CIN U17100MH1999PTC122652 · GSTIN 27AACCA7777K1Z5 · Company · attribution by exact filing name, entity resolution in progress

PEPL Developers Pvt Ltd has 3 registrations in this build, including Vaikunth Cluster 3 T1 and Vaikunth Cluster 3 Tower 2. Its filings disclose 6 earlier MahaRERA projects: 4 of 4 past projects completed on time. Litigation is declared on 3 of its registrations.

3Registrations in this build
6Past projects disclosed
on timeMedian delivery slip
3Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Vaikunth Cluster 3 T1Thane, Maharashtra55790%Registered
Vaikunth Cluster 3 Tower 2Thane, Maharashtra63590%Registered
Vaikunth Cluster 3 Tower 3Thane, Maharashtra3430%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Vaikunth Cluster 1
P51700003535
30 Dec 202230 Dec 2022On time
Vaikunth Cluster 4
P51700003283
30 Dec 202330 Dec 2023On time
Vaikunth Cluster 4A
P51700005256
31 Jul 202431 Jul 2024On time
Vaikunth Cluster 2
P51700003793
30 Dec 202430 Dec 2024On time
Vaikunth Cluster 3 Tower 2
P51700024580
30 Jun 2026Not completed yetOngoing
Vaikunth Cluster 3 T1
P51700024023
30 Jun 2026Not completed yetOngoing

Frequently asked questions

How do I verify PEPL Developers Pvt Ltd as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U17100MH1999PTC122652 and GSTIN 27AACCA7777K1Z5 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with PEPL Developers Pvt Ltd?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make PEPL Developers Pvt Ltd unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.