Home / Browse projects / Thane, Maharashtra / Vihang Plaza - A Commecial
Vihang Plaza - A Commecial
RG-MH-25548 · RERA P51700012432 · Last updated on MahaRERA portal: 28 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vihang Plaza - A Commecial is a Commercial project by VIHANG ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700012432 on 1 Sep 2017. Possession is promised by 30 Dec 2026. 18 of the 23 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.
At a glance
Project
- NameVihang Plaza - A Commecial
- TypeCommercial
- Location
- G.B.ROAD
- BHAYNDERPADA
- Thane (M Corp.)
- Thane
- 400615
- Pincode400615
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700012432
- ReraGenie IDRG-MH-25548
Builder
- NameVIHANG ENTERPRISES
- Entity typePartnership
- GSTIN27AAAFY6459P1ZA
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersVIHANG PRATAP SARNAIK, PURVESH PRATAP SARNAIK
- Other registrations7 more →
- Completed2 of 8
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Sep 2017
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed64 files
Current status
Figures as on 28 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| COMMERCIAL BUILDING 1 | NA | 5 | 5 | 0 | 23 | 23 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
COMMERCIAL BUILDING 1: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed289
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Saakaar Architects |
| Architect | AJAY RAMESH MANE |
| Architect | ABHIJEET JAGTAP |
| Engineer | R C TIPNIS |
| Engineer | Tukaram HUMRASKAR |
| Chartered Accountant | R C Jain |
| Chartered Accountant | Lilani & Co |
| Partner | Role in project |
|---|---|
| VIHANG ENTERPRISES | - |
Litigation declared7
| Case | Court | Status |
|---|---|---|
| 556/2016 | CIVIL COURT THANE | argument of exhibit hearing |
| 640/2016 | CIVIL COURT THANE | Argument on exhibit hearing |
| 635/2016 | CIVIL COURT THANE | Exhibit hearing |
| 592/2012 | REVISION BEFORE ADD COMMISSIONER KONKAN DIVISION THANE | DISPOSED |
| 518/2005 | CIVIL COURT THANE | PROJECT SURVEY NUMBERS ARE DELETED FROM THE SUIT |
| 217/2013 | DISTRICT COURT THANE | DISPOSED |
| 636/2018 | THANE CIVIL JUDGE SENIOR DIVISION | Issues |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed64
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect certificate from 1 - 07-04-2023.pdf | 28 May 2026 |
| Withdrawal Update Form 2File: engineer certificate from-2 - plaza A - 31-03-2023.pdf | 28 May 2026 |
| Withdrawal Update Form 3File: FORM 3 - VIHANG PLAZA A COMMERCIAL_compressed.pdf | 28 May 2026 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B PLAZA A COMMERCIAL.pdf | 15 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 PLAZA COMMERCIAL MARCH 25.pdf | 12 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 20-21.pdf | 8 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 8 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf | 8 Apr 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 10593.pdf | 5 Feb 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPARATE BANK ACCOUNT VIHANG PLAZA.pdf | 5 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE VIHANG PLAZA COMMERCIAL A.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 commercial plaza APRIL 2024.pdf | 23 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 commercial plaza SEPT 2024.pdf | 23 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Plaza A Form 2 Mar 24_compressed.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD- UNSOLD.pdf | 7 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - VIHANG PLAZA A COMMERCIAL.pdf | 7 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate from 1 - 07-04-2023.pdf | 5 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate from 2- plaza A 31-03-2022.pdf | 5 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate from-2 - plaza A - 31-03-2023.pdf | 5 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: from 2A - QUALITY ASSURANCES Date 30-03-2020.pdf | 5 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: from 2a- quality assurances 30-03-2021.pdf | 5 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: from 2a- quality assurances 30-03-2022.pdf | 5 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: from 2A Quality assurancces 30-03-2023.pdf | 5 Jun 2024 |
| Declaration about Commencement CertificateFile: DECLARATION OF COMMENCEMENT CERTIFICATE.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: Form 3 (2024).pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: FORM 3 - VIHANG PLAZA A COMMERCIAL_compressed.pdf | 4 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - VIHANG PLAZA A COMMERCIAL.pdf | 4 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A - SEPARATE BANK ACCOUNT VIHANG PLAZA A COMMERCIAL.pdf | 4 Jun 2024 |
| Proforma of Agreement for saleFile: WOODS FSA-NEW CUSTOMER-Shop No.pdf | 3 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT-2023.pdf | 1 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT-2022.pdf | 1 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEERS 2A-2020.pdf | 1 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEERS 2A-2021.pdf | 1 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEERS 2A-2022.pdf | 1 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEERS 2A-2023.pdf | 1 Jun 2024 |
| CERSAI detailsFile: Cersai Report.pdf | 1 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23.pdf | 1 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-MARCH 2022.pdf | 31 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate Mar 21.pdf | 31 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERING CERTIFICATE -MARCH 2022.pdf | 31 May 2024 |
| Certificates of CA (Form 3)File: FORM-3-MARCH 2022.pdf | 31 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT- 0401001010593 - PLAZA -A- COMMERCIAL.pdf | 28 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate letter for Bank Account - Plaza A Commercial.pdf | 28 May 2024 |
| Certificates of CA (Form 5)File: vihang plaza A form 5.pdf | 21 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: PLAZA COMMENCEMENT CERTIFICATE 02-02-2018-i.pdf | 12 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PLAZA- A- ARCHITECT CERT 25-09-2017.pdf | 30 Sep 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PLAZA- A- ENGINEER CERT 12-07-2017.pdf | 30 Sep 2017 |
| OtherFile: Rera Area Achitect certificate PLAZA- A- 27-09-2017.pdf | 30 Sep 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTICICATE A BUILDING.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: RERA - CA CERTIFICATE PLAZA COMMERCIAL A.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: PLAZA- UNDERTAKING.pdf | 29 Jul 2017 |
| Building plan approvalFile: COMMENCEMENT CERTIFICATE- PLAZA- GODREJ- 30-03-2017-.pdf | 28 Jul 2017 |
| Layout approvalFile: layout of plaza.pdf | 28 Jul 2017 |
| PAN CardFile: pan card-vihang enterprises.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE-VIHANG PLAZA.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE-221-8.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE-219-2A.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE 102-1,3,2B.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: non encumberance certificate-plaza.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: layout of plaza.pdf | 28 Jul 2017 |
| Building Plan Approval (IOD)File: COMMENCEMENT CERTIFICATE- PLAZA- GODREJ- 30-03-2017-.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: Form-B - Plaza.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PLAZA-engineer Certificate - A Building.pdf | 28 Jul 2017 |
| OtherFile: surveyor - plaza- certificate-27-07-2017.pdf | 28 Jul 2017 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| NOVA D-1P51700032331 | BHAYNDERPADA, THANE, Thane | - | Dec 2021 | Ongoing | Dec 2028Registered original: Dec 2026 | Not due yet |
| vihang woodsP51700005038 | BHAYNDERPADA, Thane | 59 | Aug 2017 | Ongoing | Dec 2026 | Not due yet |
| GOLDEN HILLS B- 3P51700020730 | BHAYENDERPADA, Thane | - | May 2019 | Completed | Dec 2024 | Late, Dec 2024 |
| VIHANGS VERMONTP51700001458 | BHAYNDERPADA, Thane | - | Jul 2017 | Completed | Dec 2022 | Dec 2021 |
| VIHANG HILLSP51700007590 | Thane (M Corp.), Thane | - | Aug 2017 | Completed | Dec 2018 | Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 64 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Vihang Plaza - A Commecial on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHAYNDERPADA7,600+ in Thane
Filed coordinates, straight-line distance. 158 registered projects within 2 km.
Godrej Emerald Thane
Godrej Greenview Housing Private Limited
NORTH IMPERIAL GREENS -TOWER 2
Skylark Buildspace Private Limited
VIHANG MARINA
BALAJI ENTERPRISES
Puranik City Reserva Phase 1
Puranik Builders Limited
NORTH IMPERIAL GREENS - TOWER 1
Skylark Buildspace Private Limited
RAUNAK 108
UNNATHI ASSOCIATES
See every Thane project, with the district possession charts
Builder: VIHANG ENTERPRISES
VIHANG ENTERPRISES has 8 registrations on MahaRERA, including VIHANGS VERMONT and Vihang Plaza - A Commecial. Its filings disclose 6 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Vihang Plaza - A Commecial is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vihang Plaza - A Commecial?
The registered promoter entity is VIHANG ENTERPRISES, a partnership as per the filing. Its GSTIN 27AAAFY6459P1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vihang Plaza - A Commecial?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Vihang Plaza - A Commecial?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vihang Plaza - A Commecial?
The professionals named in the filing: Architect: Saakaar Architects; Architect: AJAY RAMESH MANE; Architect: ABHIJEET JAGTAP; Engineer: R C TIPNIS; Engineer: Tukaram HUMRASKAR; Chartered Accountant: R C Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vihang Plaza - A Commecial?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback