Registered Litigation declared Residential / Group Housing project

Vaikunth Cluster 3 T1

By PEPL Developers Pvt Ltd

RG-MH-22889 · RERA P51700024023 · Last updated on MahaRERA portal: 30 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 8 cases
  • 8 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 1,170.00 crore secured on the land, in favour of hdfc bank

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 12 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 99%
58 of 557Units unsoldnot recorded sold or booked
8Complaints at MahaRERAon this registration
Jump to the 150 documents Report an error

Vaikunth Cluster 3 T1 is a Residential / Group Housing project by PEPL Developers Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as P51700024023 on 14 Jan 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 12 months from the original filing. 499 of the 557 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 8 complaints are on record with the regulator.

At a glance

Project

  • NameVaikunth Cluster 3 T1
  • TypeResidential / Group Housing
  • Location
    • Balkum road
    • Thane
    • Thane (M Corp.)
    • 400607
  • Pincode400607
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700024023
  • ReraGenie IDRG-MH-22889

Builder

  • NamePEPL Developers Pvt Ltd
  • Entity typeCompany
  • CINU17100MH1999PTC122652
  • GSTIN27AACCA7777K1Z5
  • DirectorPankaj S Mundada
  • Other registrations2 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredJan 2020First promiseJun 2026Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Jan 2020
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed150 files

Current status

90%499 of 557 units booked
74.0%Work done, per cost certificate

Figures as on 30 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VidyaNA46415570557

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

Vidya: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes94%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes0%
Street LightingYes75%
Community BuildingsYes45%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes95%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed308

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots308
Closed/Covered308

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area727 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofhdfc bank
Secured amountRs 1,170.00 crore
Declared on25 Sep 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI22690.0
Proposed, not sanctioned22,690 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC Bank Ltd, Ground Floor, Jehangir Building, M G Road, Fort, Mumbai 400001
Estimated costRs 282.27 cr
Cost incurredRs 208.87 cr
Work done74.0%
BuildingWingEstimatedIncurred
VidyaNARs 178.77 crRs 165.43 cr
-NARs 103.51 crRs 43.45 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectScapes
EngineerCurrie & Brown Pvt Ltd
EngineerKishor Parmar
EngineerGleeds Consulting India Pvt. Ltd.
Chartered AccountantSRBC & CO LLP
Chartered AccountantD B Ketkar & Co
PartnerRole in project
PEPL Developers Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA02062621194Jun 2026 → Jun 2027

Reason as filed by the promoter1. The delay was occasioned due to the unavoidable and mandatory revision of the sanctioned plans arising from site specific constraints and compulsory compliance with statutory car parking norms, leaving the Promoter with no discretion in the matter. Such revision mandatorily required prior approval from the Ministry of Environment, Forest and Climate Change (“MoEF”), without which further construction could not legally proceed. The situation was further aggravated by the complete non functioning of the concerned MoEF Committee from January 2024 to May 2024, a circumstance wholly beyond the c

Litigation declared8

CaseCourtStatus
83/2015High Court MumbaiOngoing
RTS 2717 27 PRA KA 1 J 4/2016Before the Minister for Revenue and ForestOngoing
151/2021District Consumer Redressal Forum MumbaiClosed
25/2021Additional District Consumer Dispute Redressal Commission BelapurClosed
460/2021District Consumer Redressal ForumClosed
169/2022District Consumer Redressal Forum MumbaiClosed
55/2023Before SDO at ThaneClosed
70/2023Before TahasildarOngoing

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC006000000196333RAJESH ANKUSH GAWDEPiramal Estates Pvt. Ltd.11/03/2021
CC006000000198818K Vijay BabuPiramal Estate Private Limited29/10/2021
CC006000000251621Srisa Chandrica Raghava RaoPiramal Estate Private Limited26/06/2022
CC006000000251624Srisa Chandrica Raghava RaoPiramal Estate Private Limited26/06/2022
CC12400088Snehal Sharad BhivatePiramal Estate Private Limited13/09/2024
CC12401072HITENDRAKUMAR BHAICHANDBHAI PNCHALPiramal Estate Private Limited09/12/2024
CC12502588Tushar Dnyandeo JagdalePiramal Estate Private Limited27/07/2025
CC12600680PEPL Developers Pvt LtdSabiya Haji Rehman05/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed150

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 150 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: 00 Form 2A Vaikunth Cluster 3 T1.pdf30 Jun 2026
Withdrawal Update Form 1File: 04 Form 1 - Cluster 3 T1 Mar 26.pdf20 Apr 2026
Withdrawal Update Form 2File: 04 Form 2 - Cluster 3 T1 Mar 26.pdf20 Apr 2026
Withdrawal Update Form 3File: 04 Form 3 - Cluster 3 T1 Mar 26.pdf20 Apr 2026
Withdrawal Update Form 1File: 04 Form 1 - Cluster 3 T1.pdf20 Jan 2026
Withdrawal Update Form 2File: 04 Form 2 - Cluster 3 T1.pdf20 Jan 2026
Withdrawal Update Form 3File: 04 Form 3 - Cluster 3 T1.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1, Cluster 3 T1 - Sept 2025.pdf24 Nov 2025
Withdrawal Update Form 2File: Form 2, Cluster 3 T1 - Sept 2025.pdf24 Nov 2025
Withdrawal Update Form 3File: Form 3, Cluster 3 T1 - Sept 2025 .pdf24 Nov 2025
Form 2A (FY 2024-2025)File: Vaikunth CL3 T1.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: Cluster 3 T1.pdf30 Sep 2025
Form 1File: Form 1, Cluster 3 T1.pdf20 Jul 2025
Form 2File: Form 2, Cluster 3 T1.pdf20 Jul 2025
Form 3File: Form 3, Cluster 3 T1.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold, Cluster 3 T1.pdf20 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form _Cl3T1 Updated 2.pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form _Cl3T1 Updated.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form _Cl3T1.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Cl3T1.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1, Cl3T1_17042025171359.PDF17 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Cl3T1_17042025173050-compressed.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Piramal Vaikunth Cluster 3 T1 Form 1, December'2024.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaikunth Cluster 3T1.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Piramal Vaikunth Cl3 T1 Form 2, December'2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Piramal Vaikunth Cluster 3 T1 Sold Unsold Inventory.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Piramal Vaikunth Cl3 T1 Form 2A, December'2024.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Piramal Vaikunth_Cluster 3 T1 Form 1, Sept'2024.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Piramal Vaikunth_Cluster 3 T1 Form 3, Sept'2024.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Piramal Vaikunth_Cluster 3 T1 Form 3, June'2024.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Piramal Vaikunth_Cluster 3 T1 Form 2, Sept'2024.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Piramal Vaikunth_Cluster 3 T1 Form 2A, Sept'2024.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: 11 Piramal Vaikunth Cluster 3 T1 Sold Unsold Inventory.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Cluster 3T1 - PEPL Vaikunth mgt signed.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: V_CL3_T1_merged.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vaikunth_CL3_T1_Form 2_June 24.pdf19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Vaikunth C3 T1 Vidya March.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Vaikunth C3 T1 Vidya.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Vaikunth C3 T1 - Vidya.pdf18 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaikunth CL3 T1_Form1_June 24.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Cluster 3T1 (Vidya)_SoldUnsold.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Vaikunth CL3 T1_Form1_June 24.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 3 T1 EC.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Cluster 3 T1 CA.pdf19 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: CL-3-RERA.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CLUSTER 3 T1 AC.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: CLUSTER 3 T1 SOLD UNSOLD.pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Cluster 3T1 CA.pdf20 Jan 2024
Building plan approvalFile: Ame Per _ CC Dec 2023.pdf18 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: Ame Per _ CC Dec 2023.pdf18 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Ame Per _ CC Dec 2023.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 3 T1 EC.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Cluster 3 T1.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cluster 3 T1 AC.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 3T1.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Cluster 3 T1 CA.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 3 T1 EC.pdf19 Oct 2023
Details of encumbrancesFile: Cluster 3 T1.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cluster 3 T1 AC.pdf17 Oct 2023
Disclosure of sold/ booked inventoryFile: Cluster 3 T1 Sold Unsold.pdf17 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: CLUSTER 3 T1 QA.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Cluster 3 T1.pdf29 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 3 T1 EC.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Vaikunth CL3 T1.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vaikunth Cluster 3 T1.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Vaikunth Cluster 3 T1.pdf14 Jul 2023
Disclosure of sold/ booked inventoryFile: Vaikunth Cluster 3 T1.pdf13 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CL 3 T1.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CL 3 T1.pdf20 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CL 3 T1.pdf14 Apr 2023
Disclosure of sold/ booked inventoryFile: Cl 3 T1.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: vaikunth CL 3 T1 2A Mar 23.pdf12 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: CHS Vaikunth CL 3 T1.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Vaikunth CL3 T1.pdf16 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QA_Vaikunth CL-3-T-1.pdf16 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert Vaikunth CL3 T1.pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Vaikunth CL3 T1.pdf14 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 3 T1.pdf13 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Vaikunth -cl-3-T-1.pdf19 Oct 2022

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Vaikunth Cluster 3 Tower 2P51700024580Thane, Thane635Feb 2020OngoingJun 2026Not delivered
Vaikunth Cluster 2P51700003793Thane West, Thane-Aug 2017CompletedDec 2024Dec 2024
Vaikunth Cluster 4AP51700005256Balkum, Thane-Aug 2017CompletedJul 2024Jul 2024
Vaikunth Cluster 4P51700003283Thane West, Thane-Aug 2017Certificate SignedDec 2023Dec 2023
Vaikunth Cluster 1P51700003535Thane West, Thane-Aug 2017CompletedDec 2022Dec 2022

How this compares with Thane

90%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Vaikunth Cluster 3 T1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane7,600+ in Thane

2 kmVaikunth Cluster 3 T1Completed 97Lapsed / revoked 70Other 131Dot size: filed unitsN

Filed coordinates, straight-line distance. 298 registered projects within 2 km.

Builder: PEPL Developers Pvt Ltd

PEPL Developers Pvt Ltd has 3 registrations on MahaRERA, including Vaikunth Cluster 3 T1 and Vaikunth Cluster 3 Tower 2. Its filings disclose 6 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Vaikunth Cluster 3 T1 is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Vaikunth Cluster 3 T1?

The registered promoter entity is PEPL Developers Pvt Ltd, a company as per the filing. Its CIN U17100MH1999PTC122652 and GSTIN 27AACCA7777K1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Vaikunth Cluster 3 T1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Vaikunth Cluster 3 T1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Vaikunth Cluster 3 T1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Vaikunth Cluster 3 T1?

The professionals named in the filing: Architect: Scapes; Engineer: Currie & Brown Pvt Ltd; Engineer: Kishor Parmar; Engineer: Gleeds Consulting India Pvt. Ltd.; Chartered Accountant: SRBC & CO LLP; Chartered Accountant: D B Ketkar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vaikunth Cluster 3 T1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vaikunth Cluster 3 T1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vaikunth Cluster 3 T1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.