SAISHRUSHTI
RG-MH-02477 · RERA P51600008058 · Last updated on MahaRERA portal: 10 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 52 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAISHRUSHTI is a Others project by JAY DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600008058 on 18 Aug 2017. Possession is promised by 31 Oct 2027. The completion date has moved by 52 months from the original filing. 103 of the 116 units on this registration are recorded sold or booked, and 21 of 22 construction stages are filed complete.
At a glance
Project
- NameSAISHRUSHTI
- TypeOthers
- Location
- CANAL ROAD
- NASHIK
- 422013
- Pincode422013
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600008058
- ReraGenie IDRG-MH-02477
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Aug 2017
- Promised completion31 Oct 2027
- Revised completionRevised to 31 Oct 2027 (originally 30 Jun 2023)
- Buildings2 building records
- Documents filed136 files
Current status
Figures as on 10 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAISHRUSHTI A WING | NA | 16 | 14 | 52 | 12 | 64 |
| SAISHRUSHTI B WING | NA | 16 | 14 | 52 | 0 | 52 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
21 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 99%.
SAISHRUSHTI A WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SAISHRUSHTI B WING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 99% |
Progress on shared amenities15
As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed136
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| SAISHRUSHTI A WING | 1 | 67 | 68 |
| SAISHRUSHTI B WING | 1 | 67 | 68 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MANAT INFRA | Nashik (M Corp.) | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAISHRUSHTI A WING | NA | Rs 11.50 cr | Rs 11.50 cr |
| SAISHRUSHTI B WING | NA | Rs 7.90 cr | Rs 7.90 cr |
| - | NA | Rs 61.00 lakh | Rs 61.00 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUMIT KUMATH |
| Engineer | BHUSHAN SHINTRE |
| Chartered Accountant | SUNIL G KUNDNANI |
| Chartered Accountant | S BRAMHECHA AND CO |
| Partner | Role in project |
|---|---|
| JAY DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the slack of workers in karona the possession is delayed.
Reason as filed by the promoterDUE TO LABOUR SHORTAGE
Reason as filed by the promoterdue to some technical reasons unable to get oc.
Reason as filed by the promoterDUE TO SOME TECHNICAL REASONS UNABLE TO GET OC FROM DEPARTMENT
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Aug 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 7 Nov 2024
Documents filed136
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A Sai Shrushti (3).pdf | 10 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Aug 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Aug 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 22 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 22 Jul 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 22 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Sai Shrushti (1).pdf | 6 Jul 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Jul 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Jul 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Jul 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Jul 2026 |
| Withdrawal Update Form 3File: 43 Form 3 Revised signed_compressed.pdf | 6 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Sai Shrushti.pdf | 6 Oct 2025 |
| Withdrawal Update Form 2File: Scan2024-08-06_182302.pdf | 6 Oct 2025 |
| Withdrawal Update Form 3File: ca certificate.pdf | 6 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form 2 A Sai Shrushti.pdf | 3 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Sai Shrushti Mar 25.pdf | 25 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: format b (2).pdf | 30 Jun 2025 |
| Form 3File: FORM 3 SAI SHRUSHTI (1)_11zon.pdf | 30 Jun 2025 |
| Form 1File: ar certificate s no 43(signed).pdf | 30 Jun 2025 |
| Form 2File: DocScanner 20 May 2025 1-52 pm.pdf | 30 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 Sai shrushti (1).pdf | 8 Feb 2025 |
| Certificates of CA (Form 3)File: Sai shrushti form 3 dec 2024_11zon.pdf | 7 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: sai shushi (1).pdf | 7 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 (1)_11zon.pdf | 4 Jan 2025 |
| Certificates of CA (Form 3)File: form 3 Sai shrushti.pdf | 4 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 (4).pdf | 4 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: DocScanner 11 Nov 2024 4-33 pm(1).pdf | 12 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: DocScanner 7 Nov 2024 6-34 pm.pdf | 7 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf | 7 Nov 2024 |
| Declaration about Commencement CertificateFile: DocScanner 9 Oct 2024 11-52 am.pdf | 9 Oct 2024 |
| Declaration in FORM BFile: Scan2024-10-08_163527_11zon.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Scan2024-10-08_124944.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Scan2024-10-08_131731.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Scan2024-10-08_125000.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DocScanner 5 Aug 2024 6-20 pm.pdf | 12 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Scan2024-08-06_182324.pdf | 12 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Scan2024-08-06_182302.pdf | 12 Aug 2024 |
| Certificates of CA (Form 3)File: Scan 12 Jul 2024_11zon.pdf | 12 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DocScanner 6 May 2024 3-42 pm.pdf | 7 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DocScanner 7 May 2024 11-25 am.pdf | 7 May 2024 |
| Certificates of CA (Form 3)File: 43_compressed.pdf | 8 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sai Srushti 31-12-24_compressed.pdf | 29 Mar 2024 |
| Certificates of CA (Form 3)File: ilovepdf_merged (5)_compressed.pdf | 13 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Pi7_Sai_Shrushti_Architecture_Certificate_001 (1).pdf | 19 Aug 2023 |
| Certificates of CA (Form 3)File: CA CERTIFICATE_001_11zon (2) (1).pdf | 19 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2020.pdf | 17 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2021.pdf | 17 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 12 2021.pdf | 17 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 03 2022.pdf | 17 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30 06 2022.pdf | 17 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30 09 2022.pdf | 17 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31 12 2022.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31 03 2019.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_31 03 2020.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_31 03 2021.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_31 03 2022.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_31 12 2021.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_31 12 2022.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_30 06 2022.pdf | 17 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_30 09 2022.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 31032019.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 31032020.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 31032021.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 31122021.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 31032022.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3 30062022.pdf | 17 Feb 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ADITYA TOWER APARTMENT | MAKAMLABAD | 16 | Completed | Jun 2010 | Late, Jan 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 19 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 136 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAISHRUSHTI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NASHIK4,100+ in Nashik
Filed coordinates, straight-line distance. 92 registered projects within 2 km.
Samraat AmOzon
M/S Shweta Infrastructure & Housing (I) Pv
ELYSIAN
ROONGTA HOMES LLP
HAPPY LIFE AT APNA GHAR PHASE III
M/S Shweta Infrastructure & Housing (I) Pv
SKY53
SKY53
ROONGTA ROSEWOOD APARTMENT
SHREE TIRUMALA BUILDCON
ROONGTA EMINENCE APARTMENT
SHREE TIRUMALA BUILDCON
See every Nashik project, with the district possession charts
Builder: JAY DEVELOPERS
JAY DEVELOPERS has 20 registrations on MahaRERA, including VIJAY RESIDENCY and VIJAYSHRUSHTI. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 7 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if SAISHRUSHTI is delayed beyond 31 Oct 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAISHRUSHTI?
The registered promoter entity is JAY DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAISHRUSHTI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAISHRUSHTI?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAISHRUSHTI?
The professionals named in the filing: Architect: SUMIT KUMATH; Engineer: BHUSHAN SHINTRE; Chartered Accountant: SUNIL G KUNDNANI; Chartered Accountant: S BRAMHECHA AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAISHRUSHTI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback