Red flags
- 19 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Puraniks Abitante Fiore, Phase 2B is a Residential / Group Housing project by Puranik Buildcon Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100020238 on 29 Mar 2019. Possession is promised by 30 Dec 2030. 542 of the 688 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete. 19 complaints are on record with the regulator.
At a glance
Project
- NamePuraniks Abitante Fiore, Phase 2B
- TypeResidential / Group Housing
- Location
- Bavdhan BK Road
- Near Puraniks Abitante Phase 1
- Bavadhan BK
- Mulshi
- Pune
- 411021
- Pincode411021
- RERA no.P52100020238
- ReraGenie IDRG-MH-04761
Builder
- NamePuranik Buildcon Private Limited
- Entity typeCompany
- CINU45400MH2007PTC170399
- GSTIN27AAECP2515N1Z8
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorShailesh Gopal Puranik
- Other registrations10 more →
- Completed5 of 11
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Mar 2019
- Promised completion30 Dec 2030
- Revised completionNone
- Buildings3 building records
- Documents filed115 files
Current status
Figures as on 21 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E | NA | 35 | 30 | 240 | 0 | 240 |
| F | NA | 33 | 28 | 224 | 0 | 224 |
| G | NA | 33 | 28 | 224 | 0 | 224 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 68%.
E54%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 9% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
F43%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 60% |
| Slabs of Super Structure | 12% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 4% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 2% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
G55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 68% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 3% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed520
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| E | 195 | 195 |
| F | 140 | 140 |
| G | 185 | 185 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vastushilpa Associates |
| Engineer | Pranil Deshpande |
| Chartered Accountant | VMD and Company |
| Chartered Accountant | HDO and Associates |
| Chartered Accountant | VMD & Co. |
| Chartered Accountant | VMD & Co |
| Chartered Accountant | Chirag Sarvaiya & Co |
| Partner | Role in project |
|---|---|
| Puranik Buildcon Private Limited | - |
Litigation declared3
| Case | Court | Status |
|---|---|---|
| SCS 663/2013 | Add Judge Small Cause CT and JD Pune | For Filing Defence Evidence |
| MA 100827/2015 | District Judge Addl Session Judge Pune | Awaiting for summons |
| 31/2022 | Tenth Joint CJST and ADDl CJM Pune | Filing Say and Application |
Complaints filed with MahaRERA19
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400538 | Uday Parshuram Kanhere | Puranik Buildcon Private Limited | 23/10/2024 |
| CC12601028 | Aditya Dilip Belose | Puranik Buildcon Private Limited | 25/02/2026 |
| CC12600815 | ABHAY KUMAR BAL MUKUND AGARWAL | Puranik Buildcon Private Limited | 13/02/2026 |
| CC12600816 | PAYAL JITENDRA GUPTA | Puranik Buildcon Private Limited | 13/02/2026 |
| CC12601568 | MANISHA ASHOK PATIL | Puranik Buildcon Private Limited | 21/03/2026 |
| CC12601886 | SUNIL KUMAR SINGH | Puranik Buildcon Private Limited | 31/03/2026 |
| CC12602089 | Tejas Vishnu Pawar | Puranik Buildcon Private Limited | 09/04/2026 |
| CC12602118 | Mahesh Sureshrao Borikar | Puranik Buildcon Private Limited | 10/04/2026 |
| CC12602120 | Dhananjay Ramkishan Ture | Puranik Buildcon Private Limited | 10/04/2026 |
| CC12602121 | Pankaj Gulabrao Kannamwar | Puranik Buildcon Private Limited | 10/04/2026 |
| CC12602122 | Rucha Nishad Kshirsagar | Puranik Buildcon Private Limited | 10/04/2026 |
| CC12602234 | Santosh Rangnath Puranik | Puranik Buildcon Private Limited | 16/04/2026 |
| CC12602227 | Prasad Avinash Hamine | Puranik Buildcon Private Limited | 15/04/2026 |
| CC12602228 | Prasad Avinash Hamine | Puranik Buildcon Private Limited | 15/04/2026 |
| CC12602869 | Shreyas Bharatbhooshan Saraf | Puranik Buildcon Private Limited | 16/05/2026 |
| CC12603572 | Kaustubh Vijay Joshi | Puranik Buildcon Private Limited | 09/06/2026 |
| CC12603574 | Kalyani Pradip Saraf | Puranik Buildcon Private Limited | 09/06/2026 |
| CC12603994 | Poonam Ankit Kerkal | Puranik Buildcon Private Limited | 27/06/2026 |
| CC12604245 | Rahul Rajeev Khapre | Puranik Buildcon Private Limited | 06/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2030
Documents filed115
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: New FORM 1 architect- Abitante Ph2B.pdf | 21 Apr 2026 |
| Form 2File: Form 2 Engineers Certificate_Abitante_2B 30092025.pdf | 21 Apr 2026 |
| Form 3File: CA Certificates - Abitante - 2B_compressed.pdf | 21 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Inventory details.pdf | 21 Apr 2026 |
| Form 1File: Form 1 - Abitante Fiore Ph2B.pdf | 21 Apr 2026 |
| Form 2File: Form 2.pdf | 21 Apr 2026 |
| Form 3File: Form 3.pdf | 21 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Sales Data 20042026.pdf | 21 Apr 2026 |
| Form 1File: New FORM 1 architect- Abitante Ph2B.pdf | 23 Jan 2026 |
| Form 2File: Form 2 Engineers Certificate_Abitante_2B.pdf | 23 Jan 2026 |
| Form 3File: CA Certificates - Abitante - 2B Final.pdf | 23 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: AbitanteII2B_compressed.pdf | 23 Jan 2026 |
| Form 5 (FY 2024-2025)File: Rera Form 5 - Abhitante 2B - sign date.pdf | 29 Sep 2025 |
| Form 1File: New FORM 1 architect- Abitante Ph2B - E,F & G Bldg -30062025.pdf | 12 Aug 2025 |
| Form 2File: Form 2 Engineers Certificate_Abitante_2B - 080825Sign.pdf | 12 Aug 2025 |
| Form 3File: CA Certificates - Abitante - 2B 2072025.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory- Abitante 2B-EFG.pdf | 12 Aug 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 31032025.pdf | 4 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New FORM 1 architect- Abitante Ph2B.pdf | 20 Apr 2025 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 20 Apr 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 7 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 30092024.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 31122024.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Abitante Ph2B - 31122024.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B 06012025.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 30092024.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 31122024.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Abitante Ph2B - 31122024.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B 06012025.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Abitante Ph2B - 31122024.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B 06012025.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 30092024.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante_2B - 31122024.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante 2B.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante 2B.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B 30092024.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante 2B.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B 30092024.pdf | 20 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Abitante Fiore Phase 2B.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Abitante Fiore Phase 2B.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Abitante Fiore Phase 2B.pdf | 7 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form_2A-Abitante 2B _23-24.pdf | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Anitante 2B-E.PDF | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Abitate-2B-E.PDF | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Abitante 2B-E.PDF | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Abitante 2B-E.PDF | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Abitante 2B-E,F,G.PDF | 24 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Abitante 2B-E,F,G.PDF | 24 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante Fiore-2B_E F G - P52100020238.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Abitante 2B 300624.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: Abitante Fiore Phase 2B_compressed.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032024Architects Certificate - Abitante Ph2B.pdf | 23 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Abitante2B 310324.pdf | 23 Apr 2024 |
| Certificates of CA (Form 3)File: Aitante 2B_compressed.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New FORM 1 architect- Abitante Ph2B.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Abitante 2B 31122023.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: Abitante 2B_compressed.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante Ph2B - 30092023.pdf | 30 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Abitante 2B - 300923.pdf | 30 Oct 2023 |
| Certificates of CA (Form 3)File: Abitante Ph 2B.pdf | 30 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera Form 5 Abhitante 2B - sign.pdf | 30 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Abitante phase 2 CC 21082023.pdf | 23 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante Ph2B 30062023.pdf | 31 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Abitante 2B 300623.pdf | 31 Jul 2023 |
| Certificates of CA (Form 3)File: Abitante 2B 30062023.pdf | 31 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Abitante 2B 22 23.PDF | 10 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Abitante Ph2B - E F G Bldg -31032023.pdf | 1 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante 2B 310323.pdf | 1 May 2023 |
| Certificates of CA (Form 3)File: Abitate 2B_compressed.pdf | 1 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Rera Form 5 Puranik Abitante Phase 2B - sign.pdf | 14 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE BLDG ABITANTE 2B.pdf | 17 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate_Abitante 2B 31122022.pdf | 17 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Abitante 2B 31122022.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: Abitante 2B.pdf | 17 Feb 2023 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates - Abitante - 2B.pdf | 12 Jan 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Aldea Espanola Phase III | Aldea Espanola Village Mahalunge Taluka Mulshi District Pune | 118 | Completed | Dec 2015 | Late, Mar 2016 |
| Aldea Espanola Phase II | Aldea Espanola Village Mahalunge Taluka Mulshi District Pune | 188 | Completed | Jun 2013 | Late, Mar 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 10 other registrations, which the RERA portal never shows together
- All 115 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Puraniks Abitante Fiore, Phase 2B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Puraniks Abitante Phase 113,700+ in Pune
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
ORIZZONTE PHASE - I
GALAXY VENTURES
Builder: Puranik Buildcon Private Limited
Puranik Buildcon Private Limited has 11 registrations on MahaRERA, including Puraniks Abitante Phase 1A and Puraniks Abitante Phase 1B. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Puraniks Abitante Fiore, Phase 2B is delayed beyond 30 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Puraniks Abitante Fiore, Phase 2B?
The registered promoter entity is Puranik Buildcon Private Limited, a company as per the filing. Its CIN U45400MH2007PTC170399 and GSTIN 27AAECP2515N1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Puraniks Abitante Fiore, Phase 2B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Puraniks Abitante Fiore, Phase 2B?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Puraniks Abitante Fiore, Phase 2B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Puraniks Abitante Fiore, Phase 2B?
The professionals named in the filing: Architect: Vastushilpa Associates; Engineer: Pranil Deshpande; Chartered Accountant: VMD and Company; Chartered Accountant: HDO and Associates; Chartered Accountant: VMD & Co.; Chartered Accountant: VMD & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Puraniks Abitante Fiore, Phase 2B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback