Home / Browse projects / Nashik, Maharashtra / Samraat AmOzon
Samraat AmOzon
By M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
RG-MH-34405 · RERA P51600023135 · Last updated on MahaRERA portal: 18 Apr 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Samraat AmOzon is a Others project by M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. in Nashik, Maharashtra, registered with MahaRERA as P51600023135 on 2 Dec 2019. The registration is recorded completed; possession was promised by 28 Nov 2025. The completion date has moved by 12 months from the original filing. 395 of the 528 units on this registration are recorded sold or booked, and 170 of 187 construction stages are filed complete.
At a glance
Project
- NameSamraat AmOzon
- TypeOthers
- Location
- Gangapur Road
- Serene Meadows
- Aanandwali
- Nashik
- 422013
- Pincode422013
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600023135
- ReraGenie IDRG-MH-34405
Builder
- NameM/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
- Entity typeCompany
- CINU55100MH2005PTC155493
- GSTIN27AAJCS4306F1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorSujoy Jayant Gupta
- DirectorSUDHIR CHANDRAKANT METKAR
- Other registrations14 more →
- Completed8 of 15
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on2 Dec 2019
- Promised completion28 Nov 2025
- Revised completionRevised to 28 Nov 2025 (originally 29 Nov 2024)
- Buildings17 building records
- Documents filed308 files
Current status
Figures as on 18 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A - Wing A1 | NA | 9 | 7 | 28 | 6 | 34 |
| Building A - Wing A2 | NA | 9 | 7 | 27 | 6 | 33 |
| Building A - Wing A3 | NA | 9 | 7 | 30 | 4 | 34 |
| Building A - Wing A4 | NA | 9 | 7 | 28 | 7 | 35 |
| Building A - Wing A5 | NA | 9 | 7 | 28 | 5 | 33 |
| Building A - Wing A6 | NA | 8 | 7 | 0 | 9 | 9 |
| Building B - Wing B1 | NA | 9 | 7 | 28 | 7 | 35 |
| Building B - Wing B2 | NA | 9 | 7 | 28 | 5 | 33 |
| Building B - Wing B3 | NA | 9 | 7 | 28 | 7 | 35 |
| Building B - Wing B4 | NA | 9 | 7 | 28 | 5 | 33 |
| Building B - Wing B5 | NA | 9 | 7 | 28 | 6 | 34 |
| Building C - Wing C1 | NA | 9 | 7 | 30 | 0 | 30 |
| Building C - Wing C2 | NA | 9 | 7 | 30 | 0 | 30 |
| Building C - Wing C3 | NA | 9 | 7 | 30 | 0 | 30 |
| Building C - Wing C4 | NA | 9 | 7 | 30 | 0 | 30 |
| Building D - Wing D1 | NA | 9 | 7 | 30 | 0 | 30 |
| Building D - Wing D2 | NA | 9 | 7 | 30 | 0 | 30 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building17
As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
170 of 187 construction stages are filed complete across 17 buildings. The stage furthest along is Podiums (if any), at 0%.
