Registered No litigation declared Others project

ELYSIAN

By ROONGTA HOMES LLP

RG-MH-84795 · RERA P51600054678 · Last updated on MahaRERA portal: 1 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 125.00 crore secured on the land, in favour of Bajaj Housing Finance Ltd

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 9 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Mar 2032Possession promisedno revision filed
15 of 55Construction stages doneacross 5 buildings; furthest along: Excavation, 75%
241 of 313Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 107 documents Report an error

ELYSIAN is a Others project by ROONGTA HOMES LLP in Nashik, Maharashtra, registered with MahaRERA as P51600054678 on 2 Feb 2024. Possession is promised by 31 Mar 2032. 72 of the 313 units on this registration are recorded sold or booked, and 15 of 55 construction stages are filed complete.

At a glance

Project

  • NameELYSIAN
  • TypeOthers
  • Location
    • Gangapur Road
    • Nirmala Convent Road
    • Nashik
    • 422013
  • Pincode422013
  • RERA no.P51600054678
  • ReraGenie IDRG-MH-84795

Builder

  • NameROONGTA HOMES LLP
  • Entity typePartnership
  • GSTIN27AAUFR4502Q2ZE
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersAKHIL LALIT ROONGTA, LALIT SATYANARAYAN ROONGTA, NIKHIL LALIT ROONGTA
  • Other registrations25 more →
  • Completed25 of 26
  • Declared earlier projects9 →

Key dates

this monthRegisteredFeb 2024PromisedMar 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Feb 2024
  • Promised completion31 Mar 2032
  • Revised completionNone
  • Buildings5 building records
  • Documents filed107 files

Current status

23%72 of 313 units booked
12.3%Work done, per cost certificate

Figures as on 1 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ELYSIAN WING-ENA383464569
ELYSIAN WING-ANA332854458
ELYSIAN WING-BNA3328541064
ELYSIAN WING-CNA332854357
ELYSIAN WING-DNA383364165

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 75%.

ELYSIAN WING-E7%
ActivityProgress
Excavation75%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ELYSIAN WING-A41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure21%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ELYSIAN WING-B41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure21%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ELYSIAN WING-C41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure22%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ELYSIAN WING-D28%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed816

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots816
Closed/Covered816
BuildingClosed/CoveredTotal
ELYSIAN WING-E192192
ELYSIAN WING-A189189
ELYSIAN WING-B189189
ELYSIAN WING-C5454
ELYSIAN WING-D192192

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area14,284 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBajaj Housing Finance Ltd
Secured amountRs 125.00 crore
CERSAI search filedYes
Declared on25 Sep 2025

Approvals and building plan

Sanctioning authorityNASHIK MUNICIPAL CORPORATION
Permissible FSI79518.97
Proposed, not sanctioned79,519 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Oxygen plaza, Near SSK Solitaire Hotel, Opp. G Shoppe, Ganesh Nagar, Tidke Colony, Nashik, Maharashtra - 422002
Estimated costRs 233.57 cr
Cost incurredRs 28.64 cr
Work done12.26%
BuildingWingEstimatedIncurred
ELYSIAN WING-ANARs 52.55 crRs 10.83 cr
ELYSIAN WING-BNARs 52.46 crRs 10.82 cr
ELYSIAN WING-ENARs 46.41 crRs 1.50 cr
ELYSIAN WING-DNARs 45.79 crRs 1.38 cr
ELYSIAN WING-CNARs 18.36 crRs 4.11 cr
-NARs 18.00 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPANKAJ JADHAV
ArchitectSPECTRUM DESIGN GROUP
EngineerAMOL YADAVRAO BHALERAO
EngineerMAHIMTURA CONSULTANTS PRIVATE LTD
EngineerMayuresh Kishor Kale
Chartered AccountantPranav S. Lahoti & Co. Chartered Accountants
Chartered AccountantM/s. Pravin R.Rathi & Associates, Chartered Accountants
Chartered AccountantPRAVIN R RATHI & ASSOCIATES FRN 131494W
PartnerRole in project
ROONGTA HOMES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2032

Documents filed107

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 01042026.pdf1 Jun 2026
Withdrawal Update Form 2File: 3 form 2 elysian FY 25-26.pdf1 Jun 2026
Withdrawal Update Form 3File: Form 3 Elysian Q4.pdf1 Jun 2026
Form 2A (FY 2025-2026)File: FORM 2A ELYSIAN 25-26.pdf27 May 2026
Withdrawal Update Form 1File: FORM 1-ELYSIAN-01012026.pdf2 Mar 2026
Withdrawal Update Form 2File: Form 2 Elysian Q3.pdf2 Mar 2026
Withdrawal Update Form 3File: Form 3 Elysian Q3.pdf2 Mar 2026
Withdrawal Update Form 1File: FORM 1-ELYSIAN-01102025.pdf25 Dec 2025
Withdrawal Update Form 2File: FORM 2-ELYSIAN-01102025.pdf25 Dec 2025
Withdrawal Update Form 3File: FORM 3 ELYSIAN Q2.pdf25 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 ELYSIAN.pdf22 Nov 2025
Form 1File: FORM1-ELYSIAN-01042025.pdf25 Jun 2025
Form 2File: FORM 2-ELYSIAN-01042025.pdf25 Jun 2025
Form 3File: FORM 3-ELYSIAN_01042025.pdf25 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD-ELYSIAN-FY24-25.pdf25 Jun 2025
Self-declaration of Quarterly ProgressFile: SELF DECLARATION ON ENCUMBRANCE FINANCE.pdf25 Jun 2025
OthersFile: Asset Based Search ERROR.pdf25 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1-ELYSIAN-01042025.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-ELYSIAN-FY24-25.pdf24 Apr 2025
Other - TechnicalFile: FORM 2A_ELYSIAN_FY 24-25.pdf12 Apr 2025
Details of encumbrances concerned to FinanceFile: INDEX 2.pdf1 Apr 2025
Details of encumbrances concerned to FinanceFile: SELF DECLARATION ON ENCUMBRANCE FINANCE.pdf1 Apr 2025
Details of encumbrances concerned to LegalFile: INDEX 2.pdf1 Apr 2025
Details of encumbrances concerned to LegalFile: SELF DECLARATION ON ENCUMBRANCE FINANCE.pdf1 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Elysian qtr3 24-25.pdf7 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-ELYSIAN-QTR3 24-25.pdf6 Feb 2025
Proforma of Agreement for saleFile: AFS RERA.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 3 ELYSIAN_compressed.pdf31 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: REVISED COMMENCEMENT.pdf29 Jan 2025
Declaration about Commencement CertificateFile: FORMAT D.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE-ELYSIAN-QTR1.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE-ELYSIAN-QTR2.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ELYSIAN FORM 3.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ELYSIAN Q2_.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold-Elysian-Q3.pdf18 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: ELYSIAN FORM 3.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-ELYSIAN-Q2.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-ELYSIAN-Q2.pdf18 Nov 2024
Declaration about Commencement CertificateFile: FORMAT D REVISED.pdf7 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold_Elysian_Q2 24-25.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Elysian_FY 23-24.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Elysian Q1.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: ELYSIAN_SOLD UNSOLD INVENTORY_Q1.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ELYSIAN FORM 2 Q4.pdf6 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Elysian_FY 23-24.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold_Elysian_Q4.pdf1 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ELYSIAN Q4.pdf1 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ELYSIAN FORM 1.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ELYSIAN_FORM-1_Q4.pdf29 Apr 2024
CERSAI detailsFile: CERSAI_ELYSIAN.pdf27 Apr 2024
Other - TechnicalFile: Form 2A_Elysian_FY 23-24.pdf22 Apr 2024
Building plan approvalFile: C WING PLAN.pdf30 Jan 2024
Building plan approvalFile: D AND E WING 1.pdf30 Jan 2024
Building plan approvalFile: D AND E WING 2.pdf30 Jan 2024
Building plan approvalFile: LAYOUT.pdf30 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: C WING PLAN.pdf30 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: D AND E WING 1.pdf30 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: D AND E WING 2.pdf30 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: LAYOUT.pdf30 Jan 2024
Building plan approvalFile: 123-1.pdf29 Jan 2024
Building plan approvalFile: 123-2.pdf29 Jan 2024
Building plan approvalFile: 123-3.pdf29 Jan 2024
Building plan approvalFile: 123-4.pdf29 Jan 2024
Building plan approvalFile: 123-5.pdf29 Jan 2024
Building plan approvalFile: 123-6.pdf29 Jan 2024
Building plan approvalFile: 123-7.pdf29 Jan 2024
Building plan approvalFile: 123-8.pdf29 Jan 2024
Building plan approvalFile: 123-12.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-1.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-2.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-3.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-4.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-5.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-6.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-7.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-8.pdf29 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 123-12.pdf29 Jan 2024
Layout approvalFile: LAYOUT.pdf20 Jan 2024
Building plan approvalFile: APPROVED BP-1-2_compressed.pdf20 Jan 2024

Promoter's earlier projects9

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

9 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHREE TIRUMALA GULMOHAR APARTMENTDivision Makhmalabad Shiwar NASHIK Taluka NASHIK Dist NASHIK156CompletedApr 2022Aug 2020
SHREE TIRUMALA PARAMOUNT APARTMENTTaluka NASHIK Dist NASHIK-422009173CompletedJun 2021Feb 2020
SHREE TIRUMALA REGENCY APARTMENTDeepali Nagar NASHIK Taluka NASHIK Dist NASHIK 42200950CompletedDec 2020May 2020
ROONGTA IMPERIA APARTMENTNASHIK 422001112CompletedJul 2020Mar 2019
ROONGTA HORIZON APARTMENTNASHIK 422001112CompletedJul 2020Mar 2019
SHREE TIRUMALA PLATINUM APARTMENTCOLLEGE ROAD NASHIK 42200510CompletedMay 2020Dec 2018
SHREE TIRUMALA PARADISE APARTMENTCHETANA NAGAR NASHIK 42200928CompletedSep 2019Nov 2018
SHREE TIRUMALA HARINIWAS APARTMENTSR.NO.78 PLOT NO.83 SATPUR NASHIK42CompletedMar 2019May 2018
SHREE TIRUMALA SWASTIK APARTMENTINDIRA NAGAR NASHIK28CompletedDec 2018Jun 2018

How this compares with Nashik

23%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ELYSIAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nirmala Convent Road4,100+ in Nashik

Builder: ROONGTA HOMES LLP

ROONGTA HOMES LLP has 26 registrations on MahaRERA, including SHREE TIRUMALA SWASTIK APARTMENT and SHREE TIRUMALA PARADISE APARTMENT. Its filings disclose 9 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if ELYSIAN is delayed beyond 31 Mar 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELYSIAN?

The registered promoter entity is ROONGTA HOMES LLP, a partnership as per the filing. Its GSTIN 27AAUFR4502Q2ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELYSIAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ELYSIAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELYSIAN?

The professionals named in the filing: Architect: PANKAJ JADHAV; Architect: SPECTRUM DESIGN GROUP; Engineer: AMOL YADAVRAO BHALERAO; Engineer: MAHIMTURA CONSULTANTS PRIVATE LTD; Engineer: Mayuresh Kishor Kale; Chartered Accountant: Pranav S. Lahoti & Co. Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELYSIAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELYSIAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELYSIAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.