Home / Browse projects / Pune, Maharashtra / Life Republic Sector R35/35thAvenue Harmony Residency

Registered Litigation declared Residential / Group Housing project

Life Republic Sector R35/35thAvenue Harmony Residency

By KOLTE-PATIL DEVELOPERS LIMITED

RG-MH-31252 · RERA P52100079586 · Last updated on MahaRERA portal: 19 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 13 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
22 of 55Construction stages doneacross 5 buildings; furthest along: Installation of Lifts, 95%
462 of 472Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

Life Republic Sector R35/35thAvenue Harmony Residency is a Residential / Group Housing project by KOLTE-PATIL DEVELOPERS LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100079586 on 17 Mar 2025. Possession is promised by 31 Dec 2027. 10 of the 472 units on this registration are recorded sold or booked, and 22 of 55 construction stages are filed complete.

At a glance

Project

  • NameLife Republic Sector R35/35thAvenue Harmony Residency
  • TypeResidential / Group Housing
  • Location
    • Jambe
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100079586
  • ReraGenie IDRG-MH-31252

Builder

  • NameKOLTE-PATIL DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200PN1991PLC129428
  • GSTIN27AAACK7310G1ZT
  • DirectorYashvardhan Patil
  • Other registrations63 more →
  • Completed14 of 64
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

this monthRegisteredMar 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Mar 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed99 files

Current status

2%10 of 472 units booked
72.7%Work done, per cost certificate

Figures as on 19 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building A Wing A1NA9071071
Building A Wing A2NA901250125
Building B Wing B2NA901160116
Building DNA9089089
Building ENA9071071

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 19 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Installation of Lifts, at 95%.

Building A Wing A163%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Building A Wing A252%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Building B Wing B263%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Building D53%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building E47%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 19 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes40%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes35%
Street LightingYes40%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes40%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes35%

Parking filed885

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots885
Closed/Covered495
Open Space390
BuildingClosed/CoveredOpen SpaceTotal
Building A Wing A16373136
Building A Wing A2119112231
Building B Wing B2111104215
Building D13533168
Building E6768135

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,366 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Jul 2025
LandownerVillageDistrict
Milind KoltePune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI23674.44
Proposed, not sanctioned23,674 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchASHOKA GALAXY, PLOT NO 1, GALAXY SOCIETY DHOLE PATIL ROAD,BUNDGARDEN
Estimated costRs 81.45 cr
Cost incurredRs 59.22 cr
Work done72.71%
BuildingWingEstimatedIncurred
-NARs 16.80 crRs 13.95 cr
Building B Wing B2NARs 16.53 crRs 16.53 cr
Building A Wing A2NARs 16.39 crRs 10.74 cr
Building DNARs 14.37 crRs 8.62 cr
Building ENARs 9.07 crRs 4.48 cr
Building A Wing A1NARs 8.29 crRs 4.90 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKolhatkar and Gowaikar
EngineerSanatkumar Patil
EngineerVijay Deshpande
EngineerGaurag Joshi
Chartered AccountantVidhi S Shah & Associates
PartnerRole in project
KOLTE-PATIL DEVELOPERS LIMITED-

Litigation declared2

CaseCourtStatus
372/2022/2022Civil Court PuneArguments
1098/2023/2023Civil Court PuneFiling of Say on Application

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Feb 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 251231_ Details_lLife Republic_R35.pdf19 Apr 2026
Withdrawal Update Form 2File: Form 2 R35 Phase I.pdf19 Apr 2026
Withdrawal Update Form 3File: Signed Form 3 R35 Phase I.pdf19 Apr 2026
Withdrawal Update Form 1File: 251231_ Details_lLife Republic_R35.pdf6 Feb 2026
Withdrawal Update Form 2File: Form 2 R35 Phase I.pdf6 Feb 2026
Withdrawal Update Form 3File: Form 3 R35 Phase I.pdf6 Feb 2026
Withdrawal Update Form 1File: 250930_ Details_lLife Republic_R35.pdf27 Nov 2025
Withdrawal Update Form 2File: Signed Form-2 LR R35 Ph I.pdf27 Nov 2025
Withdrawal Update Form 3File: Form-3 LR R35.pdf27 Nov 2025
Withdrawal Update Form 1File: 250630_ Details_lLife Republic_R35.pdf6 Oct 2025
Withdrawal Update Form 2File: Form-2 R35.pdf6 Oct 2025
Withdrawal Update Form 3File: R35.pdf6 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form-3 LR R35.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 LR R35.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 250331_ Details_lLife Republic_R35_1.pdf18 Apr 2025
Proforma of Allotment letterFile: ilovepdf_merged.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf7 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration- finance V1.pdf7 Mar 2025
Layout approvalFile: 01-27.pdf21 Feb 2025
Copy of Layout Approval (in case of layout)File: 01-27.pdf21 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2_R35.pdf21 Feb 2025
Building plan approvalFile: 02-27 copy.pdf20 Feb 2025
Building plan approvalFile: 03-27 copy.pdf20 Feb 2025
Building plan approvalFile: 04-27 copy.pdf20 Feb 2025
Building plan approvalFile: 05-27.pdf20 Feb 2025
Building plan approvalFile: 06-27.pdf20 Feb 2025
Building plan approvalFile: 07-27.pdf20 Feb 2025
Building plan approvalFile: 08-27.pdf20 Feb 2025
Building plan approvalFile: 09-27.pdf20 Feb 2025
Building plan approvalFile: 13-27.pdf20 Feb 2025
Building plan approvalFile: 14-27.pdf20 Feb 2025
Building plan approvalFile: 15-27.pdf20 Feb 2025
Building plan approvalFile: 16-27.pdf20 Feb 2025
Building plan approvalFile: 20-27.pdf20 Feb 2025
Building plan approvalFile: 21-27.pdf20 Feb 2025
Building plan approvalFile: 22-27.pdf20 Feb 2025
Building plan approvalFile: 23-27.pdf20 Feb 2025
Building plan approvalFile: 24-27.pdf20 Feb 2025
Building plan approvalFile: 25-27.pdf20 Feb 2025
Building plan approvalFile: 26-27.pdf20 Feb 2025
Building plan approvalFile: 27-27.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_ Architect Certificate.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 27-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 26-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 25-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 24-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 23-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 22-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 21-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 20-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 16-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 15-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 13-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 14-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 02-27 copy.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 03-27 copy.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 04-27 copy.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 05-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 06-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 07-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 08-27.pdf20 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: 09-27.pdf20 Feb 2025
Other - LegalFile: POA_Milind Kolte.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-8.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-7.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-6.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-5.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-4.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-3.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-1.pdf20 Feb 2025
Other - LegalFile: 13090_2.pdf20 Feb 2025
Other - LegalFile: 13090_1.pdf20 Feb 2025
Other - LegalFile: 13090_1.pdf20 Feb 2025
Other - LegalFile: Sale Deed Jambe 18562 011222-2.pdf20 Feb 2025
Declaration about Commencement CertificateFile: Declaration - Commencement Certificate.pdf20 Feb 2025
Other - FinanceFile: Declaration for not opening landowners bank account_declarations.pdf20 Feb 2025
Other - TechnicalFile: Name change declaration.pdf20 Feb 2025
Other - TechnicalFile: Self Declaration - Areas.pdf20 Feb 2025
Other - TechnicalFile: SELF DECLARATION - FSI revised.pdf20 Feb 2025
Other - TechnicalFile: Declaration - Two or Multiple Projects.pdf20 Feb 2025

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

13 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
EVARAP51800026949Borivali, Mumbai Suburban-Nov 2020CompletedOct 2024Oct 2024
24K Stargaze - J BuildingP52100027791Bavdhan, Pune-Jan 2021CompletedJun 2024Jun 2024
Western AvenueP52100000917Wakad, Pune-Jul 2017CompletedDec 2023Registered original: Dec 2022Jan 2023
24K StargazeP52100018473Bavdhan, Pune-Nov 2018CompletedMar 2023Mar 2023
Redevelopment of Jai Vijay CHSL - Phase IP51800004446Vile-Parle (East), Mumbai Suburban-Aug 2017CompletedSep 2022Registered original: Sep 2019Sep 2022
24K ATRIAP52100000428Vishal Nagar, Pimple Nilakh, Pune-Jul 2017CompletedDec 2021Dec 2021
STARGAZEP52100009722Bavadhan BK, Pune-Aug 2017CompletedDec 2018Dec 2018
Ivy Estate Umang PremierP52100000655WAGHOLI, Pune-Jul 2017CompletedSep 2018Sep 2018
GLITTERATIP52100006257Pimpri Chinchawad (M Corp.), Pune-Aug 2017CompletedJun 2018Jun 2018
GLITTERATI IIP52100000319Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedApr 2018Registered original: Dec 2017Apr 2018
Redevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase IP51800008272Andheri, Mumbai Suburban-Aug 2017CompletedMar 2018Registered original: Dec 2017Mar 2018
GlitteratiPimple Nilakh Pune - 411014187-CompletedApr 2016Apr 2016
City BayDhole-Patil road Pune-41100127-CompletedApr 2014Apr 2014

How this compares with Pune

2%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Life Republic Sector R35/35thAvenue Harmony on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Jambe13,700+ in Pune

2 kmLife Republic Sector R35Completed 57Lapsed / revoked 17Other 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 127 registered projects within 2 km.

Builder: KOLTE-PATIL DEVELOPERS LIMITED

KOLTE-PATIL DEVELOPERS LIMITED has 64 registrations on MahaRERA, including 24K OPULA and 24K ATRIA. Its filings disclose 14 earlier MahaRERA projects: declares 13 of 14 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Life Republic Sector R35/35thAvenue Harmony Residency is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Life Republic Sector R35/35thAvenue Harmony Residency?

The registered promoter entity is KOLTE-PATIL DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200PN1991PLC129428 and GSTIN 27AAACK7310G1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Life Republic Sector R35/35thAvenue Harmony Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Life Republic Sector R35/35thAvenue Harmony Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Life Republic Sector R35/35thAvenue Harmony Residency?

The professionals named in the filing: Architect: Kolhatkar and Gowaikar; Engineer: Sanatkumar Patil; Engineer: Vijay Deshpande; Engineer: Gaurag Joshi; Chartered Accountant: Vidhi S Shah & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Life Republic Sector R35/35thAvenue Harmony Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Life Republic Sector R35/35thAvenue Harmony Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Life Republic Sector R35/35thAvenue Harmony to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.