Samraat Apna Ghar Phase-II
By M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
RG-MH-93340 · RERA P51600020657 · Last updated on MahaRERA portal: 7 May 2025
Source: official MahaRERA filing
Red flags
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Samraat Apna Ghar Phase-II is a Others project by M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. in Nashik, Maharashtra, registered with MahaRERA as P51600020657 on 30 Apr 2019. The registration is recorded completed; possession was promised by 30 Dec 2023.
At a glance
Project
- NameSamraat Apna Ghar Phase-II
- TypeOthers
- Location
- Canal Road
- Someshwar Satpur Link Road Near DJ Reva Meadows
- Satpur
- Nashik
- 422013
- Pincode422013
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600020657
- ReraGenie IDRG-MH-93340
Builder
- NameM/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
- Entity typeCompany
- CINU55100MH2005PTC155493
- GSTIN27AAJCS4306F1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorSujoy Jayant Gupta
- DirectorSUDHIR CHANDRAKANT METKAR
- Other registrations14 more →
- Completed8 of 15
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on30 Apr 2019
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings11 building records
- Documents filed232 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building F - Wing F1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building F - Wing F2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building G - Wing G1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building G -Wing G2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building G - Wing G3 | NA | 9 | 0 | 0 | 0 | 0 |
| Building G- Wing G4 | NA | 9 | 0 | 0 | 0 | 0 |
| Building H -Wing H1 | NA | 9 | 0 | 0 | 0 | 0 |
| Building H - Wing H2 | NA | 9 | 0 | 0 | 0 | 0 |
| Building H - Wing H3 | NA | 9 | 0 | 0 | 0 | 0 |
| Building H - Wing H4 | NA | 9 | 0 | 0 | 0 | 0 |
| Building H - Wing H5 | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building11
As on 7 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
100 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Internal walls, at 32%.
Building F - Wing F191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building F - Wing F291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building G - Wing G191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building G -Wing G291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building G - Wing G391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building G- Wing G491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building H -Wing H150%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 32% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building H - Wing H250%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 32% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 2% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building H - Wing H391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building H - Wing H491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building H - Wing H591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 60% |
| Open Parking | No | Not applicable |
Parking filed149
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building F - Wing F1 | 22 | 22 |
| Building F - Wing F2 | 22 | 22 |
| Building G - Wing G1 | 18 | 18 |
| Building G -Wing G2 | 8 | 8 |
| Building G - Wing G3 | 8 | 8 |
| Building G- Wing G4 | 18 | 18 |
| Building H -Wing H1 | 18 | 18 |
| Building H - Wing H2 | 8 | 8 |
| Building H - Wing H3 | 8 | 8 |
| Building H - Wing H4 | 1 | 1 |
| Building H - Wing H5 | 18 | 18 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar.Sumit Kumath |
| Engineer | Mr Sudhir Metkar |
| Engineer | Mr Jayant Inamdar |
| Engineer | Mr VIkram ENdait |
| Engineer | Mr Anil Wagh |
| Chartered Accountant | A K Chordia and Associates |
| Partner | Role in project |
|---|---|
| M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe here by applying for Extension of our RERA registered Project- Samraat Apna Ghar Phase II vide its RERA Registration No. P51600020657 dated 18/05/2020, said project constructed on Survey No. 50/2 area admeasuring 24,500 square meters, having CTS No. 2383/1 & Survey No. 48/2/A area admeasuring 5,100 square meters situate at Gangapur, Taluka Nashik, District Nashik. We here by writing to you a detailed explanation regarding the delays encountered in the completion of the registered project bearing vide Registration No. P51600020657. We here by clears that we have already completed Buildings F
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Dec 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Apr 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Sep 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Jan 2025
Documents filed232
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 232 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - TechnicalFile: FORM IV APNA GHAR PHASE II.pdf | 7 May 2025 |
| Other - TechnicalFile: RERA form IIA APG-II.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form II Apna ghar ph II march .pdf | 15 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form II Apna ghar ph II June.pdf | 15 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form II Apna ghar ph II Sep .pdf | 15 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: APG PII QIV 2324.pdf | 12 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: APG PII QI 2425.pdf | 12 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: APG PII QII 2425.pdf | 12 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: APG PII QIII 2425.pdf | 12 Mar 2025 |
| Certificates of CA (Form 3)File: APNA GHAR PHASE II FORM III QIII.pdf | 28 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apna Ghar Phase II FORM II QIII.pdf | 28 Feb 2025 |
| Certificates of CA (Form 3)File: PHASE II - FORM III.pdf | 7 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM ONE PHASE II.pdf | 24 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM ONE PHASE II.pdf | 23 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FORM FOUR APNA GHAR PHASE II.pdf | 23 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC WING H1 AND H2.pdf | 14 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24.pdf | 7 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 PHASE II.pdf | 6 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 AG II.pdf | 30 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form One Apna Ghar Phase Two.pdf | 5 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM ONE PHASE TWO QUARTER FOUR.pdf | 3 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM TWO FOR APNA GHAR TWO QUARTER THREE.pdf | 29 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM TWO A AG PHASE II.pdf | 27 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION CERT.pdf | 29 Feb 2024 |
| Declaration in FORM BFile: Affidavit cum undertaking.pdf | 12 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Apna Ghar Phase II Q2.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form-III Apna Ghar II Q3.pdf | 3 Feb 2024 |
| Details of encumbrancesFile: INDEX II OF RECONVENCE OF TATA CAPITAL.pdf | 20 Jan 2024 |
| Details of encumbrancesFile: Index II ICICI Mortgage Deed.pdf | 20 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Building Commencement Certificate.pdf | 16 Jan 2024 |
| Declaration about Commencement CertificateFile: Declaration for commencement year-2021.pdf | 16 Jan 2024 |
| Declaration about Commencement CertificateFile: Declaration for coemmencment year-2023.pdf | 16 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 APG PH II Jan 2024.pdf | 9 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5- FY-2021-22.pdf | 28 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY-2022-23.pdf | 28 Dec 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion Application H1 and H2 wing.pdf | 28 Dec 2023 |
| Form 2AFile: APG-II RERA form 2A -1 .pdf | 26 Dec 2023 |
| Form 2AFile: APG-II RERA form 2A -2.pdf | 26 Dec 2023 |
| Form 2AFile: APG-II RERA form 2A -3.pdf | 26 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Inventories Apna Ghar Phase II.pdf | 26 Dec 2023 |
| Certificates of CA (Form 3)File: Form III Apna GHAR II Q2.pdf | 26 Dec 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Self Declaration for Part Completion Certificate.pdf | 23 Dec 2023 |
| Copy of the legal title reportFile: TITLE REPORT DATED 10-11-2023.pdf | 6 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - SAMRAAT APNA GHAR PHASE II- Q1 2023-24.pdf | 13 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTORY -APNA GHAR -Q1-2023-24.pdf | 11 Oct 2023 |
| Certificates of CA (Form 3)File: CA Certificate Q1 23-24 Apna Ghar II_ Form 3.pdf | 11 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 APN Oct 2023.pdf | 2 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory-APN- 2022-23- Q4.pdf | 17 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Apna Ghar II - Q1 2023-24.pdf | 6 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Apna Ghar II Q1 2324.pdf | 6 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Revised Form 2 Apna Ghar II Q4 2223.pdf | 30 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3 Apna Ghar II Q4 2223.pdf | 26 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 13 Form 2A.pdf | 17 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: APG-II -RERA form 2A certificate- 17.pdf | 17 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 APG II March 2023.pdf | 13 Jun 2023 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement For Sale.pdf | 8 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest by Directors 31012023.pdf | 26 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 APG PH II.pdf | 10 Apr 2023 |
