Home / Browse projects / Thane, Maharashtra / North Westend Tower 2

Registered No litigation declared Others project

North Westend Tower 2

By JP Infra Realty Private Limited

RG-MH-31386 · RERA P51700079721 · Last updated on MahaRERA portal: 24 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 150.00 crore secured on the land, in favour of RBL BANK LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2032Possession promisedmoved 4 months from the original
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
239 of 308Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

North Westend Tower 2 is a Others project by JP Infra Realty Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700079721 on 21 Mar 2025. Possession is promised by 30 Apr 2032. The completion date has moved by 4 months from the original filing. 69 of the 308 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete.

At a glance

Project

  • NameNorth Westend Tower 2
  • TypeOthers
  • Location
    • BHAYANDER WEST
    • BHAYANDER
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401101
  • Pincode401101
  • RERA no.P51700079721
  • ReraGenie IDRG-MH-31386

Builder

  • NameJP Infra Realty Private Limited
  • Entity typeCompany
  • CINU45200MH2010PTC206022
  • GSTIN27AAOCS9607A1Z7
  • DirectorsSHUBHAM VIJAYKUMAR JAIN, ABHISHEK CHHAGANLAL KHETAN
  • Other registrations16 more →
  • Completed8 of 17
  • Declared earlier projects15 →

Key dates

this monthRegisteredMar 2025First promiseDec 2031Revised toApr 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Mar 2025
  • Promised completion30 Apr 2032
  • Revised completionRevised to 30 Apr 2032 (originally 31 Dec 2031)
  • Buildings2 building records
  • Documents filed94 files

Current status

22%69 of 308 units booked
8.6%Work done, per cost certificate

Figures as on 24 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 2- WING 2ANA30301820182
TOWER 2 - WING 2BNA30301233126

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

TOWER 2- WING 2A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER 2 - WING 2B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed244

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots244
Closed/Covered244
BuildingClosed/CoveredTotal
TOWER 2- WING 2A141141
TOWER 2 - WING 2B103103

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,610 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofRBL BANK LIMITED
Secured amountRs 150.00 crore
CERSAI search filedYes
Declared on8 Apr 2026
LandownerVillageDistrict
SPAN VENTUREBHAYANDARThane

Approvals and building plan

Sanctioning authorityMira Bhaynder Muncipal Corporation
Permissible FSI36860.76
Proposed, not sanctioned36,861 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRBL BANK LTD,DHANNUR HOUSE,15,SIR P M ROAD, FORT,MUMBAI-400001
Estimated costRs 298.00 cr
Cost incurredRs 25.70 cr
Work done8.62%
BuildingWingEstimatedIncurred
TOWER 2- WING 2ANARs 143.48 crRs 12.85 cr
TOWER 2 - WING 2BNARs 143.48 crRs 12.85 cr
-NARs 11.05 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajesh Khandeparkar of M/s. Urbdes
ArchitectURBDES
EngineerVijay Joshi
EngineerAVP STRUCTURAL CONSULTANTS
Chartered AccountantCAS & CO
Chartered AccountantSGCO & Co. LLP
Chartered AccountantSGCO & CO LLP
PartnerRole in project
JP Infra Realty Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51700079721/WarDec 2031 → Apr 2032

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2032

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1_JUNE 2026_North Westend Tower 2.pdf24 Sep 2026
Withdrawal Update Form 2File: FORM 2_JUNE 2026_North Westend Tower 2.pdf24 Sep 2026
Withdrawal Update Form 3File: FORM 3_JUNE 2026_North Westend Tower 2.pdf24 Sep 2026
Withdrawal Update Form 1File: Form 1 NWT2 31032026.pdf15 May 2026
Withdrawal Update Form 2File: Form 2 NWE T2 31032026.pdf15 May 2026
Withdrawal Update Form 3File: Form 3 North Westend Tower 2 31032026.pdf15 May 2026
Form 2A (FY 2025-2026)File: Form 2A NWT 2.pdf15 May 2026
Layout approvalFile: HIGHLIGHTED PLAN COPY - LAYOUT .pdf22 Jan 2026
Withdrawal Update Form 1File: Form 1- NWT2.pdf22 Jan 2026
Withdrawal Update Form 2File: Form 2_ Signed Copy_ NWE T2_As on 31-12-25.pdf22 Jan 2026
Withdrawal Update Form 3File: Form 3 North Westend Tower 2 31122025.pdf22 Jan 2026
Withdrawal Update Form 1File: Form 1- North Westend T2 30092025.pdf25 Nov 2025
Withdrawal Update Form 2File: Form 2_Signed Copy_ North West End T2_ As on 30-09-25.pdf25 Nov 2025
Withdrawal Update Form 3File: Form 3 - North Westend Tower 2 - 30092025.pdf25 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf9 Oct 2025
Withdrawal Update Form 1File: Form 1- June 2025 North Westend T2.pdf9 Oct 2025
Withdrawal Update Form 1File: Form 1- June 2025 North Westend T2.pdf9 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf9 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf9 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf9 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf9 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf9 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf9 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf9 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf9 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf9 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A-Signed Copy_NWE T2_FY 24-25.pdf9 Oct 2025
Form 5 (FY 2024-2025)File: RERA Form 5 - North West End Tower 2 March 25.pdf29 Sep 2025
Disclosure of sold/ booked inventoryFile: Sold unsold North Westend T2.pdf29 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- June 2025 North Westend T2.pdf4 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf1 Aug 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf1 Aug 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold- North west 2.pdf1 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - North West End Tower 2 - Mar-25 (1).pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Signed Copy_ North West End T2_ As on 31-03-25.pdf22 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 North Westen Tower 2 signed.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: North Westend Tower 2 dt 29 04 2025.pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-North Westend T2.pdf19 Mar 2025
Layout approvalFile: Sheet 2-Ground floor.pdf18 Mar 2025
Copy of Layout Approval (in case of layout)File: Sheet 2-Ground floor.pdf18 Mar 2025
Other - TechnicalFile: Declaration for Multipurpose hall.pdf18 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration about land cost.pdf11 Mar 2025
Other - TechnicalFile: Declaration for Multipurpose hall.pdf11 Mar 2025
Layout approvalFile: PLAN FINAL_compressed.pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: PLAN FINAL_compressed.pdf5 Mar 2025
Declaration in FORM BFile: REVISED FORM B.pdf5 Mar 2025
Declaration about Commencement CertificateFile: CC DECLARATION REVISED.pdf5 Mar 2025
Other - TechnicalFile: Declaration-03-03-2025-North Westend Tower 2 (1).pdf5 Mar 2025
Other - TechnicalFile: DD ACK.pdf5 Mar 2025
Other - TechnicalFile: DD.pdf5 Mar 2025
Other - TechnicalFile: REVISED ARCHITECT LETTER.pdf5 Mar 2025
Other - TechnicalFile: OTHER TECHNICAL.pdf5 Mar 2025
Other - TechnicalFile: Additional Government Fees.pdf4 Mar 2025
Details of encumbrances concerned to FinanceFile: Finance-Encumbrance Certificate.pdf12 Feb 2025
Details of encumbrances concerned to FinanceFile: Legal - Non Encumbrance Certificate.pdf12 Feb 2025
Other - LegalFile: Disclosure note.pdf12 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Promoter Declaration for designated Bank account.pdf12 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A-Bank Declaration-Promoter and Span.pdf12 Feb 2025
Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter.pdf12 Feb 2025
Details of encumbrances concerned to LegalFile: Finance-Encumbrance Certificate.pdf12 Feb 2025
Details of encumbrances concerned to LegalFile: Legal - Non Encumbrance Certificate.pdf12 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estae Org.pdf12 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estae Organisation.pdf12 Feb 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Declaration for designated Bank account Form B.pdf12 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured-insecured.pdf12 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: CA Disclosure of secured-insecured.pdf12 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - North Westend Tower 2.pdf6 Jan 2025
Copy of the legal title reportFile: Title Certificate - North Westend Tower 2.pdf20 Dec 2024
Proforma of Allotment letterFile: AL.pdf17 Dec 2024
Other - LegalFile: 7-12 of 237.pdf17 Dec 2024
Deviation Report with respect to model copy of AgreementFile: Deviation report of Agreement.pdf17 Dec 2024
Proforma of Agreement for saleFile: Model AFS.pdf17 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: HDFC Bank Letter.pdf17 Dec 2024
Building plan approvalFile: 2.pdf13 Dec 2024
Building plan approvalFile: 3.pdf13 Dec 2024
Building plan approvalFile: 4.pdf13 Dec 2024
Building plan approvalFile: 5.pdf13 Dec 2024
Building plan approvalFile: 6.pdf13 Dec 2024
Building plan approvalFile: 7.pdf13 Dec 2024
Building plan approvalFile: 8.pdf13 Dec 2024

Promoter's earlier projects14

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise5 not delivered by the promised date7 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
JP CONNECT-MIRAROADPC1330002502082VINAY NAGAR, Thane624Jan 2026OngoingDec 2032Not due yet
The Palace Tower AP51700078483VINAY NAGAR, Thane567Dec 2024OngoingDec 2031Not due yet
Codename StarLifeP51700054275Bhayander East, Thane1,539Jan 2024OngoingDec 2031Not due yet
North Westend Tower 1P51700053522Bhayander, Thane865Nov 2023OngoingDec 2029Not due yet
The Palace Tower CP51700033431Vinay Nagar, Thane637Feb 2022OngoingDec 2028Not due yet
The Palace Tower BP51700033430Vinay Nagar, Thane942Feb 2022OngoingDec 2028Not due yet
JP North AvivaP51700023940Vinay Nagar, Thane-Jan 2020Certificate SignedDec 2026Not due yet
JP North Imperia - Tower 2P51700019783Near Vinay Nagar, Thane-Mar 2019CompletedDec 2025Dec 2025
JP North Imperia - Tower 1P51700019613Near Vinay Nagar, Thane-Feb 2019CompletedDec 2025Dec 2025
JP North EuphoriaP51700016290Vinaynagar, Thane-May 2018Certificate SignedDec 2025Not delivered
JP North AlexaP51700016736near Vinay Nagar, Thane-Jun 2018Certificate SignedDec 2025Not delivered
JP North ElaraP51700007001Vinaynagar, Thane-Aug 2017Certificate SignedJun 2022Not delivered
JP North EstellaP51700008916Vinaynagar, Thane-Aug 2017Certificate SignedDec 2021Not delivered
JP North AtriaP51700004117Vinaynagar, Thane-Aug 2017Certificate SignedDec 2021Not delivered

How this compares with Thane

22%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 4 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep North Westend Tower 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHAYANDER7,600+ in Thane

Builder: JP Infra Realty Private Limited

JP Infra Realty Private Limited has 17 registrations on MahaRERA, including JP North Estella and JP North Atria. Its filings disclose 15 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if North Westend Tower 2 is delayed beyond 30 Apr 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of North Westend Tower 2?

The registered promoter entity is JP Infra Realty Private Limited, a company as per the filing. Its CIN U45200MH2010PTC206022 and GSTIN 27AAOCS9607A1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in North Westend Tower 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for North Westend Tower 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at North Westend Tower 2?

The professionals named in the filing: Architect: Rajesh Khandeparkar of M/s. Urbdes; Architect: URBDES; Engineer: Vijay Joshi; Engineer: AVP STRUCTURAL CONSULTANTS; Chartered Accountant: CAS & CO; Chartered Accountant: SGCO & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in North Westend Tower 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About North Westend Tower 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save North Westend Tower 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.