Building A - Wing A191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A - Wing A291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A - Wing A391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A - Wing A491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A - Wing A591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A - Wing A691%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B - Wing B191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B - Wing B291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B - Wing B391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B - Wing B491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B - Wing B591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C - Wing C191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C - Wing C291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C - Wing C391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C - Wing C491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building D - Wing D191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building D - Wing D291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed434
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A - Wing A1 | 28 | 0 | 28 |
| Building A - Wing A2 | 28 | 0 | 28 |
| Building A - Wing A3 | 28 | 0 | 28 |
| Building A - Wing A4 | 28 | 0 | 28 |
| Building A - Wing A5 | 28 | 0 | 28 |
| Building B - Wing B1 | 28 | 0 | 28 |
| Building B - Wing B2 | 28 | 0 | 28 |
| Building B - Wing B3 | 28 | 0 | 28 |
| Building B - Wing B4 | 28 | 0 | 28 |
| Building B - Wing B5 | 1 | 1 | 2 |
| Building C - Wing C1 | 30 | 0 | 30 |
| Building C - Wing C2 | 30 | 0 | 30 |
| Building C - Wing C3 | 30 | 0 | 30 |
| Building C - Wing C4 | 30 | 0 | 30 |
| Building D - Wing D1 | 30 | 0 | 30 |
| Building D - Wing D2 | 30 | 0 | 30 |
Land and ownership11
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mohammad Saheb Bhauddin Khatib | Nashik | Nashik |
| Chiraguddin Mohammad Saheb Khatib | Nashik | Nashik |
| Atiq Chiraguddin Khatib | Nashik | Nashik |
| Saeed Chiraguddin Khatib | Nashik | Nashik |
| Raees Chiraguddin Khatib | Nashik | Nashik |
| Zaheer Chiraguddin Khatib | Nashik | Nashik |
| Shakil Nijamuddin Khatib | Nashik | Nashik |
| Shekhan Amiruddin Khatib | Nashik | Nashik |
| Sabir Muniroddin Khatib | Nashik | Nashik |
| Isamoddin Muniroddin Khatib alias Hisamoddin | Nashik | Nashik |
| Gulam Dastagir Shijauddin Khatib | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building A - Wing A1 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building A - Wing A2 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building A - Wing A3 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building A - Wing A4 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building A - Wing A5 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building A - Wing A6 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building B - Wing B1 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building B - Wing B2 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building B - Wing B3 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building B - Wing B4 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building B - Wing B5 | NA | Rs 72.38 cr | Rs 79.46 cr |
| Building C - Wing C1 | NA | Rs 72.38 cr | Rs 79.46 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar. Sumit Kumath and Associates |
| Architect | AR AMOL CHAUDHARI |
| Engineer | SUDHIR CHANDRAKANT METKAR |
| Engineer | BHUSHAN GANDHI |
| Engineer | vikram endait |
| Chartered Accountant | A K CHORDIA & ASSOCIATES |
| Chartered Accountant | SPARC AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project ‘SAMRAAT AMOZON’ (“SAID PROJECT”) which is registered under RERA registration no. P51600020657 which consist of Building A (Wing A1, Wing A2, Wing A3, Wing A4, Wing A5 & Wing A6), Building B (Wing B1, Wing B2, Wing B3, Wing B4 & Wing B5), Building C (Wing C1, Wing C2, Wing C3 & Wing C4) and Building D (Wing D1 & D2). It is pertinent to mention that we have already completed Building A, B and D in the said Project with necessary compliances. We have obtained Part Completion Certificate from Nashik Municipal Corporation vide Certificate No. Outward No./N.Ni.Vi./319/31443/2023 dated 2
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Apr 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Jul 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 11 Oct 2024
Documents filed308
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 308 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM I Q-IV -2025.pdf | 18 Apr 2026 |
| Form 2File: FORM II Q-IV.pdf | 18 Apr 2026 |
| Form 3File: Form III Q4.pdf | 18 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Q4 Amazon 2024-25.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: AMO FORM 1 Q1.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: AMO FORM 1 Q2.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: AMO FORM 1 Q1.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: AMO FORM 1 Q2.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: AMO FORM 1 Q3.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Q1-Jun 2025 Amozon.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Q2-SEP 2025 Amozon.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Q1-Jun 2025 Amozon.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Q2-SEP 2025 Amozon.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Q3-DEC 2025 Amozon.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: AMO Q1 25-26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Samraat Amozon Q2 July - Sept 2025.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: AMO Q1 25-26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Samraat Amozon Q2 July - Sept 2025.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: RERA Form 3 Amozon Q3 FY 2025-26.pdf | 18 Apr 2026 |
| Form 2A (FY 2019-2020)File: FORM 2A - 2019-2020.pdf | 18 Apr 2026 |
| Form 2A (FY 2020-2021)File: FORM IIA 2020-2021.pdf | 18 Apr 2026 |
| Form 2A (FY 2021-2022)File: FORM IIA 2021-2022.pdf | 18 Apr 2026 |
| Form 2A (FY 2022-2023)File: FORM IIA 2022-2023.pdf | 18 Apr 2026 |
| Form 2A (FY 2023-2024)File: FORM IIA 2023-2024.pdf | 18 Apr 2026 |
| Form 2A (FY 2024-2025)File: FORM IIA 2024-2025.pdf | 18 Apr 2026 |
| Form 2A (FY 2025-2026)File: RERA from 2A - 2025-2026.pdf | 18 Apr 2026 |
| Form 5 (FY 2025-2026)File: Signed Samraat Amozon Form 5 FY 2024-25.pdf | 18 Apr 2026 |
| Form 5 (FY 2024-2025)File: Signed Samraat Amozon Form 5 FY 2024-25.pdf | 18 Apr 2026 |
| Form 5 (FY 2019-2020)File: FORM V 30092021.pdf | 18 Apr 2026 |
| Form 1File: FORM I 01072023.pdf | 15 Nov 2025 |
| Form 2File: FORM II 06072023.pdf | 15 Nov 2025 |
| Form 3File: FORM III 24062023.pdf | 15 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 SoldUnsold Inventory 30062023.pdf | 15 Nov 2025 |
| OthersFile: FORM IIA 13032023.pdf | 15 Nov 2025 |
| Form 1File: FORM I 01102023.pdf | 15 Nov 2025 |
| Form 2File: FORM II 05102023.pdf | 15 Nov 2025 |
| Form 3File: FORM III 06102023.pdf | 15 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 SoldUnsold Inventory 31122023.pdf | 15 Nov 2025 |
| Form 1File: FORM I 02102024.pdf | 15 Nov 2025 |
| Form 2File: FORM II 05012024.pdf | 15 Nov 2025 |
| Form 3File: FORM III 11032024.pdf | 15 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 SoldUnsold Inventory 30092024.pdf | 15 Nov 2025 |
| Form 1File: FORM I 01042024.pdf | 15 Nov 2025 |
| Form 2File: FORM II 30062024.pdf | 15 Nov 2025 |
| Form 3File: FORM III 11112024.pdf | 15 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 SoldUnsold Inventory 30092024.pdf | 15 Nov 2025 |
| Form 1File: FORM I 01072024.pdf | 15 Nov 2025 |
| Form 2File: FORM II 30092024.pdf | 15 Nov 2025 |
| Form 3File: FORM III 14112024.pdf | 15 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 11 SoldUnsold inventory 30112024.pdf | 15 Nov 2025 |
| Form 1File: FORM I 28102024.pdf | 15 Nov 2025 |
| Form 2File: FORM II 31122024.pdf | 15 Nov 2025 |
| Form 3File: FORM III 17122024.pdf | 15 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 12 SoldUnsold Inventory 31122024.pdf | 15 Nov 2025 |
| Form 1File: FORM I 05012022.pdf | 13 Nov 2025 |
| Form 2File: FORM II 31032022.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 SoldUnsold inventory 31032022.pdf | 13 Nov 2025 |
| OthersFile: FORM IIA 14032022.pdf | 13 Nov 2025 |
| Form 3File: FORM III 13092022.pdf | 13 Nov 2025 |
| Form 1File: FORM I 02042022.pdf | 13 Nov 2025 |
| Form 2File: FORM II 30062022.pdf | 13 Nov 2025 |
| Form 3File: FORM III 13092022.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 4 SoldUnsold Inventory 30062022.pdf | 13 Nov 2025 |
| OthersFile: FORM IIA 13062022.pdf | 13 Nov 2025 |
| Form 1File: FORM I 04072022.pdf | 13 Nov 2025 |
| Form 2File: FORM II 30092022.pdf | 13 Nov 2025 |
| Form 3File: FORM III 13092022.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 5 SoldUnsold Inventory 30092022.pdf | 13 Nov 2025 |
| OthersFile: FORM IIA 13092022.pdf | 13 Nov 2025 |
| Form 1File: FORM I 30092022.pdf | 13 Nov 2025 |
| Form 2File: FORM II 31122022.pdf | 13 Nov 2025 |
| Form 3File: FORM III 13092022.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 SoldUnsold inventory 31122022.pdf | 13 Nov 2025 |
| OthersFile: FORM IIA 13122022.pdf | 13 Nov 2025 |
| Form 1File: FORM I 02012023.pdf | 13 Nov 2025 |
| Form 2File: FORM II 02042023.pdf | 13 Nov 2025 |
| Form 3File: FORM III 22022023.pdf | 13 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 SoldUnsold Inventory 31032023.pdf | 13 Nov 2025 |
| OthersFile: FORM IIA 13032023.pdf | 13 Nov 2025 |
| Form 1File: FORM I 01042023.pdf | 13 Nov 2025 |
Promoter's earlier projects14
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Samraat Apna Ghar Phase-IIP51600020657 | Someshwar Satpur Link Road Near DJ Reva Meadows, Nashik | - | Apr 2019 | Completed | Dec 2023 | Late, Jan 2025 |
| Samraat Apna Ghar Phase-IP51600020299 | Someshwar -Satpur link Road near DJ Reva Meadows, Nashik | - | Apr 2019 | Completed | Jun 2023 | Nov 2022 |
| Samraat Symphony Project 02 | IndiraNagar Nashik Maharashtra | 28 | - | Completed | Dec 2019 | Mar 2019 |
| Samraat Gokuldham Project 01 | Hirawadi Mumbai Agra Highway 422003 Nashik Maharashtra | 241 | - | Completed | Dec 2019 | Oct 2018 |
| Samraat Vrindavan | Om Nagar Opp Swami Narayan temple Mumbai-Agra Highway Nashik 422003 | 240 | - | Completed | Mar 2017 | Late, Jun 2017 |
| Signature | Serene Meadows Gangapur Road Anandwali Nashik 422013 | 60 | - | Completed | Dec 2016 | Late, Jun 2017 |
| Samraat Symphony Project 03 | NAGARE NAGAR BEHIND SEVEN HEAVEN HOTEL MUMBAI-AGRA HIGHWAY Nashik 422009 | 112 | - | Completed | Dec 2016 | Late, Jul 2017 |
| Samraat Symphony Project 01 | Nagare Nagar behind Seven Heaven Hotel MubaiAgra Road Nashik 422009 | 84 | - | Completed | Dec 2016 | Late, Jul 2017 |
| Samraat Tropicano 01 | Serene Meadows Gangapur Road Anandwali Nashik 422013 | 460 | - | Completed | Oct 2016 | Late, Jul 2017 |
| Dream Grandeur | Matoshri Nagar Tidke Colony Nashik 422002 | 16 | - | Completed | Jun 2012 | Late, Nov 2012 |
| Dream Nest | Near Ryan International School Old Wadala Road Nashik 422006 | 104 | - | Completed | Mar 2012 | Late, May 2012 |
| Dream Villaas | Ganesh baba Nagar Nashik-Pune Highway Nashik 422011 | 56 | - | Completed | Dec 2011 | Late, Mar 2012 |
| Dream Castle | Madhuban Colony Makhamalabad Road Panchavati Nashik 422003 | 106 | - | Completed | Dec 2010 | Late, Apr 2011 |
| Dream Flower | Nashik-Pune Highway Opposite Inox MultiPlex Nashik 422006 | 94 | - | Completed | Nov 2010 | Late, Mar 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 308 filed documents as one ZIP, foldered, with a manifest
Keep Samraat AmOzon on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Serene Meadows4,100+ in Nashik
Filed coordinates, straight-line distance. 98 registered projects within 2 km.
ELYSIAN
ROONGTA HOMES LLP
HAPPY LIFE AT APNA GHAR PHASE III
M/S Shweta Infrastructure & Housing (I) Pv
SKY53
SKY53
ROONGTA ROSEWOOD APARTMENT
SHREE TIRUMALA BUILDCON
ROONGTA EMINENCE APARTMENT
SHREE TIRUMALA BUILDCON
SAISHRUSHTI
JAY DEVELOPERS
See every Nashik project, with the district possession charts
Builder: M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. has 15 registrations on MahaRERA, including Samraat Nucleus - Project 01 and Samraat Gokuldham Project 01. Its filings disclose 14 earlier MahaRERA projects: declares 3 of 14 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Samraat AmOzon is delayed beyond 28 Nov 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Samraat AmOzon?
The registered promoter entity is M/S Shweta Infrastructure & Housing (I) Pvt. Ltd., a company as per the filing. Its CIN U55100MH2005PTC155493 and GSTIN 27AAJCS4306F1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Samraat AmOzon?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Samraat AmOzon?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Samraat AmOzon?
The professionals named in the filing: Architect: Ar. Sumit Kumath and Associates; Architect: AR AMOL CHAUDHARI; Engineer: SUDHIR CHANDRAKANT METKAR; Engineer: BHUSHAN GANDHI; Engineer: vikram endait; Chartered Accountant: A K CHORDIA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Samraat AmOzon?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback