North Westend Tower 1
By JP Infra Realty Private Limited
RG-MH-06786 · RERA P51700053522 · Last updated on MahaRERA portal: 14 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 4 months
- 1 extension taken
- Rs 150.00 crore secured on the land, in favour of RBL BANK LIMITED
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
North Westend Tower 1 is a Others project by JP Infra Realty Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700053522 on 8 Nov 2023. Possession is promised by 30 Apr 2030. The completion date has moved by 4 months from the original filing. 257 of the 865 units on this registration are recorded sold or booked, and 16 of 44 construction stages are filed complete.
At a glance
Project
- NameNorth Westend Tower 1
- TypeOthers
- Location
- Bhayander West
- Bhayander
- BHAYANDAR
- Thane
- 401101
- Pincode401101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700053522
- ReraGenie IDRG-MH-06786
Builder
- NameJP Infra Realty Private Limited
- Entity typeCompany
- CINU45200MH2010PTC206022
- GSTIN27AAOCS9607A1Z7
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- DirectorsSHUBHAM VIJAYKUMAR JAIN, ABHISHEK CHHAGANLAL KHETAN
- Other registrations16 more →
- Completed8 of 17
- Declared earlier projects15 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on8 Nov 2023
- Promised completion30 Apr 2030
- Revised completionRevised to 30 Apr 2030 (originally 31 Dec 2029)
- Buildings4 building records
- Documents filed153 files
Current status
Figures as on 14 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing 1A | NA | 38 | 37 | 237 | 0 | 237 |
| Wing 1B | NA | 38 | 37 | 227 | 0 | 227 |
| Wing 1C | NA | 38 | 37 | 201 | 0 | 201 |
| Commercial | NA | 6 | 6 | 0 | 200 | 200 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 35%.
Wing 1A40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 35% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 9% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing 1B40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 35% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 9% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing 1C40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 35% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 9% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Commercial40%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 35% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 9% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed574
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing 1A | 164 | 164 |
| Wing 1B | 135 | 135 |
| Wing 1C | 119 | 119 |
| Commercial | 156 | 156 |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Span Venture | BHAYANDAR | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing 1A | NA | Rs 88.26 cr | Rs 18.85 cr |
| Wing 1B | NA | Rs 88.26 cr | Rs 18.85 cr |
| Wing 1C | NA | Rs 88.26 cr | Rs 18.85 cr |
| Commercial | NA | Rs 88.26 cr | Rs 18.85 cr |
| - | NA | Rs 7.96 cr | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | URBDES |
| Engineer | AVP STRUCTURAL CONSULTANTS |
| Engineer | VIJAY JOSHI |
| Chartered Accountant | CAS & CO |
| Chartered Accountant | SGCO & CO LLP |
| Chartered Accountant | SGCO & Co. LLP |
| Partner | Role in project |
|---|---|
| JP Infra Realty Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Jun 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2030
Documents filed153
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 153 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_JUNE 2026_ North Westend Tower 1.pdf | 14 Aug 2026 |
| Withdrawal Update Form 2File: Form 2_JUNE 2026_ North Westend Tower 1.pdf | 14 Aug 2026 |
| Withdrawal Update Form 3File: Form 3_JUNE 2026_ North Westend Tower 1.pdf | 14 Aug 2026 |
| Building plan approvalFile: LAYOUT APPROVAL 1.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-2.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-3.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-4.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-5.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-6.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-7.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-8.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-9.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-10.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-11.pdf | 10 Jun 2026 |
| Building plan approvalFile: BUILDING PLANS-12.pdf | 10 Jun 2026 |
| Building plan approvalFile: 1 LAYOUT PLANS 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 2 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 3 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 4 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 5 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 6 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 7 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 8 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 9 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Building plan approvalFile: 10 BUILDING PLAN 10-12-2024.pdf | 10 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 NWT 1 31032026.pdf | 15 May 2026 |
| Withdrawal Update Form 2File: Form 2 NWE T1 31032026.pdf | 15 May 2026 |
| Withdrawal Update Form 3File: Form 3 North Westend Tower 1 31032026.pdf | 15 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A NWT 1.pdf | 15 May 2026 |
| Withdrawal Update Form 1File: Form 1- NWT 1.pdf | 22 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Signed Copy_ NWE T1_ As on 31-12-25.pdf | 22 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 North Westend Tower1 31122025.pdf | 22 Jan 2026 |
| Withdrawal Update Form 1File: Form 1- North Westend T1 30092025.pdf | 25 Nov 2025 |
| Withdrawal Update Form 2File: Form 2_Signed Copy_North West End T1_ As on 30-09-25.pdf | 25 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - North Westend Tower 1 - 30092025.pdf | 25 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A_Signed Copy_NWE T1_FY 24-25.pdf | 9 Oct 2025 |
| Form 5 (FY 2024-2025)File: RERA Form 5 - North West End Tower 1 March 25.pdf | 29 Sep 2025 |
| Withdrawal Update Form 1File: FORM 1.pdf | 6 Sep 2025 |
| Withdrawal Update Form 2File: FORM 2.pdf | 6 Sep 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 6 Sep 2025 |
| Withdrawal Update Form 1File: FORM 1.pdf | 1 Aug 2025 |
| Withdrawal Update Form 2File: Form 2-North Westend Tower 1-March 2024.pdf | 1 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 North Westend Tower 1 march 2025.pdf | 1 Aug 2025 |
| Form 1File: Form 1.pdf | 17 Jul 2025 |
| Form 2File: Form 2.pdf | 17 Jul 2025 |
| Form 3File: Form 3 North Westend Tower 1 march 2025.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold-North west 1.pdf | 17 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 North Westend Tower 1 march 2025.pdf | 30 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31122024.pdf | 6 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_North Westend Tower 1 as on 31-12-24.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 North Westend Tower 1 30092024.pdf | 23 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-North Westend-Tower 1-Dec 2024.pdf | 15 Feb 2025 |
| Layout approvalFile: 1.pdf | 21 Dec 2024 |
| Building plan approvalFile: 2.pdf | 21 Dec 2024 |
| Building plan approvalFile: 3.pdf | 21 Dec 2024 |
| Building plan approvalFile: 4.pdf | 21 Dec 2024 |
| Building plan approvalFile: 5.pdf | 21 Dec 2024 |
| Building plan approvalFile: 6.pdf | 21 Dec 2024 |
| Building plan approvalFile: 7.pdf | 21 Dec 2024 |
| Building plan approvalFile: 8.pdf | 21 Dec 2024 |
| Building plan approvalFile: 9.pdf | 21 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 21 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: IOD-CC Letter.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 10.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 9.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 21 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 21 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 - North West End March 24.pdf | 7 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Northwestend Tower 1 - Sept 24.pdf | 29 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - North Westend - Tower 1 - June 2024.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - North Westend - June 2024.pdf | 23 Oct 2024 |
| Building plan approvalFile: Building plan part 1.pdf | 19 Oct 2024 |
| Building plan approvalFile: Building plan part 2.pdf | 19 Oct 2024 |
| Building plan approvalFile: Building plan part 3.pdf | 19 Oct 2024 |
| Building plan approvalFile: Building plan part 4.pdf | 19 Oct 2024 |
Promoter's earlier projects14
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| JP CONNECT-MIRAROADPC1330002502082 | VINAY NAGAR, Thane | 624 | Jan 2026 | Ongoing | Dec 2032 | Not due yet |
| The Palace Tower AP51700078483 | VINAY NAGAR, Thane | 567 | Dec 2024 | Ongoing | Dec 2031 | Not due yet |
| North Westend Tower 2P51700079721 | BHAYANDER, Thane | 308 | Mar 2025 | Ongoing | Dec 2031 | Not due yet |
| Codename StarLifeP51700054275 | Bhayander East, Thane | 1,539 | Jan 2024 | Ongoing | Dec 2031 | Not due yet |
| The Palace Tower CP51700033431 | Vinay Nagar, Thane | 637 | Feb 2022 | Ongoing | Dec 2028 | Not due yet |
| The Palace Tower BP51700033430 | Vinay Nagar, Thane | 942 | Feb 2022 | Ongoing | Dec 2028 | Not due yet |
| JP North AvivaP51700023940 | Vinay Nagar, Thane | - | Jan 2020 | Certificate Signed | Dec 2026 | Not due yet |
| JP North Imperia - Tower 2P51700019783 | Near Vinay Nagar, Thane | - | Mar 2019 | Completed | Dec 2025 | Dec 2025 |
| JP North Imperia - Tower 1P51700019613 | Near Vinay Nagar, Thane | - | Feb 2019 | Completed | Dec 2025 | Dec 2025 |
| JP North EuphoriaP51700016290 | Vinaynagar, Thane | - | May 2018 | Certificate Signed | Dec 2025 | Not delivered |
| JP North AlexaP51700016736 | near Vinay Nagar, Thane | - | Jun 2018 | Certificate Signed | Dec 2025 | Not delivered |
| JP North ElaraP51700007001 | Vinaynagar, Thane | - | Aug 2017 | Certificate Signed | Jun 2022 | Not delivered |
| JP North EstellaP51700008916 | Vinaynagar, Thane | - | Aug 2017 | Certificate Signed | Dec 2021 | Not delivered |
| JP North AtriaP51700004117 | Vinaynagar, Thane | - | Aug 2017 | Certificate Signed | Dec 2021 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 16 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 153 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep North Westend Tower 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhayander7,600+ in Thane
Filed coordinates, straight-line distance. 137 registered projects within 2 km.
MAN MANDIR
TRITONIA BUILDCON AND INFRA PRIVATE LIMITE
North Westend Tower 2
JP Infra Realty Private Limited
WINDERMERE TOWER A
A G SUPERSTRUCTURES PRIVATE LIMITED
WINDERMERE TOWER B
A G SUPERSTRUCTURES PVT LTD
SKYLINE D
M/s Sai Shakti Creation
SKYLINE WING - C
SHRI RATNARAJ INFRA LLP
See every Thane project, with the district possession charts
Builder: JP Infra Realty Private Limited
JP Infra Realty Private Limited has 17 registrations on MahaRERA, including JP North Estella and JP North Atria. Its filings disclose 15 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if North Westend Tower 1 is delayed beyond 30 Apr 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of North Westend Tower 1?
The registered promoter entity is JP Infra Realty Private Limited, a company as per the filing. Its CIN U45200MH2010PTC206022 and GSTIN 27AAOCS9607A1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in North Westend Tower 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for North Westend Tower 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at North Westend Tower 1?
The professionals named in the filing: Architect: URBDES; Engineer: AVP STRUCTURAL CONSULTANTS; Engineer: VIJAY JOSHI; Chartered Accountant: CAS & CO; Chartered Accountant: SGCO & CO LLP; Chartered Accountant: SGCO & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in North Westend Tower 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback