RG-MH-29255 · RERA P52800028056 · Last updated on MahaRERA portal: 11 Feb 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 37 other registrations.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Mango Holiday Village, Guhagar - Bungalow No 3 is a Residential / Group Housing project by Samir Shrinivas Kale in Ratnagiri, Maharashtra, registered with MahaRERA as P52800028056 on 27 Jan 2021. The registration is recorded completed; possession was promised by 30 Nov 2022.
At a glance
Project
- NameMango Holiday Village, Guhagar - Bungalow No 3
- TypeResidential / Group Housing
- Location
- Kirtanwadi Road
- Opposite Government Rest house
- Kirtanwadi Tarf Guhagar
- Guhagar
- Ratnagiri
- 415703
- Pincode415703
- RERA no.P52800028056
- ReraGenie IDRG-MH-29255
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jan 2021
- Promised completion30 Nov 2022
- Revised completionNone
- Buildings1 building record
- Documents filed17 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Bungalow No 3 | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
Bungalow No 3: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 70% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjay Kulkarni |
| Engineer | Manoj Joshi |
| Chartered Accountant | Kamdar Desai and Patel Chartered Accountants |
| Partner | Role in project |
|---|---|
| Samir Shrinivas Kale | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jan 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jan 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jan 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Jan 2022
Documents filed17
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 B No 3.pdf | 11 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory B No 3.pdf | 23 Feb 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Bungalow No 3.pdf | 9 Feb 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Bungalow No 3.pdf | 18 Jan 2022 |
| Layout approvalFile: Devlop Plan 12122019 Pg 1.PDF | 18 Jan 2021 |
| Layout approvalFile: Devlop Plan 12122019 Pg 2.PDF | 18 Jan 2021 |
| Building plan approvalFile: MHVG Devlop Order 12122019.pdf | 18 Jan 2021 |
| PAN CardFile: Samir PAN .pdf | 18 Jan 2021 |
| Copy of the legal title reportFile: Mango Title Report.pdf | 18 Jan 2021 |
| Details of encumbrancesFile: B No 3 - Encumbarance Letter.pdf | 18 Jan 2021 |
| Copy of Layout Approval (in case of layout)File: Devlop Plan 12122019 Pg 1.PDF | 18 Jan 2021 |
| Copy of Layout Approval (in case of layout)File: Devlop Plan 12122019 Pg 2.PDF | 18 Jan 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: MHVG Devlop Order 12122019.pdf | 18 Jan 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: MHVG Devlop Order 12122019.pdf | 18 Jan 2021 |
| Declaration in FORM BFile: Bungalow No 3 - Form B.pdf | 18 Jan 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Bungalow No 3 - CA Cert.pdf | 18 Jan 2021 |
| Proforma of Allotment letterFile: Bungalow No 3- Agreement Draft.pdf | 18 Jan 2021 |
Promoter's earlier projects35
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Mango Lakeview GuhagarP52800054932 | Guhagar, Ratnagiri | 24 | Feb 2024 | Ongoing | Sep 2029 | Not due yet |
| MHVG Bungalow No 86P52800079696 | Kirtanwadi, Ratnagiri | 1 | Mar 2025 | Ongoing | Sep 2027 | Not due yet |
| MHVG Bungalow No 105P52800079596 | Kirtanwadi, Ratnagiri | 1 | Mar 2025 | Ongoing | Aug 2027 | Not due yet |
| MHVG Bungalow No 91P52800079665 | Kirtanwadi, Ratnagiri | 1 | Mar 2025 | Ongoing | Jun 2027 | Not due yet |
| Mango Lakefront Paradise Guhagar Bungalow No 38P52800077206 | Kondwadi, Ratnagiri | 1 | Jul 2024 | Ongoing | Nov 2026 | Not due yet |
| Mango Holiday Village Guhagar Bungalow No 109P52800066569 | Kirtanwadi, Ratnagiri | 1 | Jun 2024 | Completed | Oct 2026 | Mar 2025 |
| Mango Holiday Village Guhagar Bungalow No 101P52800056232 | Kirtanwadi, Ratnagiri | - | May 2024 | Completed | Aug 2026 | Mar 2025 |
| Mango Holiday Village Guhagar Bungalow No 104P52800052815 | Kirtanwadi, Ratnagiri | - | Oct 2023 | Certificate Signed | Feb 2026 | Nov 2024 |
| Mango Holiday Village Guhagar Bungalow No 107P52800052799 | Kirtanwadi, Ratnagiri | 1 | Oct 2023 | Completed | Jan 2026 | Feb 2025 |
| Mango Holiday Village Guhagar Bungalow No 108P52800051905 | Kirtanwadi, Ratnagiri | - | Jul 2023 | Completed | Dec 2025 | Nov 2024 |
| Mango Holiday Village Guhagar Bungalow No 90P52800051906 | Kirtanwadi, Ratnagiri | - | Jul 2023 | Completed | Nov 2025 | Nov 2024 |
| Mango Holiday Village Guhagar Bungalow No 92P52800050804 | Kirtanwadi, Ratnagiri | - | May 2023 | Completed | Sep 2025 | Feb 2024 |
| Harikunj EnclaveP51700047799 | Brahman Society, Naupada, Thane | 29 | Nov 2022 | Ongoing | Aug 2025 | Not delivered |
| Mango Holiday Village Guhagar Bungalow No 56P52800049406 | Kirtanwadi, Ratnagiri | - | Feb 2023 | Completed | Dec 2024 | Feb 2024 |
| Mango Holiday Village Guhagar Bungalow No 87P52800045443 | Kirtanwadi, Ratnagiri | - | May 2022 | Completed | May 2024 | Apr 2023 |
| Mango Holiday Village Guhagar Bungalow No 96P52800033522 | Kirtanwadi, Ratnagiri | - | Feb 2022 | Completed | Mar 2024 | Apr 2023 |
| Mango Holiday Village Guhagar Bungalow No 88P52800033586 | Kirtanwadi, Ratnagiri | - | Mar 2022 | Completed | Mar 2024 | Apr 2023 |
| Mango Holiday Village Guhagar Bungalow No 106P52800034745 | Kirtanwadi, Ratnagiri | - | Apr 2022 | Completed | Mar 2024 | Apr 2023 |
| Mango Holiday Village Guhagar Bungalow No 100P52800034054 | Kirtanwadi, Ratnagiri | - | Mar 2022 | Completed | Mar 2024 | Apr 2023 |
| Pranav EnclaveP51700024548 | Naupada, Hindu Colony, Thane | - | Feb 2020 | Completed | Mar 2024 | Mar 2022 |
| Mango Holiday Village Guhagar Bungalow No 95P52800032945 | Kirtanwadi, Ratnagiri | - | Feb 2022 | Completed | Nov 2023 | Apr 2023 |
| Mango Holiday Village Guhagar - Bungalow No 94P52800032054 | Kirtanwadi, Ratnagiri | - | Dec 2021 | Completed | Nov 2023 | Apr 2023 |
| Mango Holiday Village Guhagar - Bungalow No 27P52800031199 | Kirtanwadi, Ratnagiri | - | Oct 2021 | Completed | Oct 2023 | Apr 2023 |
| Mango Holiday Village Guhagar - Bungalow No 98P52800028597 | Kirtanwadi, Ratnagiri | - | Mar 2021 | Completed | Jun 2023 | Dec 2021 |
| Mango Holiday Village Guhagar - Bungalow No 2P52800028581 | Kirtanwadi, Ratnagiri | - | Mar 2021 | Completed | Jun 2023 | Jul 2022 |
| Mango Holiday Village Guhagar - Bungalow No 102P52800030532 | Kirtanwadi, Ratnagiri | - | Aug 2021 | Completed | May 2023 | Jul 2022 |
| Mango Holiday Village Guhagar - Bungalow No 99P52800029127 | Kirtanwadi, Ratnagiri | - | Apr 2021 | Completed | Dec 2022 | Apr 2022 |
| Mango Holiday Village Guhagar - Bungalow No 97P52800029172 | Kirtanwadi, Ratnagiri | - | May 2021 | Completed | Dec 2022 | Apr 2022 |
| Mango Holiday Village Guhagar - Bungalow No 41P52800029170 | Kirtanwadi, Ratnagiri | - | May 2021 | Completed | Dec 2022 | Apr 2022 |
| Mango Holiday Village, Guhagar - Bungalow No 6P52800024075 | Kirtanwadi, Ratnagiri | - | Jan 2020 | Completed | Dec 2022 | Feb 2021 |
| Mango Holiday Village, Guhagar - Bungalow No 54P52800021888 | Kirtanwadi, Ratnagiri | - | Aug 2019 | Completed | Aug 2022 | Jul 2021 |
| Mango Holiday Village, Guhagar - Bungalow No 103P52800026667 | Kirtanwadi, Ratnagiri | - | Oct 2020 | Completed | Jun 2022 | Jul 2021 |
| Mango Holiday Village Guhagar Bungalow No 42 and 93P52800020526 | Kirtanwadi, Ratnagiri | - | Apr 2019 | Completed | Apr 2022 | Dec 2020 |
| Mango Holiday Village, Guhagar - Phase 4P52800003399 | Kirtanwadi Tarf Guhagar, Ratnagiri | - | Aug 2017 | Completed | Jan 2021Registered original: Jan 2020 | Feb 2019 |
| Mango Holiday Village Guhagar | Kirtanwadi Road Opp Government Rest House Guhagar Dist Ratnagiri 415703 | 62 | - | Completed | Mar 2017 | Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 37 other registrations, which the RERA portal never shows together
- All 17 filed documents as one ZIP, foldered, with a manifest
Keep Mango Holiday Village, Guhagar - Bungalow No on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Opposite Government Rest house1,100+ in Ratnagiri
Mandke Lighthouse
Mandke and Mandke Infrastructure Pvt. Ltd.
EKAANT FOREST HOMES
AAKANKSHA AJAY SALVI
KKSHITIJ
MARVEL REALTY
Konkan Bliss Residences
Vaishali Vikrant Vaidya
Mango Lakefront Paradise Guhagar
Samir Shrinivas Kale
SIDDHAKALA SWAPNAPURTI
Nitin Gopal Bendal
See every Ratnagiri project, with the district possession charts
Builder: Samir Shrinivas Kale
Samir Shrinivas Kale has 38 registrations on MahaRERA, including Mango Holiday Village, Guhagar - Phase 4 and Mango Heritage. Its filings disclose 36 earlier MahaRERA projects: declares 30 of 30 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if Mango Holiday Village, Guhagar - Bungalow No 3 is delayed beyond 30 Nov 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Mango Holiday Village, Guhagar - Bungalow No 3?
The registered promoter entity is Samir Shrinivas Kale, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Mango Holiday Village, Guhagar - Bungalow No 3?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Mango Holiday Village, Guhagar - Bungalow No 3?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Mango Holiday Village, Guhagar - Bungalow No 3?
The professionals named in the filing: Architect: Sanjay Kulkarni; Engineer: Manoj Joshi; Chartered Accountant: Kamdar Desai and Patel Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Mango Holiday Village, Guhagar - Bungalow No 3?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback