Home / Browse projects / Hingoli, Maharashtra / Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli
Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli
By AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
RG-MH-88221 · RERA P51200027577 · Last updated on MahaRERA portal: 19 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Hingoli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli is a Residential / Group Housing project by AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) in Hingoli, Maharashtra, registered with MahaRERA as P51200027577 on 16 Dec 2020. Possession was promised by 10 Mar 2026 and is now 7 months past that date. The completion date has moved by 12 months from the original filing. 0 of the 180 units on this registration are recorded sold or booked, and 33 of 99 construction stages are filed complete.
At a glance
Project
- NameConstruction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli
- TypeResidential / Group Housing
- Location
- sengoan narsi road
- hingoli
- 431513
- Pincode431513
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51200027577
- ReraGenie IDRG-MH-88221
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on16 Dec 2020
- Promised completion10 Mar 2026
- Revised completionRevised to 10 Mar 2026 (originally 10 Mar 2025)
- Buildings9 building records
- Documents filed49 files
Current status
Figures as on 19 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| L1 | NA | 3 | 3 | 12 | 0 | 12 |
| L2 | NA | 3 | 3 | 12 | 0 | 12 |
| L3 | NA | 3 | 3 | 12 | 0 | 12 |
| L4 | NA | 3 | 3 | 12 | 0 | 12 |
| E 1 | NA | 3 | 3 | 36 | 0 | 36 |
| E2 | NA | 3 | 3 | 24 | 0 | 24 |
| E3 | NA | 3 | 3 | 24 | 0 | 24 |
| E4 | NA | 3 | 3 | 24 | 0 | 24 |
| E5 | NA | 3 | 3 | 24 | 0 | 24 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
33 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Slabs of Super Structure, at 99%.
L162%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 99% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L252%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L354%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L464%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E 133%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 50% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E255%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E349%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E442%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E546%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed9
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| L1 | 1 | 1 |
| L2 | 1 | 1 |
| L3 | 1 | 1 |
| L4 | 1 | 1 |
| E 1 | 1 | 1 |
| E2 | 1 | 1 |
| E3 | 1 | 1 |
| E4 | 1 | 1 |
| E5 | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DATTATRAYA PARSHURAM |
| Engineer | SUDHAKAR BAHEGAVANKAR |
| Engineer | Ankur DIwedi |
| Chartered Accountant | VAIJANATH PHAD |
| Chartered Accountant | CHEIF ACCOUNT OFFICER |
| Chartered Accountant | Anjali Sangvikar |
| Partner | Role in project |
|---|---|
| CHHATRAPATI SAMBHAJINAGAR HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to less demand progress gets slow
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed49
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: form 1_0001 (1).pdf | 19 May 2026 |
| Form 2File: form2_0001.pdf | 19 May 2026 |
| Form 3File: form 3_0001.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: disclouser of sold unsold_0001 (1).pdf | 19 May 2026 |
| Self-declaration of Quarterly ProgressFile: declaration of QPR_0001 (1).pdf | 19 May 2026 |
| Form 2A (FY 2020-2021)File: 2a 2020-21_0001 (1).pdf | 19 May 2026 |
| Form 2A (FY 2021-2022)File: 2a 2021-22_0001 (1).pdf | 19 May 2026 |
| Form 2A (FY 2022-2023)File: 2a 2022-23_0001 (1).pdf | 19 May 2026 |
| Form 2A (FY 2023-2024)File: 2 a 2023-24_0001 (1).pdf | 19 May 2026 |
| Form 2A (FY 2024-2025)File: 2a 2024-25_0001 (1).pdf | 19 May 2026 |
| Form 2A (FY 2025-2026)File: 2a 2025-26_0001 (1).pdf | 19 May 2026 |
| Form 2File: Form - 2.pdf | 12 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: 132 EWS 48 LIG Hingoli.pdf | 12 Feb 2026 |
| Self-declaration of Quarterly ProgressFile: 132 ews declaration.pdf | 12 Feb 2026 |
| Form 1File: Form-1_compressed (1).pdf | 12 Feb 2026 |
| Form 3File: Form - 3 132 Hingoli_compressed (2).pdf | 12 Feb 2026 |
| Form 1File: Form 1 132 ews.pdf | 16 Jan 2026 |
| Form 2File: Form - 2.pdf | 16 Jan 2026 |
| Form 3File: Form - 3 132 Hingoli_compressed (1).pdf | 16 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 132 EWS 48 LIG Hingoli.pdf | 16 Jan 2026 |
| Self-declaration of Quarterly ProgressFile: 132.pdf | 16 Jan 2026 |
| Form 1File: Form-1_compressed.pdf | 18 Jul 2025 |
| Form 2File: Form - 2.pdf | 18 Jul 2025 |
| Form 3File: Form - 3 132 Hingoli_compressed.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 132 EWS & 48 LIG Hingoli.pdf | 18 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: QPR 132 EWS Hingili.pdf | 18 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (1).pdf | 28 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (1).pdf | 28 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: P51200027577.pdf | 20 May 2024 |
| Details of encumbrances concerned to FinanceFile: RERA.pdf | 7 Dec 2023 |
| Details of encumbrances concerned to LegalFile: RERA.pdf | 7 Dec 2023 |
| Declaration about Commencement CertificateFile: RERA.pdf | 7 Dec 2023 |
| CERSAI detailsFile: RERA.pdf | 7 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: RERA.pdf | 7 Dec 2023 |
| Proforma of Agreement for saleFile: RERA.pdf | 7 Dec 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA.pdf | 7 Dec 2023 |
| Deviation Report with respect to Allotment letterFile: RERA.pdf | 7 Dec 2023 |
| Deviation Report with respect to model copy of AgreementFile: RERA.pdf | 7 Dec 2023 |
| Layout approvalFile: Lay Out approval hingoli.pdf | 7 Dec 2020 |
| Building plan approvalFile: PLAN APPROVAL1.pdf | 7 Dec 2020 |
| PAN CardFile: PNA.pdf | 7 Dec 2020 |
| Copy of the legal title reportFile: legal title.pdf | 7 Dec 2020 |
| Details of encumbrancesFile: Non Encumbrance Certificate.PDF | 7 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: Lay Out approval hingoli.pdf | 7 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN APPROVAL1.pdf | 7 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Lay Out approval hingoli.pdf | 7 Dec 2020 |
| Declaration in FORM BFile: Form B_opt.pdf | 7 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form C.pdf | 7 Dec 2020 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.PDF | 7 Dec 2020 |
Promoter's earlier projects8
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Proposed construction of 60 L.I.G. T/s Scheme on Plot No. 03, Gut No. 736/Part, Chikalthana, AurangP51500054769 | Plot No. 03, Gut No. 736/Part, Chikalthana, Aurangabad, Aurangabad | 60 | Feb 2024 | Ongoing | Dec 2029 | Not due yet |
| CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABADP51500034364 | OPPSITE AURANGABAD AIRPORT CHIKALTHANA, Aurangabad | 406 | Apr 2022 | Ongoing | Dec 2027 | Not due yet |
| CONSTRUCTION OF 390 T-S LIG AND 16 SHOPS AT GUT NO 708-PART, CHIKALTHANA AURANGABADP51500034364 | OPPSITE AURANGABAD AIRPORT CHIKALTHANA, Aurangabad | 390 | Apr 2022 | Ongoing | Dec 2027 | Not due yet |
| CONSTRUCTION OF 368 EWS T/S UNDER PMAY AND 168 MIG ON S.NO.68 AT PADHEGOAN ,DIST-AURANGABADP51500026531 | AURANGABAD, Aurangabad | 536 | Sep 2020 | Completed | Mar 2026 | Jul 2024 |
| Construction of 244 EWS and 70 Shops under PMAY Housing Scheme on land S. No. 17 at Ambejogai, BeedP52300049313 | Ambejogai, Beed | 244 | Feb 2023 | Ongoing | Dec 2025 | Not delivered |
| 736 EWS TS AND 256 MIG TS AT PLOT NO R-1 ADDITIONAL MIDC LATURP52400017486 | ADD. MIDC, Latur | - | Aug 2018 | Ongoing | Dec 2022 | Not delivered |
| 364 EWS T/S UNDER PMAY AT JALNA DIS JALNAP51400012018 | jalna, Jalna | 80 | Sep 2017 | Completed | Jul 2019 | Late, Sep 2020 |
| CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABADP51500013212 | NAKSHATRAWADI, Aurangabad | 240 | Sep 2017 | Completed | Apr 2019 | Late, Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 49 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Construction of 132 TS EWS Under PMAY and 48 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near hingoli7 in Hingoli
KRISHNA TOWER
SUN INFRA DEVELOPERS LLP
SHRI RAMJIVAN VILLAS
SHRI RAMJIVAN BUILDCON
TBD Phase 2
MS Tirupati Builders And Developers
R M Dhariwal Garden City - Balsond Hingoli Plo
Dhariwal And Chhoriya Developers LLP
SANJEEVAN SRISHTI
SUSHILABAI DIGAMBRARAO PATANGE
THE CROWN
ABC DEVELOPERS
See every Hingoli project, with the district possession charts
Builder: AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA)
AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA) has 9 registrations on MahaRERA, including 364 EWS T/S UNDER PMAY AT JALNA DIS JALNA and CONSTRUCTION OF 240 EWS T/S ON GUT NO 09 NAKSATRAWADI AURANGABAD. Its filings disclose 8 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Hingoli district page.
Frequently asked questions
What does it mean that Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli is delayed beyond 10 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli?
The registered promoter entity is AURANGABAD HOUSING AND AREA DEVELOPMENT BOARD ( A REGIONAL UNIT OF MHADA), a public authority as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli?
The professionals named in the filing: Architect: DATTATRAYA PARSHURAM; Engineer: SUDHAKAR BAHEGAVANKAR; Engineer: Ankur DIwedi; Chartered Accountant: VAIJANATH PHAD; Chartered Accountant: CHEIF ACCOUNT OFFICER; Chartered Accountant: Anjali Sangvikar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Construction of 132 TS EWS Under PMAY and 48 TS LIG Scheme om S No 146 A at Hingoli dist Hingoli?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback