Home / Browse projects / Aurangabad, Maharashtra / AMRUT SAI PLAZA PH 2
AMRUT SAI PLAZA PH 2
By Shree Amrut Sai Developer Pvt.Ltd
RG-MH-00859 · RERA P51500011307 · Last updated on MahaRERA portal: 18 May 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 36 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMRUT SAI PLAZA PH 2 is a Residential / Group Housing project by Shree Amrut Sai Developer Pvt.Ltd in Aurangabad, Maharashtra, registered with MahaRERA as P51500011307 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Jul 2026. The completion date has moved by 36 months from the original filing. 224 of the 304 units on this registration are recorded sold or booked, and 90 of 110 construction stages are filed complete.
At a glance
Project
- NameAMRUT SAI PLAZA PH 2
- TypeResidential / Group Housing
- Location
- Station MIDC Road
- Silk Mill Colony
- Aurangabad (M Corp.)
- Aurangabad
- 431001
- Pincode431001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500011307
- ReraGenie IDRG-MH-00859
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Aug 2017
- Promised completion31 Jul 2026
- Revised completionRevised to 31 Jul 2026 (originally 31 Jul 2023)
- Buildings10 building records
- Documents filed89 files
Current status
Figures as on 18 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING L | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING M | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING N | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING O | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING P | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING Q | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING R | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING S | NA | 6 | 4 | 32 | 0 | 32 |
| BUILDING T | NA | 6 | 4 | 16 | 0 | 16 |
| BUILDING U | NA | 6 | 4 | 32 | 0 | 32 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building10
As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
90 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING L82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING M82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING N82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING O82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING P82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING Q82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING R82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING S82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING T82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING U82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed304
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| BUILDING L | 32 | 32 |
| BUILDING M | 32 | 32 |
| BUILDING N | 32 | 32 |
| BUILDING O | 32 | 32 |
| BUILDING P | 32 | 32 |
| BUILDING Q | 32 | 32 |
| BUILDING R | 32 | 32 |
| BUILDING S | 32 | 32 |
| BUILDING T | 16 | 16 |
| BUILDING U | 32 | 32 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 6.32 cr | Rs 6.32 cr |
| BUILDING L | NA | Rs 4.03 cr | Rs 4.03 cr |
| BUILDING M | NA | Rs 4.03 cr | Rs 4.03 cr |
| BUILDING N | NA | Rs 4.03 cr | Rs 4.03 cr |
| BUILDING O | NA | Rs 4.03 cr | Rs 4.03 cr |
| BUILDING P | NA | Rs 3.67 cr | Rs 3.67 cr |
| BUILDING Q | NA | Rs 3.67 cr | Rs 3.67 cr |
| BUILDING R | NA | Rs 3.67 cr | Rs 3.67 cr |
| BUILDING S | NA | Rs 3.67 cr | Rs 3.67 cr |
| BUILDING T | NA | Rs 3.67 cr | Rs 3.67 cr |
| BUILDING U | NA | Rs 3.67 cr | Rs 3.67 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ganesh Shriram Mharolkar |
| Engineer | Core Cosultants |
| Engineer | Prakash Uttamrao Vidhate |
| Chartered Accountant | M R Hundiwala & Co |
| Chartered Accountant | Nikhil N. Loya and Co. |
| Chartered Accountant | R. O. Heda & Co. |
| Partner | Role in project |
|---|---|
| Shree Amrut Sai Developer Pvt.Ltd | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe reasons and eplanation has been discussed in detail in submission enclosed herewith along with thw annexures thereof.
Reason as filed by the promoterThe Project is consist of 10 Buildings. Out of which 6 Buildings have already completed and part completion certificate/OC have been obtained from Aurangabad Municipal Corporation (First part completion in 2018 for 4 buildings and second part completion in 2021 for 2 buildings). Further the Promoter has also completed remaining 4 buildings of project and submitted an application for OC/Completion with Chh. Sambhajinagar (Aurangabad) Municipal Corporation vide. Acknowledgement no. 121/2025-26 dtd. 25/06/2025. The Architect has also certified that total project of 10 Buildings has been completed
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 9 Jul 2023
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form-1_Q4_25-26.pdf | 18 May 2026 |
| Withdrawal Update Form 2File: Form2_p2_Q4.pdf | 18 May 2026 |
| Withdrawal Update Form 3File: Form 3 _March 2026_signed_P2_compressed.pdf | 18 May 2026 |
| Occupational CertificateFile: LMNO_Occupancy_comprss.pdf | 18 May 2026 |
| Occupational CertificateFile: OC Q T_compress.pdf | 18 May 2026 |
| Occupational CertificateFile: OC PRSUr compress.pdf | 18 May 2026 |
| Occupational CertificateFile: Gmail - 129 01 SANTION OC POROPSAL 22042026.pdf | 18 May 2026 |
| Withdrawal Update Form 1File: Form-1_P2_Dec 25_Signed.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: Form-2_P2_Dec 25_Signed.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 _Dec 2025_signed_opt.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: FORM-1.pdf | 9 Dec 2025 |
| Withdrawal Update Form 1File: Form 1_Sept 2025_P2_Signed.pdf | 9 Dec 2025 |
| Withdrawal Update Form 2File: Form-2 Sai Plaza PH-II_Signed (2).pdf | 9 Dec 2025 |
| Withdrawal Update Form 2File: Form-2 Sai Plaza PH-II_Signed (2).pdf | 9 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Sept 25_Signed_compressed.pdf | 9 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Sept 25_Signed_compressed.pdf | 9 Dec 2025 |
| Withdrawal Update Form 1File: FORM-1.pdf | 17 Sep 2025 |
| Withdrawal Update Form 2File: FORM-2 ENGINEER CERTIFICATE dt 30-06-25_Phase 2.pdf | 17 Sep 2025 |
| Withdrawal Update Form 3File: FORM-3.pdf | 17 Sep 2025 |
| Form 5 (FY 2024-2025)File: Form 2_Phase 2_24-25_Signed.pdf | 29 Jul 2025 |
| Withdrawal Update Form 1File: FORM-1 ARCHITECTURE CERTIFICATE dt_Phase 2.pdf | 24 Jul 2025 |
| Withdrawal Update Form 1File: FORM-1 ARCHITECTURE CERTIFICATE dt_Phase 2.pdf | 24 Jul 2025 |
| Withdrawal Update Form 2File: FORM-2 ENGINEER CERTIFICATE dt 30-06-25_Phase 2.pdf | 24 Jul 2025 |
| Withdrawal Update Form 2File: FORM-2 ENGINEER CERTIFICATE dt 30-06-25_Phase 2.pdf | 24 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_P2_June 25_Final.pdf | 24 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_P2_June 25_Final.pdf | 24 Jul 2025 |
| Form 1File: FORM-1 ARCH_CERT_MAR 2025.pdf | 20 Jul 2025 |
| Form 2File: FORM-2_P2_Mar 2025.pdf | 20 Jul 2025 |
| Form 3File: Form 3_P2_Mar 2025_Signed.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure regarding sold booked inventory_Mar 25_P2.pdf | 20 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3_P2_Mar 2025.pdf | 17 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCH_CERT_MAR 2025.pdf | 14 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2_P2_Mar 2025.pdf | 14 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_2023-24.pdf | 21 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_2023-24.pdf | 21 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCH_CERT_Dec 2024.pdf | 31 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3_Dec 2024_Signed_opt.pdf | 31 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2_P2_Dec 2024.pdf | 31 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCH_CERT_Sept 2024_opt.pdf | 29 Jan 2025 |
| Certificates of CA (Form 3)File: June Scanned Form 3_P2_opt.pdf | 29 Jan 2025 |
| Certificates of CA (Form 3)File: Sept Scanned Form 3_P2_opt.pdf | 29 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_P2_June 2024_V2.pdf | 29 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_P2_June 2024_V2.pdf | 29 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_P2_Sept 2024_V2.pdf | 29 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 ARCHITECTS Certificate P_II.pdf | 24 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3_31032024_ Signed_compressed.pdf | 24 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM_1_ARCH_CERT_31032024.pdf | 22 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ENG CERT_31032024.pdf | 22 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Amrut Sai Plaza Phase 2.pdf | 9 May 2024 |
| Details of encumbrances concerned to FinanceFile: Certificate of legal encumbrances.pdf | 5 Sep 2023 |
| Details of encumbrances concerned to LegalFile: Certificate of legal encumbrances.pdf | 5 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or booked inventory_.pdf | 5 Sep 2023 |
| Certificates of CA (Form 3)File: Form-3.pdf | 5 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other Real Estate org.pdf | 5 Sep 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation report allotment letter.pdf | 5 Sep 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation model copy of agreement to sale.pdf | 5 Sep 2023 |
| CERSAI detailsFile: CERSAI_Search_Report.pdf | 4 Sep 2023 |
| Proforma of Agreement for saleFile: Proforma of ATS.pdf | 4 Sep 2023 |
| Declaration about Commencement CertificateFile: Declaration about commencement.pdf | 2 Sep 2023 |
| Declaration in FORM BFile: Form B.pdf | 2 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SASDPL_Form2A_2019-20.pdf | 2 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SASDPL_Form 2A_2020-21.pdf | 2 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SASDPL_Form 2A_2021-22.pdf | 2 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SASDPL_Form2A_2023.pdf | 2 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SASDPL_FORM-5_19-20.pdf | 2 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SASDPL_Form-5_20-21.pdf | 2 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SASDPL_Form-5_21-22.pdf | 2 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SASDPL_Form-5_22-23.pdf | 2 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_Architect Certificate.pdf | 22 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_Engineer Certificate.pdf | 22 Aug 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sai Plaza ph 2 part completion.pdf | 9 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SASDPL_Amrut Sai Plaza Phase II_Rera Audit Report FY 1819.pdf | 10 May 2020 |
| Certificates of CA (Form 5)File: Form 5 Scanned.pdf | 30 Sep 2018 |
| OtherFile: Amrut SaiPhase II Part Completion _compressed.pdf | 21 Jul 2018 |
| OtherFile: Sai Plaza ph 2 part completion.pdf | 21 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificates(Compress).pdf | 5 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 5 Aug 2017 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 5 Aug 2017 |
| Proforma of Allotment letterFile: Proforma of ATS.pdf | 5 Aug 2017 |
| Proforma of Allotment letterFile: Proforma_Allotment Letter.pdf | 5 Aug 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Amrut Sai Plaza | Railway station MIDC Padampuara | 272 | Completed | Apr 2015 | Late, Apr 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
Keep AMRUT SAI PLAZA PH 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Silk Mill Colony1,400+ in Aurangabad
Filed coordinates, straight-line distance. 72 registered projects within 2 km.
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
Nabhraj RYAN BUSINESS HUB
NABHRAJ BUILDERS AND DEVELOPERS PVT LTD
See every Aurangabad project, with the district possession charts
Builder: Shree Amrut Sai Developer Pvt.Ltd
Shree Amrut Sai Developer Pvt.Ltd has 2 registrations on MahaRERA, including AMRUT SAI PLAZA PH 2 and GOLDEN HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if AMRUT SAI PLAZA PH 2 is delayed beyond 31 Jul 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMRUT SAI PLAZA PH 2?
The registered promoter entity is Shree Amrut Sai Developer Pvt.Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMRUT SAI PLAZA PH 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AMRUT SAI PLAZA PH 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMRUT SAI PLAZA PH 2?
The professionals named in the filing: Architect: Ganesh Shriram Mharolkar; Engineer: Core Cosultants; Engineer: Prakash Uttamrao Vidhate; Chartered Accountant: M R Hundiwala & Co; Chartered Accountant: Nikhil N. Loya and Co.; Chartered Accountant: R. O. Heda & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMRUT SAI PLAZA PH 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback