Samraat Apna Ghar Phase-I
By M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
RG-MH-35496 · RERA P51600020299 · Last updated on MahaRERA portal: 17 Jun 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 14 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Samraat Apna Ghar Phase-I is a Residential / Group Housing project by M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. in Nashik, Maharashtra, registered with MahaRERA as P51600020299 on 2 Apr 2019. The registration is recorded completed; possession was promised by 30 Jun 2023.
At a glance
Project
- NameSamraat Apna Ghar Phase-I
- TypeResidential / Group Housing
- Location
- CANAL ROAD
- Someshwar -Satpur link Road near DJ Reva Meadows
- Nashik
- 422013
- Pincode422013
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600020299
- ReraGenie IDRG-MH-35496
Builder
- NameM/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
- Entity typeCompany
- CINU55100MH2005PTC155493
- GSTIN27AAJCS4306F1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorSujoy Jayant Gupta
- DirectorSUDHIR CHANDRAKANT METKAR
- Other registrations14 more →
- Completed8 of 15
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on2 Apr 2019
- Promised completion30 Jun 2023
- Revised completionNone
- Buildings16 building records
- Documents filed219 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A- Wing A1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building A- Wing A2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building A- Wing A3 | NA | 9 | 0 | 0 | 0 | 0 |
| Building B- Wing B1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building B- Wing B2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building B- Wing B3 | NA | 9 | 0 | 0 | 0 | 0 |
| Building C- Wing C1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building C- Wing C2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building C- Wing C3 | NA | 9 | 0 | 0 | 0 | 0 |
| Building D- Wing D1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building D- Wing D2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building E- Wing E1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building E- Wing E2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building E- Wing E3 | NA | 9 | 0 | 0 | 0 | 0 |
| Building E- Wing E4 | NA | 9 | 0 | 0 | 0 | 0 |
| Building E- Wing E5 | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building16
As on 17 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
160 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is Podiums (if any), at 0%.
Building A- Wing A191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A- Wing A291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building A- Wing A391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B- Wing B191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B- Wing B291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B- Wing B391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C- Wing C191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C- Wing C291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building C- Wing C391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building D- Wing D191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building D- Wing D291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E- Wing E191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E- Wing E291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E- Wing E391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E- Wing E491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building E- Wing E591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed237
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building A- Wing A1 | 22 | 0 | 22 |
| Building A- Wing A2 | 7 | 0 | 7 |
| Building A- Wing A3 | 22 | 0 | 22 |
| Building B- Wing B1 | 18 | 0 | 18 |
| Building B- Wing B2 | 7 | 0 | 7 |
| Building B- Wing B3 | 18 | 0 | 18 |
| Building C- Wing C1 | 18 | 0 | 18 |
| Building C- Wing C2 | 7 | 0 | 7 |
| Building C- Wing C3 | 18 | 0 | 18 |
| Building D- Wing D1 | 18 | 0 | 18 |
| Building D- Wing D2 | 18 | 0 | 18 |
| Building E- Wing E1 | 18 | 0 | 18 |
| Building E- Wing E2 | 7 | 7 | 14 |
| Building E- Wing E3 | 7 | 0 | 7 |
| Building E- Wing E4 | 7 | 0 | 7 |
| Building E- Wing E5 | 18 | 0 | 18 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar.Sumit Kumath |
| Engineer | Mr Anil Wagh |
| Engineer | Mr Vikram Endait |
| Engineer | Mr Jayant Inamdar |
| Engineer | Mr Sudhir Metkar |
| Chartered Accountant | BCS AND ASSOCIATES LLP |
| Chartered Accountant | KALE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 14 Nov 2022
Documents filed219
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 219 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 14 Form 2A.pdf | 17 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: APG-I -RERA form 2A certificate- 17.pdf | 17 Jun 2023 |
| Status of ConveyanceFile: 001-014.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: 015-028.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: 029-042.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: 043-056.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: Apna Ghar Phase I 057-070.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: Apna Ghar Phase I 071-084.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: Apna Ghar Phase I 085-092.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: Apna Ghar Phase I 093-098.pdf | 16 Jun 2023 |
| Status of ConveyanceFile: Apna Ghar Phase I 099-106.pdf | 16 Jun 2023 |
| Proforma of Agreement for saleFile: Proforma for AFS Apna Ghar Phase I.pdf | 23 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 APN 1 02012023.pdf | 22 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 APN 1.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 APG Ph I completion.pdf | 12 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest by Directors 31012023.pdf | 26 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: APG-I -RERA form 2A certificate- 17.pdf | 4 Apr 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - APG Phase 1_ Bldg A to E (1).pdf | 11 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: APN I Q1 2223.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: APN I Q2 2223.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: APN I Q3 2223.pdf | 3 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr Cert Apna Ghar Phase I Dec 2022.pdf | 2 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Apna Ghar 1 Q4 2122.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: Apna Ghar 1 Q1 2223.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: Apna Ghar 1 Q2 2223.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: Apna Ghar I Q3 2223.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: CA Certificate Apna Ghar I Q4.pdf | 23 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: APG PH I FORM 2 Oct 2022.pdf | 11 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: APG-I RERA FORM 1.pdf | 7 Jan 2023 |
| Form 2AFile: APG-I RERA FORM 2A-17.pdf | 5 Jan 2023 |
| Building plan approvalFile: Sheet-2.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-3.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-4.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-5.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-6.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-7.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-8.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-9.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-10.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-11.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-12.pdf | 14 Nov 2022 |
| Building plan approvalFile: Sheet-1.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-1.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-2.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-3.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-4.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-5.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-6.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-7.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-8.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-9.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-10.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-11.pdf | 14 Nov 2022 |
| Building Plan Approval (IOD)File: Sheet-12.pdf | 14 Nov 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Completion Certificate Building-C.pdf | 14 Nov 2022 |
| Form 2AFile: APG-I Form 2A Certificate -16.pdf | 18 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 APG PH 1 Arch Cert Sep2022.pdf | 7 Oct 2022 |
| Certificates of CA (Form 3)File: APNA GHAR 1 SEPT 21 (1).pdf | 14 Sep 2022 |
| Certificates of CA (Form 3)File: APNA GHAR 1 DEC 21.pdf | 14 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Apna ghar phase 1-June 2022.pdf | 17 Aug 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect's Certi 04072022_APG Phase I.pdf | 6 Jul 2022 |
| Form 2AFile: APG-I- RERA form 2A -14.pdf | 30 Jun 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 1_8.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 9_16.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 17_22.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 23_28.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 29_35.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 36_41.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 42_47.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 48_53.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 54_59.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 60_65.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 66_71.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 72_77.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 78_83.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 84_89.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 90_95.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 96_100.pdf | 30 Apr 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: DEED OF DECLARATION SAMRAAT APNA GHAR PHASE 1 26042022 101_106.pdf | 30 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Apna ghar ph 1 Jan to Mar 22.pdf | 22 Apr 2022 |
Promoter's earlier projects13
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Samraat Apna Ghar Phase-IIP51600020657 | Someshwar Satpur Link Road Near DJ Reva Meadows, Nashik | - | Apr 2019 | Completed | Dec 2023 | Late, Jan 2025 |
| Samraat Symphony Project 02 | IndiraNagar Nashik Maharashtra | 28 | - | Completed | Dec 2019 | Mar 2019 |
| Samraat Gokuldham Project 01 | Hirawadi Mumbai Agra Highway 422003 Nashik Maharashtra | 241 | - | Completed | Dec 2019 | Oct 2018 |
| Samraat Vrindavan | Om Nagar Opp Swami Narayan temple Mumbai-Agra Highway Nashik 422003 | 240 | - | Completed | Mar 2017 | Late, Jun 2017 |
| Signature | Serene Meadows Gangapur Road Anandwali Nashik 422013 | 60 | - | Completed | Dec 2016 | Late, Jun 2017 |
| Samraat Symphony Project 03 | NAGARE NAGAR BEHIND SEVEN HEAVEN HOTEL MUMBAI-AGRA HIGHWAY Nashik 422009 | 112 | - | Completed | Dec 2016 | Late, Jul 2017 |
| Samraat Symphony Project 01 | Nagare Nagar behind Seven Heaven Hotel MubaiAgra Road Nashik 422009 | 84 | - | Completed | Dec 2016 | Late, Jul 2017 |
| Samraat Tropicano 01 | Serene Meadows Gangapur Road Anandwali Nashik 422013 | 460 | - | Completed | Oct 2016 | Late, Jul 2017 |
| Dream Grandeur | Matoshri Nagar Tidke Colony Nashik 422002 | 16 | - | Completed | Jun 2012 | Late, Nov 2012 |
| Dream Nest | Near Ryan International School Old Wadala Road Nashik 422006 | 104 | - | Completed | Mar 2012 | Late, May 2012 |
| Dream Villaas | Ganesh baba Nagar Nashik-Pune Highway Nashik 422011 | 56 | - | Completed | Dec 2011 | Late, Mar 2012 |
| Dream Castle | Madhuban Colony Makhamalabad Road Panchavati Nashik 422003 | 106 | - | Completed | Dec 2010 | Late, Apr 2011 |
| Dream Flower | Nashik-Pune Highway Opposite Inox MultiPlex Nashik 422006 | 94 | - | Completed | Nov 2010 | Late, Mar 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 219 filed documents as one ZIP, foldered, with a manifest
Keep Samraat Apna Ghar Phase-I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Someshwar -Satpur link Road near DJ Reva Meadows4,100+ in Nashik
Filed coordinates, straight-line distance. 84 registered projects within 2 km.
Samraat AmOzon
M/S Shweta Infrastructure & Housing (I) Pv
ELYSIAN
ROONGTA HOMES LLP
HAPPY LIFE AT APNA GHAR PHASE III
M/S Shweta Infrastructure & Housing (I) Pv
SKY53
SKY53
ROONGTA ROSEWOOD APARTMENT
SHREE TIRUMALA BUILDCON
ROONGTA EMINENCE APARTMENT
SHREE TIRUMALA BUILDCON
See every Nashik project, with the district possession charts
Builder: M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. has 15 registrations on MahaRERA, including Samraat Nucleus - Project 01 and Samraat Gokuldham Project 01. Its filings disclose 14 earlier MahaRERA projects: declares 3 of 14 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Samraat Apna Ghar Phase-I is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Samraat Apna Ghar Phase-I?
The registered promoter entity is M/S Shweta Infrastructure & Housing (I) Pvt. Ltd., a company as per the filing. Its CIN U55100MH2005PTC155493 and GSTIN 27AAJCS4306F1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Samraat Apna Ghar Phase-I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Samraat Apna Ghar Phase-I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Samraat Apna Ghar Phase-I?
The professionals named in the filing: Architect: Ar.Sumit Kumath; Engineer: Mr Anil Wagh; Engineer: Mr Vikram Endait; Engineer: Mr Jayant Inamdar; Engineer: Mr Sudhir Metkar; Chartered Accountant: BCS AND ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Samraat Apna Ghar Phase-I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback