M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. has 15 registrations in this build, including Samraat Nucleus - Project 01 and Samraat Gokuldham Project 01. Its filings disclose 14 earlier MahaRERA projects: 3 of 14 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Samraat Nucleus - Project 01 | Nashik, Maharashtra | - | - | Completed |
| Samraat Gokuldham Project 01 | Nashik, Maharashtra | - | - | Completed |
| Samraat Symphony Project 02 | Nashik, Maharashtra | - | - | Completed |
| Samraat Apna Ghar Phase-I | Nashik, Maharashtra | - | - | Completed |
| Samraat Nucleus Project 02 | Nashik, Maharashtra | - | - | Completed |
| Samraat Gokuldham Project 02 | Nashik, Maharashtra | - | - | Completed |
| Samraat Apna Ghar Phase-II | Nashik, Maharashtra | - | - | Completed |
| Samraat AmOzon | Nashik, Maharashtra | 528 | 75% | Completed |
| Samraat Apna Ghar Phase-III | Nashik, Maharashtra | - | - | De-registered |
| HAPPY LIFE AT APNA GHAR PHASE III | Nashik, Maharashtra | 280 | 8% | Registered |
| HAPPY LIFE AT APNA GHAR PHASE IV | Nashik, Maharashtra | 112 | 0% | Registered |
| HAPPY LIFE AT APNA GHAR PHASE V | Nashik, Maharashtra | 140 | 0% | Registered |
| HAPPY LIFE AT APNA GHAR COMMERCIAL PHASE VI | Nashik, Maharashtra | 74 | 0% | Registered |
| HAPPY LIFE AT APNA GHAR COMMERCIAL PHASE-VII | Nashik, Maharashtra | 40 | 0% | Registered |
| W ISLAND | Nashik, Maharashtra | 27 | 0% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Dream Flower | 30 Nov 2010 | 29 Mar 2011 | +4 months |
| Dream Castle | 31 Dec 2010 | 11 Apr 2011 | +3 months |
| Dream Villaas | 31 Dec 2011 | 28 Mar 2012 | +3 months |
| Dream Nest | 31 Mar 2012 | 23 May 2012 | +2 months |
| Dream Grandeur | 30 Jun 2012 | 2 Nov 2012 | +4 months |
| Samraat Tropicano 01 | 31 Oct 2016 | 18 Jul 2017 | +9 months |
| Signature | 31 Dec 2016 | 9 Jun 2017 | +5 months |
| Samraat Symphony Project 03 | 31 Dec 2016 | 18 Jul 2017 | +7 months |
| Samraat Symphony Project 01 | 31 Dec 2016 | 31 Jul 2017 | +7 months |
| Samraat Vrindavan | 31 Mar 2017 | 9 Jun 2017 | +2 months |
| Samraat Symphony Project 02 | 31 Dec 2019 | 11 Mar 2019 | On time |
| Samraat Gokuldham Project 01 | 31 Dec 2019 | 1 Oct 2018 | On time |
Frequently asked questions
How do I verify M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.