Home / Browse projects / Aurangabad, Maharashtra / CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD
CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD
By AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
RG-MH-01893 · RERA P51500013212 · Last updated on MahaRERA portal: 7 Dec 2023
Source: official MahaRERA filing
Red flags
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD is a Residential / Group Housing project by AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) in Aurangabad, Maharashtra, registered with MahaRERA as P51500013212 on 21 Sep 2017. The registration is recorded completed; possession was promised by 20 Apr 2019.
At a glance
Project
- NameCONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD
- TypeResidential / Group Housing
- Location
- PAITHAN ROAD
- NAKSHATRAWADI
- Aurangabad (M Corp.)
- Aurangabad
- 431001
- Pincode431001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500013212
- ReraGenie IDRG-MH-01893
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on21 Sep 2017
- Promised completion20 Apr 2019
- Revised completionNone
- Buildings8 building records
- Documents filed29 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDG 1 | NA | 4 | 0 | 0 | 0 | 0 |
| BUILDG 2 | NA | 4 | 0 | 0 | 0 | 0 |
| BUILDG 3 | NA | 4 | 0 | 0 | 0 | 0 |
| BULDG 4 | NA | 4 | 0 | 0 | 0 | 0 |
| BUILDG 5 | NA | 4 | 0 | 0 | 0 | 0 |
| BUILDG 6 | NA | 4 | 0 | 0 | 0 | 0 |
| BUILDG 7 | NA | 4 | 0 | 0 | 0 | 0 |
| BUILDG 8 | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building8
As on 7 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
71 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDG 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDG 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDG 382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BULDG 482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDG 582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDG 682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDG 782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDG 873%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIRUDDHA RAMESHRAO NAIK |
| Engineer | PRASAD ARUN APHALE |
| Chartered Accountant | CHIEF ACCOUNT OFFICER MHADA AURANGABAD |
| Partner | Role in project |
|---|---|
| CHHATRAPATI SAMBHAJINAGAR HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Initial work order for Construction of 240 EWS T/s. & 80 MIG T/s. issued on date 21/04/2017 without taking firm demand, to start the work of Planning and Approval from Local Authority. Necessary approval for plans was received on date 27/07/2017. 2) As per direction given in VC by Hon’ble Vice President / Chief Executive Office Authority work order for 25% quantum of work i.e. for 64 T/s. was issued on date 16/08/2017. In the First Phase (before taking firm demand.) which is physically completed. 3) As per Tender Condition it was necessary to issue work order for Construction of T/s. as per
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 22 Dec 2022
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Details of encumbrances concerned to FinanceFile: RERA.pdf | 7 Dec 2023 |
| Details of encumbrances concerned to LegalFile: RERA.pdf | 7 Dec 2023 |
| Declaration about Commencement CertificateFile: RERA.pdf | 7 Dec 2023 |
| CERSAI detailsFile: RERA.pdf | 7 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: RERA.pdf | 7 Dec 2023 |
| Proforma of Agreement for saleFile: RERA.pdf | 7 Dec 2023 |
| Deviation Report with respect to Allotment letterFile: RERA.pdf | 7 Dec 2023 |
| Deviation Report with respect to model copy of AgreementFile: RERA.pdf | 7 Dec 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Nakshatrawadi RERA Bank Account.pdf | 20 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE FINAL.pdf | 22 Dec 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECTS CERTIFICATE.pdf | 22 Dec 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Nakhtrawadi Part OC.pdf | 8 Sep 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part occupancy.pdf | 8 Sep 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part occupancy.pdf | 8 Sep 2021 |
| Layout approvalFile: LAYOUT PLAN.pdf | 2 Aug 2017 |
| Building plan approvalFile: BUILDING PLAN2.pdf | 2 Aug 2017 |
| Building plan approvalFile: BUILDING PLAN2.pdf | 2 Aug 2017 |
| PAN CardFile: pan card.pdf | 2 Aug 2017 |
| Copy of the legal title reportFile: land clearance.PDF | 2 Aug 2017 |
| Copy of the legal title reportFile: 712.pdf | 2 Aug 2017 |
| Details of encumbrancesFile: non encubarance.PDF | 2 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 2 Aug 2017 |
| Building Plan Approval (IOD)File: BUILDING PLAN2.pdf | 2 Aug 2017 |
| Building Plan Approval (IOD)File: BUILDING PLAN2.pdf | 2 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: COM.pdf | 2 Aug 2017 |
| Declaration in FORM BFile: FORM B_opt.pdf | 2 Aug 2017 |
| Certificates of CA (Form 3)File: CA certificate_opt.pdf | 2 Aug 2017 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.PDF | 2 Aug 2017 |
| Proforma of Allotment letterFile: TABA PAVTI.PDF | 2 Aug 2017 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Proposed construction of 60 L.I.G. T/s Scheme on Plot No. 03, Gut No. 736/Part, Chikalthana, AurangP51500054769 | Plot No. 03, Gut No. 736/Part, Chikalthana, Aurangabad, Aurangabad | 60 | Feb 2024 | Ongoing | Dec 2029 | Not due yet |
| CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABADP51500034364 | OPPSITE AURANGABAD AIRPORT CHIKALTHANA, Aurangabad | 406 | Apr 2022 | Ongoing | Dec 2027 | Not due yet |
| CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABADP51500034364 | OPPSITE AURANGABAD AIRPORT CHIKALTHANA, Aurangabad | 390 | Apr 2022 | Ongoing | Dec 2027 | Not due yet |
| CONSTRUCTION OF 368 EWS T/S UNDER PMAY AND 168 MIG ON S.NO.68 AT PADHEGOAN ,DIST-AURANGABADP51500026531 | AURANGABAD, Aurangabad | 536 | Sep 2020 | Completed | Mar 2026 | Jul 2024 |
| Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, BeedP52300049313 | Ambejogai, Beed | 244 | Feb 2023 | Ongoing | Dec 2025 | Not delivered |
| Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist HingoliP51200027577 | hingoli, Hingoli | 180 | Dec 2020 | Ongoing | Mar 2025 | Not delivered |
| 736 EWS TS AND 256 MIG TS AT PLOT NO R-1 ADDITIONAL MIDC LATURP52400017486 | ADD. MIDC, Latur | - | Aug 2018 | Ongoing | Dec 2022 | Not delivered |
| 364 EWS T/S UNDER PMAY AT JALNA DIS JALNAP51400012018 | jalna, Jalna | 80 | Sep 2017 | Completed | Jul 2019 | Late, Sep 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 29 filed documents as one ZIP, foldered, with a manifest
Keep CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAKSHATRAWADI1,400+ in Aurangabad
Filed coordinates, straight-line distance. 25 registered projects within 2 km.
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
AMRUT SAI PLAZA PH 2
Shree Amrut Sai Developer Pvt.Ltd
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
See every Aurangabad project, with the district possession charts
Builder: AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) has 9 registrations on MahaRERA, including 364 EWS T/S UNDER PMAY AT JALNA DIS JALNA and CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD. Its filings disclose 8 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD is delayed beyond 20 Apr 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD?
The registered promoter entity is AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA), a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD?
The professionals named in the filing: Architect: ANIRUDDHA RAMESHRAO NAIK; Engineer: PRASAD ARUN APHALE; Chartered Accountant: CHIEF ACCOUNT OFFICER MHADA AURANGABAD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback