Home / Browse projects / Pune, Maharashtra / Priyadarshan - I
Priyadarshan - I
By Kumar Agro Products Pvt Ltd
RG-MH-37607 · RERA P52100047781 · Last updated on MahaRERA portal: 3 May 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Priyadarshan - I is a Residential / Group Housing project by Kumar Agro Products Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100047781 on 28 Nov 2022. The registration is recorded completed; possession was promised by 15 May 2025.
At a glance
Project
- NamePriyadarshan - I
- TypeResidential / Group Housing
- Location
- Balaji Mandir Lane
- Jai Bhavani Nagar
- Pashan
- Haveli
- Pune
- 411021
- Pincode411021
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047781
- ReraGenie IDRG-MH-37607
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on28 Nov 2022
- Promised completion15 May 2025
- Revised completionNone
- Buildings1 building record
- Documents filed70 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| I | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 97%.
I: 86% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 88% |
| Sanitary Fittings within the flats / premises | 97% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 86% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Progress on shared amenities15
As on 3 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Parking filed36
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| Kumar Agro Products Pvt Ltd | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Jul 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 May 2025
Documents filed70
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 250502_OC.pdf | 3 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-PRIYADARSHAN I MAR25.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar certificate.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory.pdf | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5_Form 2A.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar Certificate.pdf | 22 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 22 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 22 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of Sold Inventory.pdf | 22 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Priyadarshan I.pdf | 14 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of sold inventory.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 23 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5_Form 2A.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 2_Priyadarshan_I.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5_Form 2A.pdf | 20 Apr 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: 240308_Decl about Grievance Redressal Cell.pdf | 8 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of sold inventory.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: 2_Priyadarshan_I.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 54_Priyadarshan - I.pdf | 30 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 19 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: 2_Priyadarshan_I.pdf | 19 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 19 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 21 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: 34_Priyadarshan - I.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 21 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar Certificate.pdf | 21 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 21 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 21 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: 34_Priyadarshan - I.pdf | 13 Jan 2023 |
| Proforma of Agreement for saleFile: 221105_Agreement for Sale_R3.pdf | 5 Nov 2022 |
| Proforma of Agreement for saleFile: 221105_Deviation Report_Agreement for Sale_R3.pdf | 5 Nov 2022 |
| Proforma of Allotment letterFile: 221004_Agreement for Sale_R2.pdf | 4 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: 20_Deviation Report_Agreement for Sale_R1.pdf | 4 Oct 2022 |
| Other - LegalFile: Encl 1_Annex A_NCLT ORDER_compressed.pdf | 4 Oct 2022 |
| Other - LegalFile: 221001_Priyadarshan_Clarification.pdf | 3 Oct 2022 |
| Proforma of Allotment letterFile: 5_Allotment Letter_R1.pdf | 2 Sep 2022 |
| Other - LegalFile: 220902_Clarification on Scrutiny.pdf | 2 Sep 2022 |
| Deviation Report with respect to Allotment letterFile: 16_Deviation Report_Allotment Letter_R1.pdf | 21 Jul 2022 |
| Layout approvalFile: 4_Layout.pdf | 16 Jul 2022 |
| Building plan approvalFile: 13_Building Plan.pdf | 16 Jul 2022 |
| PAN CardFile: 1_Pan Card.PDF | 16 Jul 2022 |
| Copy of the legal title reportFile: 2_Legal Title Report.pdf | 16 Jul 2022 |
| Copy of the legal title reportFile: 2_Legal Title Report_Format A.pdf | 16 Jul 2022 |
| Details of encumbrances concerned to FinanceFile: 3_Encumbrance Certificate_Finance.pdf | 16 Jul 2022 |
| Details of encumbrances concerned to LegalFile: 3_Encumbrance Certificate_Legal.pdf | 16 Jul 2022 |
| Copy of Layout Approval (in case of layout)File: 4_Layout.pdf | 16 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 13_Building Plan.pdf | 16 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 11_Commencement Certificate.pdf | 16 Jul 2022 |
| Declaration about Commencement CertificateFile: 14_Declaration_Commencement Certificate.pdf | 16 Jul 2022 |
| Declaration in FORM BFile: 6_Form B_Declaration.pdf | 16 Jul 2022 |
| CERSAI detailsFile: 12_CERSAI certificate.pdf | 16 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8_CA Certificate.pdf | 16 Jul 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 18_Self Declaration_Bank Account Details.pdf | 16 Jul 2022 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Kumar Pratham - A B C and ShopsP52100022486 | Moshi - Borhadewadi, Pune | 222 | Sep 2019 | Completed | Feb 2025 | Mar 2024 |
| Peninsula CP52100028012 | Pashan, Pune | 44 | Jan 2021 | Completed | Oct 2024 | Feb 2024 |
| Kumar Pratham - F MhadaP52100049685 | Moshi, Pune | 53 | Feb 2023 | Completed | Mar 2024 | Mar 2024 |
| Priyadarshan - JP52100029119 | Jai Bhavani Nagar, Pune | 28 | Apr 2021 | Completed | Jan 2024 | Late, Feb 2024 |
| Princeville - A2, C2 and Conv Shop 2P52100018603 | Moshi, Pune | 93 | Nov 2018 | Completed | Jun 2023 | Jun 2022 |
| Princeville - B4 and B5P52100015685 | Borhadewadi, Pune | 92 | Mar 2018 | Completed | Feb 2022 | Jun 2021 |
| Primus - AP52100004518 | Hadapsar Industrial Estate, Pune | - | Aug 2017 | Completed | Dec 2021Registered original: Dec 2019 | Aug 2021 |
| Picasso Phase IIP52100000104 | Sade Satra Nali, Hadapsar, Pune | 88 | Jul 2017 | Completed | Dec 2019 | Sep 2018 |
| Princeville - B3 and C1P52100000755 | Pimpri Chinchawad (M Corp.), Pune | 94 | Jul 2017 | Completed | May 2019 | Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 70 filed documents as one ZIP, foldered, with a manifest
Keep Priyadarshan - I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Jai Bhavani Nagar13,700+ in Pune
Filed coordinates, straight-line distance. 191 registered projects within 2 km.
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
Puraniks Abitante Fiore, Phase 2B
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
Builder: Kumar Agro Products Pvt Ltd
Kumar Agro Products Pvt Ltd has 9 registrations on MahaRERA, including Princeville - A2, C2 and Conv Shop 2 and Kumar Pratham - A B C and Shops. Its filings disclose 9 earlier MahaRERA projects: declares 8 of 9 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Priyadarshan - I is delayed beyond 15 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Priyadarshan - I?
The registered promoter entity is Kumar Agro Products Pvt Ltd, a company as per the filing. Its CIN U45100PN1991PTC064416 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Priyadarshan - I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Priyadarshan - I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in Priyadarshan - I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.