Registered Litigation declared Residential / Group Housing project

Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops

By KOLTE-PATIL DEVELOPERS LIMITED

RG-MH-42847 · RERA P52100050599 · Last updated on MahaRERA portal: 28 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 15 cases
  • Rs 223.32 crore secured on the land, in favour of Induslnd Bank Limited
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No complaints on record
  • Completion date never moved
  • Allotment letter follows the model form
  • All 13 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
16 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 95%
85 of 603Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops is a Residential / Group Housing project by KOLTE-PATIL DEVELOPERS LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100050599 on 21 Apr 2023. Possession is promised by 30 Mar 2028. 518 of the 603 units on this registration are recorded sold or booked, and 16 of 44 construction stages are filed complete.

At a glance

Project

  • NameLife Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops
  • TypeResidential / Group Housing
  • Location
    • Hinjewadi Marunji Kasarsai Road
    • Hinjewadi
    • Jambe
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050599
  • ReraGenie IDRG-MH-42847

Builder

  • NameKOLTE-PATIL DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200PN1991PLC129428
  • GSTIN27AAACK7310G1ZT
  • DirectorYashvardhan Patil
  • Other registrations63 more →
  • Completed14 of 64
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects14 →

Key dates

this monthRegisteredApr 2023PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Apr 2023
  • Promised completion30 Mar 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed74 files

Current status

86%518 of 603 units booked
66.0%Work done, per cost certificate

Figures as on 28 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
J BuildingNA23232800280
K BuildingNA232326119280
D BuildingNA2203030
ShopsNA1101313

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 28 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.

J Building70%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
K Building51%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
D Building73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Shops0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes55%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes55%
Water conservation /Rain water harvestingYes45%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes67%
Open ParkingYes0%

Parking filed1218

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,218
Closed/Covered522
Open Space696
BuildingClosed/CoveredOpen SpaceTotal
J Building261348609
K Building261348609

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area14,937 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
Charge in favour ofInduslnd Bank Limited
Secured amountRs 223.32 crore
CERSAI search filedYes
Declared on13 Jul 2025
LandownerVillageDistrict
RAJESH ANIRUDHA PATILPune (M Corp.)Pune
MILIND DIGAMBAR KOLTEPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI41447.92
Proposed, not sanctioned41,448 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 189.42 cr
Cost incurredRs 124.98 cr
Work done65.98%
BuildingWingEstimatedIncurred
-NARs 64.86 crRs 42.34 cr
J BuildingNARs 59.47 crRs 43.30 cr
K BuildingNARs 59.47 crRs 36.55 cr
ShopsNARs 5.62 crRs 2.80 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSPACE DESIGNERS SYNDICATE
EngineerFIROZ SHAIKH
EngineerGaurag Joshi
Chartered AccountantNIKITA BAJAJ
Chartered AccountantCA Vidhi S Shah
PartnerRole in project
KOLTE-PATIL DEVELOPERS LIMITED-

Litigation declared15

CaseCourtStatus
SPL CS NO 265/2013/2013CJJDOngoing
RCS NO 1487/2005/2005CJJDOngoing
SPL CS 2255/2009/2009CJSDOngoing
SPL CS 575/2015/2015CJSDOngoing
SLP C CC NO 9467/2017/2017SUPREME COURTOngoing
SLP C CC NO 9463/2017/2017SUPREME COURTOngoing
421/2016/2016CJSDOngoing
WRIT PETITION NO 11697/2017/2017HIGH COURTOngoing
WRIT PETITION NO 11701/2017/2017HIGH COURTOngoing
WRIT PETITION NO 11702/2017/2017HIGH COURTOngoing
WPST 31252/2017/2017HIGH COURTOngoing
RCS 1689/2021/2021CIVIL COURTOngoing
CIVIL MA 372/2022/2022CIVIL COURTOngoing
WRIT PETITION NO 7264 OF 2022/2022HIGH COURTOngoing
WPST 31252/2017 /2017Civil Judge Junior DivisionOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Mar 2028

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 R16.pdf28 Apr 2026
Withdrawal Update Form 2File: Form 2 R16 JKD.pdf28 Apr 2026
Withdrawal Update Form 3File: Signed form 3 LR R16 JKD.pdf28 Apr 2026
Withdrawal Update Form 1File: 251231_ Details_lLife Republic_R16 J K D SHOPS.pdf6 Feb 2026
Withdrawal Update Form 2File: Form 2 R16 JKD.pdf6 Feb 2026
Withdrawal Update Form 3File: R16 JKD.pdf6 Feb 2026
Withdrawal Update Form 1File: 250630_ Details_lLife Republic_R16 J K D SHOPS.pdf26 Nov 2025
Withdrawal Update Form 1File: 250930_ Details_lLife Republic_R16 J K D SHOPS.pdf26 Nov 2025
Withdrawal Update Form 2File: Form-2 R16JKD.pdf26 Nov 2025
Withdrawal Update Form 2File: Form-2 LR R16JKD.pdf26 Nov 2025
Withdrawal Update Form 3File: R16JKD.pdf26 Nov 2025
Withdrawal Update Form 3File: Form-3 LR R16JKD.pdf26 Nov 2025
Withdrawal Update Form 1File: 250630_ Details_lLife Republic_R16 J K D SHOPS.pdf13 Oct 2025
Withdrawal Update Form 2File: Form-2 R16JKD.pdf13 Oct 2025
Withdrawal Update Form 3File: Form-3 LR R16JKD.pdf13 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 LR R16JKD.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 LR R16JKD.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 250331_ Details_lLife Republic_R16 J K D SHOPS.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 241231_ Details_lLife Republic_R16 J K D SHOPS.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 LR R16JKD.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 LR R16 JKD.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 R16JKD.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240930_ Details_lLife Republic_R16 J K D SHOPS.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: R16 JKD.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240630_ Details_lLife Republic_R16 J K D SHOPS.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 R16JKD.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 R16JKD.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16JKD signed form-2.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - R16 J,K,D.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 240331_ Details_lLife Republic_R16 J K D SHOPS.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16JKD.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R16JKD.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R16 JKD.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R16-JKD_compressed.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R16 - J K D.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LR R16 JKD.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LR R16 J K D.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R16JKD.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: R16JKD.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 rera JKD.pdf18 Apr 2023
Proforma of Agreement for saleFile: 27-03-2023-DRAFT AFS FINAL- R16 J K and D Building and Shops.pdf18 Apr 2023
CERSAI detailsFile: cersai declaration.pdf6 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: other entity disclosure.pdf6 Apr 2023
Other - FinanceFile: cersai declaration.pdf6 Apr 2023
Other - TechnicalFile: Declaration - FSI.pdf6 Apr 2023
Layout approvalFile: Sanction Plan 1 l.pdf4 Apr 2023
Layout approvalFile: Sanction Plan 2 -.pdf4 Apr 2023
Layout approvalFile: Sanction Plan 3.pdf4 Apr 2023
Building plan approvalFile: Sanction Plan 1 l.pdf4 Apr 2023
Building plan approvalFile: Sanction Plan 2 -.pdf4 Apr 2023
Building plan approvalFile: Sanction Plan 3.pdf4 Apr 2023
Building plan approvalFile: Building Plan.pdf4 Apr 2023
Copy of Layout Approval (in case of layout)File: Sanction Plan 1 l.pdf4 Apr 2023
Copy of Layout Approval (in case of layout)File: Sanction Plan 2 -.pdf4 Apr 2023
Copy of Layout Approval (in case of layout)File: Sanction Plan 3.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan 1 l.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan 2 -.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan 3.pdf4 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf4 Apr 2023
Other - LegalFile: Self Declaration-landowner.pdf4 Apr 2023
Details of encumbrances concerned to FinanceFile: finance encumbrance.pdf6 Mar 2023
Details of encumbrances concerned to FinanceFile: Declaration - Encumbrances of Legal.pdf6 Mar 2023
Details of encumbrances concerned to LegalFile: finance encumbrance.pdf6 Mar 2023
Details of encumbrances concerned to LegalFile: Declaration - Encumbrances of Legal.pdf6 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report - AFS 03032023.pdf6 Mar 2023
PAN CardFile: PAN - KPIT.pdf4 Mar 2023
Copy of the legal title reportFile: LR title revise_compressed.pdf4 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf4 Mar 2023
Declaration about Commencement CertificateFile: Declaration of Commencement Certificate revised.pdf4 Mar 2023
Declaration in FORM BFile: Promoter Form B.pdf4 Mar 2023
CERSAI detailsFile: Cersai File.pdf4 Mar 2023
Proforma of Allotment letterFile: Letter of Allotment.pdf4 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf4 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment Letter.pdf4 Mar 2023

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

13 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
EVARAP51800026949Borivali, Mumbai Suburban-Nov 2020CompletedOct 2024Oct 2024
24K Stargaze - J BuildingP52100027791Bavdhan, Pune-Jan 2021CompletedJun 2024Jun 2024
Western AvenueP52100000917Wakad, Pune-Jul 2017CompletedDec 2023Registered original: Dec 2022Jan 2023
24K StargazeP52100018473Bavdhan, Pune-Nov 2018CompletedMar 2023Mar 2023
Redevelopment of Jai Vijay CHSL - Phase IP51800004446Vile-Parle (East), Mumbai Suburban-Aug 2017CompletedSep 2022Registered original: Sep 2019Sep 2022
24K ATRIAP52100000428Vishal Nagar, Pimple Nilakh, Pune-Jul 2017CompletedDec 2021Dec 2021
STARGAZEP52100009722Bavadhan BK, Pune-Aug 2017CompletedDec 2018Dec 2018
Ivy Estate Umang PremierP52100000655WAGHOLI, Pune-Jul 2017CompletedSep 2018Sep 2018
GLITTERATIP52100006257Pimpri Chinchawad (M Corp.), Pune-Aug 2017CompletedJun 2018Jun 2018
GLITTERATI IIP52100000319Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedApr 2018Registered original: Dec 2017Apr 2018
Redevelopment of Link Palace Premises Co-Op Soc. Ltd. Phase IP51800008272Andheri, Mumbai Suburban-Aug 2017CompletedMar 2018Registered original: Dec 2017Mar 2018
GlitteratiPimple Nilakh Pune - 411014187-CompletedApr 2016Apr 2016
City BayDhole-Patil road Pune-41100127-CompletedApr 2014Apr 2014

How this compares with Pune

86%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Life Republic/Sector R16/16th Avenue/Arezo-J on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjewadi13,700+ in Pune

2 kmLife Republic/Sector R16Completed 122Lapsed / revoked 54Other 74Dot size: filed unitsN

Filed coordinates, straight-line distance. 250 registered projects within 2 km.

Builder: KOLTE-PATIL DEVELOPERS LIMITED

KOLTE-PATIL DEVELOPERS LIMITED has 64 registrations on MahaRERA, including 24K OPULA and 24K ATRIA. Its filings disclose 14 earlier MahaRERA projects: declares 13 of 14 past projects completed on time. Litigation is declared on 14 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops is delayed beyond 30 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops?

The registered promoter entity is KOLTE-PATIL DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200PN1991PLC129428 and GSTIN 27AAACK7310G1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops?

The professionals named in the filing: Architect: SPACE DESIGNERS SYNDICATE; Engineer: FIROZ SHAIKH; Engineer: Gaurag Joshi; Chartered Accountant: NIKITA BAJAJ; Chartered Accountant: CA Vidhi S Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Life Republic/Sector R16/16th Avenue/Arezo-J, K, D Building and Shops. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Life Republic/Sector R16/16th Avenue/Arezo-J to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.