current status

17%64 of 384 units booked
8.7%Work done, per cost certificate

Figures as on 21 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
APARTMENT BUILDING TYPE C SADAT APARTMENTNA66321042
APARTMENT BUILDING TYPE D RAHMAT APARTMENTS WING ANA6010010
TYPE A BUNGLOW NO 1NA11101
TYPE A BUNGLOW NO 2NA11101
TYPE B BUNGLOW NO 7NA11101
TYPE B BUNGLOW NO 8NA11101
TYPE B BUNGLOW NO 9NA11101
TYPE B BUNGLOW NO 10NA11101
ROW HOUSE NO 1NA11101
ROW HOUSE NO 2NA11101
ROW HOUSE NO 3NA11101
ROW HOUSE NO 4NA11101
ROW HOUSE NO 5NA11101
ROW HOUSE NO 6NA11101
APARTMENT BUILDING TYPE A VISION TOWER A WINGNA131236036
APARTMENT BUILDING TYPE B TAUHEED APARTMENT WING ANA1028028
APARTMENT BUILDING TYPE A VISION TOWER B WINGNA121236036
APARTMENT BUILDING TYPE A VISION TOWER C WINGNA121244044
APARTMENT BUILDING TYPE A VISION TOWER D WINGNA121244044
APARTMENT BUILDING TYPE A VISION TOWER E WINGNA121244044
TYPE A VISION TOWERNA11011
TYPE A VISION TOWERNA11011
TYPE A VISION TOWERNA11011
TYPE A VISION TOWERNA11011
TYPE A VISION TOWERNA11011
TYPE A VISION TOWERNA11011
TYPE A VISION TOWERNA00011
TYPE A VISION TOWERNA11011
APARTMENT TYPE B TAUHEED APARTMENT B WINGNA1028028
TYPE C SADAT APARTMENTNA11044
TYPE C SADAT APARTMENTNA11011
TYPE C SADAT APARTMENTNA11011
TYPE C SADAT APARTMENTNA11011
TYPE C SADAT APARTMENTNA11101
TYPE C SADAT APARTMENTNA11011
TYPE C SADAT APARTMENTNA11011
BUILDING TYPE B TAUHEED APARTMENT C WINGNA1022022
APARTMENT TYPE D RAHMAT APARTMENT WING BNA7010010
APARTMENT TYPE D RAHMAT APARTMENT WING CNA6610010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 21 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 39 buildings; the table lists the first 20.

187 of 429 construction stages are filed complete across 39 buildings. The stage furthest along is Excavation, at 80%.

APARTMENT BUILDING TYPE C SADAT APARTMENT82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
APARTMENT BUILDING TYPE D RAHMAT APARTMENTS WING A36%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE A BUNGLOW NO 173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE A BUNGLOW NO 273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B BUNGLOW NO 773%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B BUNGLOW NO 873%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B BUNGLOW NO 973%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B BUNGLOW NO 1073%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE NO 173%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE NO 273%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE NO 373%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE NO 473%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE NO 573%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ROW HOUSE NO 673%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
APARTMENT BUILDING TYPE A VISION TOWER A WING26%
ActivityProgress
Excavation80%
Basement (if any)70%
Podiums (if any)30%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
APARTMENT BUILDING TYPE B TAUHEED APARTMENT WING A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
APARTMENT BUILDING TYPE A VISION TOWER B WING26%
ActivityProgress
Excavation80%
Basement (if any)70%
Podiums (if any)30%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
APARTMENT BUILDING TYPE A VISION TOWER C WING26%
ActivityProgress
Excavation80%
Basement (if any)70%
Podiums (if any)30%
Plinth100%
Stilt Floor1%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
APARTMENT BUILDING TYPE A VISION TOWER D WING26%
ActivityProgress
Excavation80%
Basement (if any)70%
Podiums (if any)30%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
APARTMENT BUILDING TYPE A VISION TOWER E WING26%
ActivityProgress
Excavation80%
Basement (if any)70%
Podiums (if any)30%
Plinth100%
Stilt Floor0%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed297