| Form 2AFile: APG-II -RERA form 2A certificate- 17.pdf | 5 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr Cert Apna Ghar Phase II Dec 2022.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Nuc Q1 2223.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: APG II Q1 2223.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: APG II Q2 2223.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: APG II Q3 2223.pdf | 3 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engr Cert Apna Ghar Phase II Dec 2022.pdf | 2 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Apna Ghar 2 Q4 2122.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: Apna Ghar 2 Q1 2223.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: Apna Ghar 2 Q2 2223.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: Apna Ghar II Q3 2223.pdf | 2 Mar 2023 |
| Certificates of CA (Form 3)File: CA Certificate Apna Ghar II Q4.pdf | 23 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: APG PH II FORM 2 Oct 2022.pdf | 11 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: APG PH II Form 1.pdf | 10 Jan 2023 |
| Form 2AFile: APG-II RERA FORM 2A-16.pdf | 5 Jan 2023 |
| Form 2AFile: APG-II Form 2A Certificate -15.pdf | 18 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Arch Cert APG Phase II Sep2022.pdf | 7 Oct 2022 |
| Building plan approvalFile: Sheet-01.pdf | 20 Sep 2022 |
| Building plan approvalFile: Sheet-02.pdf | 20 Sep 2022 |
| Building plan approvalFile: Sheet-03.pdf | 20 Sep 2022 |
| Building plan approvalFile: Sheet-04.pdf | 20 Sep 2022 |
| Building plan approvalFile: Sheet-05.pdf | 20 Sep 2022 |
Promoter's earlier projects13
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Samraat Apna Ghar Phase-IP51600020299 | Someshwar -Satpur link Road near DJ Reva Meadows, Nashik | - | Apr 2019 | Completed | Jun 2023 | Nov 2022 |
| Samraat Symphony Project 02 | IndiraNagar Nashik Maharashtra | 28 | - | Completed | Dec 2019 | Mar 2019 |
| Samraat Gokuldham Project 01 | Hirawadi Mumbai Agra Highway 422003 Nashik Maharashtra | 241 | - | Completed | Dec 2019 | Oct 2018 |
| Samraat Vrindavan | Om Nagar Opp Swami Narayan temple Mumbai-Agra Highway Nashik 422003 | 240 | - | Completed | Mar 2017 | Late, Jun 2017 |
| Signature | Serene Meadows Gangapur Road Anandwali Nashik 422013 | 60 | - | Completed | Dec 2016 | Late, Jun 2017 |
| Samraat Symphony Project 03 | NAGARE NAGAR BEHIND SEVEN HEAVEN HOTEL MUMBAI-AGRA HIGHWAY Nashik 422009 | 112 | - | Completed | Dec 2016 | Late, Jul 2017 |
| Samraat Symphony Project 01 | Nagare Nagar behind Seven Heaven Hotel MubaiAgra Road Nashik 422009 | 84 | - | Completed | Dec 2016 | Late, Jul 2017 |
| Samraat Tropicano 01 | Serene Meadows Gangapur Road Anandwali Nashik 422013 | 460 | - | Completed | Oct 2016 | Late, Jul 2017 |
| Dream Grandeur | Matoshri Nagar Tidke Colony Nashik 422002 | 16 | - | Completed | Jun 2012 | Late, Nov 2012 |
| Dream Nest | Near Ryan International School Old Wadala Road Nashik 422006 | 104 | - | Completed | Mar 2012 | Late, May 2012 |
| Dream Villaas | Ganesh baba Nagar Nashik-Pune Highway Nashik 422011 | 56 | - | Completed | Dec 2011 | Late, Mar 2012 |
| Dream Castle | Madhuban Colony Makhamalabad Road Panchavati Nashik 422003 | 106 | - | Completed | Dec 2010 | Late, Apr 2011 |
| Dream Flower | Nashik-Pune Highway Opposite Inox MultiPlex Nashik 422006 | 94 | - | Completed | Nov 2010 | Late, Mar 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 14 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 232 filed documents as one ZIP, foldered, with a manifest
Keep Samraat Apna Ghar Phase-II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Someshwar Satpur Link Road Near DJ Reva Meadows4,100+ in Nashik
Filed coordinates, straight-line distance. 84 registered projects within 2 km.
Samraat AmOzon
M/S Shweta Infrastructure & Housing (I) Pv
ELYSIAN
ROONGTA HOMES LLP
HAPPY LIFE AT APNA GHAR PHASE III
M/S Shweta Infrastructure & Housing (I) Pv
SKY53
SKY53
ROONGTA ROSEWOOD APARTMENT
SHREE TIRUMALA BUILDCON
ROONGTA EMINENCE APARTMENT
SHREE TIRUMALA BUILDCON
See every Nashik project, with the district possession charts
Builder: M/S Shweta Infrastructure & Housing (I) Pvt. Ltd.
M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. has 15 registrations on MahaRERA, including Samraat Nucleus - Project 01 and Samraat Gokuldham Project 01. Its filings disclose 14 earlier MahaRERA projects: declares 3 of 14 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Samraat Apna Ghar Phase-II is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Samraat Apna Ghar Phase-II?
The registered promoter entity is M/S Shweta Infrastructure & Housing (I) Pvt. Ltd., a company as per the filing. Its CIN U55100MH2005PTC155493 and GSTIN 27AAJCS4306F1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Samraat Apna Ghar Phase-II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Samraat Apna Ghar Phase-II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Samraat Apna Ghar Phase-II?
The professionals named in the filing: Architect: Ar.Sumit Kumath; Engineer: Mr Sudhir Metkar; Engineer: Mr Jayant Inamdar; Engineer: Mr VIkram ENdait; Engineer: Mr Anil Wagh; Chartered Accountant: A K Chordia and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Samraat Apna Ghar Phase-II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback