ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / VIHANG MARINA

Registered Litigation declared Residential / Group Housing project

VIHANG MARINA

By BALAJI ENTERPRISES

RG-MH-40253 · RERA P51700034747 · Last updated on MahaRERA portal: 13 Jun 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
5 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 70%
984 of 984Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

VIHANG MARINA is a Residential / Group Housing project by BALAJI ENTERPRISES in Thane, Maharashtra, registered with MahaRERA as P51700034747 on 28 Apr 2022. Possession is promised by 31 Dec 2029. 0 of the 984 units on this registration are recorded sold or booked, and 5 of 22 construction stages are filed complete.

At a glance

Project

  • NameVIHANG MARINA
  • TypeResidential / Group Housing
  • Location
    • GHODBUNDER ROAD
    • BHAYENDERPADA
    • Chavindra
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700034747
  • ReraGenie IDRG-MH-40253

Builder

  • NameBALAJI ENTERPRISES
  • Entity typePartnership
  • PartnerVIHANG PRATAP SARNAIK
  • Other registrations10 more →
  • Completed3 of 11
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2022PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2022
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed60 files

Current status

0%0 of 984 units booked

Figures as on 13 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA28254780478
BUILDING BNA272349313506

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 70%.

BUILDING A6%
ActivityProgress
Excavation70%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING B46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed290

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots290
Closed/Covered290

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area14,220 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2026
LandownerVillageDistrict
SMT. YENABAI HALYA BHOIRThane (M Corp.)Thane
YENABAI HALYA BHOIRThane (M Corp.)Thane
SUMATI GOVIND TANGDIThane (M Corp.)Thane
KAPIL MAHENDRA SHARMAThane (M Corp.)Thane
SANGEETA ASHOK PATILThane (M Corp.)Thane
BALAJI ENTERPRISESThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI47677.1
Proposed, not sanctioned47,677 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNAUPADA THANE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHIJEET JAGTAP
EngineerTUKARAM HAMRASKAR
Chartered AccountantLILANI & CO
PartnerRole in project
BALAJI ENTERPRISES-

Litigation declared4

CaseCourtStatus
518/2005THANE CIVIL COURTEXHIBIT HEARING
1564/2012THANE CIVIL COURTSUIT IS DISPOSED AS WITHDRAWN
RTS 2722- No- 310- J-4/2022REVENUE MINISTER MANTRALAYAFOR REPLY
518/2005thane civil courtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration about all RERA Designated Bank Accounts (Format A)File: BALAJI-RERA FORMAT4 - COSMOS.pdf13 Jun 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: format B.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Marina MARCH 25.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 June 2024 marina.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Sept 2024 Marina.pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 dec 2024 marina.pdf15 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: SEPARATE BANK ACCOUNT VIHANG MARINA.pdf10 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 12537.pdf10 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE MARINA A B.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: marina FORM 2 june 2024.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: marina FORM 2 December 2024.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: marina FORM 2 sept 2024.pdf31 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: marina form 2a december 2024.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BALAJI FORM 3 Mar 2023.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BALAJI FORM 3 Mar 2024.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Marina JUNE 2024.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 marina SEPT 2024.pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2023 Marina.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2024 marina.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 1 2023 Marina.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Balaji Form 2 MAr 24_compressed.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: BALAJI - Form 5 Mar 2023_compressed.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: BALAJI - Form 5 Mar 24_compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer 2023.pdf1 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEERS Form 2A - 2023.pdf1 Jun 2024
Proforma of Agreement for saleFile: FINAL FSA - MARINA- date 15-05-2024- DRAFT.pdf15 May 2024
Other - LegalFile: NIHAMIT DIWANI DAVA-1564-12_compressed (1)_compressed_Part1.pdf30 Nov 2023
Other - LegalFile: NIHAMIT DIWANI DAVA-1564-12_compressed (1)_compressed_Part2.pdf30 Nov 2023
Other - LegalFile: NIHAMIT DIWANI DAVA-1564-12_compressed (1)_compressed_Part3.pdf30 Nov 2023
Other - LegalFile: NIHAMIT DIWANI DAVA-1564-12_compressed (1)_compressed_Part4.pdf30 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: AMENDED C C MARINA 25-04-2023.pdf26 Apr 2023
Copy of the legal title reportFile: SUPPLIMENTARY TITLE CERTIFICATE 18-02-2023_compressed.pdf18 Feb 2023
Details of encumbrances concerned to FinanceFile: Reviewl Application -RTS 2722- PRA -KRA 310- J 4 - REVENUE MINI.pdf18 Feb 2023
Details of encumbrances concerned to FinanceFile: case status - Reg Civil Suit 1564-2012 date 02-02-2023.pdf18 Feb 2023
Details of encumbrances concerned to LegalFile: Reviewl Application -RTS 2722- PRA -KRA 310- J 4 - REVENUE MINI.pdf18 Feb 2023
Details of encumbrances concerned to LegalFile: case status - Reg Civil Suit 1564-2012 date 02-02-2023.pdf18 Feb 2023
Other - LegalFile: Marina- allotment letter for flat distribution-.pdf22 Jul 2022
Layout approvalFile: layout.pdf27 Apr 2022
Building plan approvalFile: A building ground floor plan.pdf27 Apr 2022
Building plan approvalFile: A building typical floor plan.pdf27 Apr 2022
Building plan approvalFile: B building Ground floor.pdf27 Apr 2022
Building plan approvalFile: B building Typical floor.pdf27 Apr 2022
Building plan approvalFile: B building 23rd floor.pdf27 Apr 2022
Copy of Layout Approval (in case of layout)File: layout.pdf27 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: A building ground floor plan.pdf27 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: A building typical floor plan.pdf27 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: B building Ground floor.pdf27 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: B building Typical floor.pdf27 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: B building 23rd floor.pdf27 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Percentage of construction.pdf27 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate.pdf27 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf27 Apr 2022
PAN CardFile: BALAJI ENTERPRISES PAN CARD -1_compressed.pdf26 Apr 2022
Copy of the legal title reportFile: Legal Title Report - 26-04-2022 - Vihang Marina_compressed.pdf26 Apr 2022
Details of encumbrancesFile: NON ENCUMBERANCE CERTIFICATE.pdf26 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: CC Marina Balaji Enterprises Dated-25-4-2022_compressed.pdf26 Apr 2022
Declaration about Commencement CertificateFile: DECLARATION FOR COMMENCEMENT CERTIFICATE.pdf26 Apr 2022
Declaration in FORM BFile: AFFIDAVIT CUM DECLLARATION.pdf26 Apr 2022
CERSAI detailsFile: UNDERTAKING CERSAI.pdf26 Apr 2022
Proforma of Allotment letterFile: UNDERTAKING.pdf26 Apr 2022

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIHANG MARINA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHAYENDERPADA7,600+ in Thane

2 kmVIHANG MARINACompleted 33Lapsed / revoked 8Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 64 registered projects within 2 km.

Builder: BALAJI ENTERPRISES

BALAJI ENTERPRISES has 11 registrations on MahaRERA, including KRUSHNA SHANTI APARTMENT A WING and ADITYA APPARTMENT. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if VIHANG MARINA is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIHANG MARINA?

The registered promoter entity is BALAJI ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIHANG MARINA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIHANG MARINA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIHANG MARINA?

The professionals named in the filing: Architect: ABHIJEET JAGTAP; Engineer: TUKARAM HAMRASKAR; Chartered Accountant: LILANI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIHANG MARINA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIHANG MARINA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIHANG MARINA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.