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots297
Closed/Covered210
Open Space87
BuildingClosed/CoveredOpen SpaceTotal
APARTMENT BUILDING TYPE C SADAT APARTMENT24832
APARTMENT BUILDING TYPE D RAHMAT APARTMENTS WING A7310
TYPE A BUNGLOW NO 1022
TYPE A BUNGLOW NO 2022
TYPE B BUNGLOW NO 7022
TYPE B BUNGLOW NO 8011
TYPE B BUNGLOW NO 9022
TYPE B BUNGLOW NO 10011
ROW HOUSE NO 1022
ROW HOUSE NO 2022
ROW HOUSE NO 3022
ROW HOUSE NO 4022
ROW HOUSE NO 5022
ROW HOUSE NO 6022
APARTMENT BUILDING TYPE A VISION TOWER A WING27835
APARTMENT BUILDING TYPE B TAUHEED APARTMENT WING A404
APARTMENT BUILDING TYPE A VISION TOWER B WING27936
APARTMENT BUILDING TYPE A VISION TOWER C WING331144
APARTMENT BUILDING TYPE A VISION TOWER D WING33942
APARTMENT BUILDING TYPE A VISION TOWER E WING33942
APARTMENT TYPE B TAUHEED APARTMENT B WING404
TYPE C SADAT APARTMENT011
TYPE C SADAT APARTMENT011
BUILDING TYPE B TAUHEED APARTMENT C WING404
APARTMENT TYPE D RAHMAT APARTMENT WING B7310
APARTMENT TYPE D RAHMAT APARTMENT WING C7310

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,898 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on5 Nov 2025

Approvals and building plan

Sanctioning authorityAURANGABAD MUNICIPAL CORPORATION AURANGABAD
Permissible FSI5977.79
Proposed, not sanctioned5,978 sq m
Buildings approved39
Buildings sanctioned39

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHAHGANJ AURANGABAD
Estimated costRs 102.94 cr
Cost incurredRs 8.93 cr
Work done8.68%
BuildingWingEstimatedIncurred
-NARs 50.30 cr-
APARTMENT BUILDING TYPE A VISION TOWER A WINGNARs 29.89 crRs 1.46 cr
APARTMENT BUILDING TYPE B TAUHEED APARTMENT WING ANARs 13.68 cr-
APARTMENT BUILDING TYPE D RAHMAT APARTMENTS WING ANARs 4.05 crRs 2.45 cr
APARTMENT BUILDING TYPE C SADAT APARTMENTNARs 2.58 crRs 2.58 cr
TYPE A BUNGLOW NO 1NARs 34.44 lakhRs 34.44 lakh
TYPE A BUNGLOW NO 2NARs 30.10 lakhRs 30.10 lakh
TYPE B BUNGLOW NO 9NARs 20.66 lakhRs 20.66 lakh
TYPE B BUNGLOW NO 10NARs 20.66 lakhRs 20.66 lakh
TYPE B BUNGLOW NO 7NARs 18.16 lakhRs 18.16 lakh
TYPE B BUNGLOW NO 8NARs 18.16 lakhRs 18.16 lakh
ROW HOUSE NO 1NARs 17.97 lakhRs 17.97 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMD YUNUS
EngineerMD Yunus
Chartered AccountantHUSAIN & CO
PartnerRole in project
AQ INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA17082502386Aug 2025 → Aug 2035

Reason as filed by the promoter1.DUE TO PANDEMIC ALL ACTIVITIES INCULDING CONSTRCUTION WERE STOP FOR ALMOST 3 YEARS 2. AS PER UDCPR-2021 NO OF UNITS TO CONSTRUCTED WERE INCREASED AS PER NEW REVISED SACNTIONED PLAN

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Aug 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 2 Apr 2023

Documents filed234

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 234 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate Cottar 1.pdf21 Jun 2026
Withdrawal Update Form 1File: QPR 2 FORM 1 25-26 (2).pdf21 Jun 2026
Withdrawal Update Form 1File: FORM 1 QPR 3 2025-26.pdf21 Jun 2026
Withdrawal Update Form 1File: Architects Certificate Q 4 2025-2026.pdf21 Jun 2026
Withdrawal Update Form 2File: Engineers Certificate Q 1.pdf21 Jun 2026
Withdrawal Update Form 2File: Engnieer Certificate Q 2.pdf21 Jun 2026
Withdrawal Update Form 2File: Engineering Certificate Q3.pdf21 Jun 2026
Withdrawal Update Form 2File: Engineer Certificate Q 4.pdf21 Jun 2026
Withdrawal Update Form 3File: Form 3 Chartered Accountantu0027s certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf21 Jun 2026
Withdrawal Update Form 3File: AQ INFRASTRUCTURE Q2.pdf21 Jun 2026
Withdrawal Update Form 3File: AQ INFRASTRUCTURE Q 3 FORM 3 25-26.pdf21 Jun 2026
Withdrawal Update Form 3File: AQ INFRASTRUCTURE Q 4 FORM 3 25-26.pdf21 Jun 2026
Form 2A (FY 2025-2026)File: Quality Assurance.pdf21 Jun 2026
Form 5 (FY 2025-2026)File: AQ INFRASTRUCTURE Annual Report.pdf18 Jun 2026
Withdrawal Update Form 1File: Form 1 Architectu0027s Certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf18 Nov 2025
Withdrawal Update Form 1File: Form 1 Architectu0027s Certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf18 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineeringu0027s Certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf18 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineeringu0027s Certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf18 Nov 2025
Withdrawal Update Form 3File: Form 3 Chartered Accountantu0027s certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf18 Nov 2025
Withdrawal Update Form 3File: Form 3 Chartered Accountantu0027s certificate 1-4-25 to 30-6-25 QPR 1 2025-26.pdf18 Nov 2025
Withdrawal Update Form 1File: Form 1 01-04-25 to 30-06-25.pdf12 Nov 2025
Withdrawal Update Form 2File: Form 2 01-04-25 to 30-06-25.pdf12 Nov 2025
Withdrawal Update Form 3File: Form 3 01-04-25 to 30-06-25_compressed.pdf12 Nov 2025
Withdrawal Update Form 1File: Form 1 01-04-25 to 30-06-25.pdf7 Nov 2025
Withdrawal Update Form 2File: Form 2 01-04-25 to 30-06-25.pdf7 Nov 2025
Withdrawal Update Form 3File: Form 3 01-04-25 to 30-06-25_compressed.pdf7 Nov 2025
Withdrawal Update Form 1File: Form 1 01-04-25 to 30-06-25.pdf17 Sep 2025
Withdrawal Update Form 1File: Form 1 01-04-25 to 30-06-25.pdf17 Sep 2025
Withdrawal Update Form 2File: ENGINEER CERTIFICATE 3RD PAGE.pdf17 Sep 2025
Withdrawal Update Form 2File: Form 2 01-04-25 to 30-06-25.pdf17 Sep 2025
Withdrawal Update Form 3File: form no 3.pdf17 Sep 2025
Withdrawal Update Form 3File: Form 3 01-04-25 to 30-06-25_compressed.pdf17 Sep 2025
Form 2A (FY 2017-2018)File: FORM 2-A NEW.pdf17 Sep 2025
Form 2A (FY 2018-2019)File: FORM 2-A NEW.pdf17 Sep 2025
Form 2A (FY 2019-2020)File: FORM 2-A NEW.pdf17 Sep 2025
Form 2A (FY 2022-2023)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23).pdf17 Sep 2025
Form 2A (FY 2023-2024)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf17 Sep 2025
Form 2A (FY 2020-2021)File: FORM 2-A NEW.pdf17 Sep 2025
Form 2A (FY 2021-2022)File: FORM 2-A NEW.pdf17 Sep 2025
Form 1File: Form 1 01-01-2025 to 31-03-2025.pdf16 Sep 2025
Form 2File: Form 2 01-01-25 to 31-03-2025.pdf16 Sep 2025
Form 3File: Form 3 01-01-25 to 31-03-25.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory AQ_compressed.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025
Form 2File: ENG 31-03-2022 AQ.pdf16 Sep 2025
Form 3File: FORM 3 2017 AQ.pdf16 Sep 2025
Disclosure of Sold and Booked InventoryFile: DIS CLOSURE AQ OLD.pdf16 Sep 2025
Form 1File: ARC AQ 31-03-2022.pdf16 Sep 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
AQ HEIGHTSP51500011237Aurangabad (M Corp.), AurangabadAug 2017CompletedFeb 2021Dec 2020

How this compares with Aurangabad

17%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 120 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep AQ TOWN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near JALAN NAGAR1,400+ in Aurangabad

Builder: AQ INFRASTRUCTURE PRIVATE LIMITED

AQ INFRASTRUCTURE PRIVATE LIMITED has 2 registrations on MahaRERA, including AQ HEIGHTS and AQ TOWN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if AQ TOWN is delayed beyond 28 Aug 2035?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AQ TOWN?

The registered promoter entity is AQ INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AQ TOWN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AQ TOWN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AQ TOWN?

The professionals named in the filing: Architect: MD YUNUS; Engineer: MD Yunus; Chartered Accountant: HUSAIN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AQ TOWN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AQ TOWN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AQ TOWN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.